Method for dismantling superstructure of overwater long-span bridge
The invention relates to the technical field of bridge demolition, and discloses an overwater large-span bridge superstructure demolition method which comprises the following steps: aiming at demolition of an old bridge which cannot support a large crane to get on the bridge, two small cranes can be adopted to stand on beam slabs of which the bridge deck pavement is not demolished on the two sides to carry out double-click platform crane demolition on the beam slabs; the influence of the crane on the old bridge is reduced; the middle beam plate is firstly lifted out and placed on the beam plate beside to be dragged and dismantled; and then a guide beam mechanism is arranged at the position of the gap of the beam plate, it is guaranteed that the beam plate can be smoothly dragged until the beam plate is hung on the guide beam mechanism, and the subsequently-dismounted beam plate is placed on the guide beam mechanism to be conveyed and dismounted. The water large-span bridge superstructure dismantling device is applied to the water large-span bridge superstructure dismantling method, the dismantling device comprises a bridge frame whole body, a hanging mechanism, a guide beam mechanism and a beam plate fixing mechanism, and the bridge frame whole body is composed of beam plates.
本发明涉及桥梁拆除技术领域,公开了一种水上大跨度桥梁上部结构拆除方法,拆除方法包括如下步骤:针对于无法支撑大型吊车上桥的老桥拆除,可采用两台小型吊车站在两侧未拆除桥面铺装的梁板上进行双击台吊拆除梁板,从而减小吊车对老桥的影响;先抬出中间梁板,放置在旁边的梁板上进行拖拉拆除;之后在梁板缺口位置安置导梁机构,保证梁板能顺利拖拽至将梁板吊放在导梁机构上,将后续拆除的梁板放置于导梁机构上进行输送拆除。针对上述步骤提出了一种水上大跨度桥梁上部结构拆除装置,应用于一种水上大跨度桥梁上部结构拆除方法,拆除装置包括桥梁架整体、吊挂机构、导梁机构以及梁板固定机构,桥梁架整体由梁板组成。
Method for dismantling superstructure of overwater long-span bridge
The invention relates to the technical field of bridge demolition, and discloses an overwater large-span bridge superstructure demolition method which comprises the following steps: aiming at demolition of an old bridge which cannot support a large crane to get on the bridge, two small cranes can be adopted to stand on beam slabs of which the bridge deck pavement is not demolished on the two sides to carry out double-click platform crane demolition on the beam slabs; the influence of the crane on the old bridge is reduced; the middle beam plate is firstly lifted out and placed on the beam plate beside to be dragged and dismantled; and then a guide beam mechanism is arranged at the position of the gap of the beam plate, it is guaranteed that the beam plate can be smoothly dragged until the beam plate is hung on the guide beam mechanism, and the subsequently-dismounted beam plate is placed on the guide beam mechanism to be conveyed and dismounted. The water large-span bridge superstructure dismantling device is applied to the water large-span bridge superstructure dismantling method, the dismantling device comprises a bridge frame whole body, a hanging mechanism, a guide beam mechanism and a beam plate fixing mechanism, and the bridge frame whole body is composed of beam plates.
本发明涉及桥梁拆除技术领域,公开了一种水上大跨度桥梁上部结构拆除方法,拆除方法包括如下步骤:针对于无法支撑大型吊车上桥的老桥拆除,可采用两台小型吊车站在两侧未拆除桥面铺装的梁板上进行双击台吊拆除梁板,从而减小吊车对老桥的影响;先抬出中间梁板,放置在旁边的梁板上进行拖拉拆除;之后在梁板缺口位置安置导梁机构,保证梁板能顺利拖拽至将梁板吊放在导梁机构上,将后续拆除的梁板放置于导梁机构上进行输送拆除。针对上述步骤提出了一种水上大跨度桥梁上部结构拆除装置,应用于一种水上大跨度桥梁上部结构拆除方法,拆除装置包括桥梁架整体、吊挂机构、导梁机构以及梁板固定机构,桥梁架整体由梁板组成。
Method for dismantling superstructure of overwater long-span bridge
一种水上大跨度桥梁上部结构拆除方法
WU JINGJIANG (author) / HU LIANCHAO (author) / YANG ZUOJIE (author) / QIAN YUHANG (author) / JUNG WON HOON (author) / SHU PENGFEI (author) / YANG HAO (author) / FENG SHOUNING (author) / WANG YUEQUN (author) / LIU ZHINING (author)
2024-07-19
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
European Patent Office | 2022
|Construction method for dismantling overwater suspended arch bridge
European Patent Office | 2020
|Overwater displacement operation method of overwater large-span hoisting equipment
European Patent Office | 2024
|