Support dismounting construction early warning device and support dismounting construction method based on early warning device
The invention relates to a support dismounting construction early warning device and a support dismounting construction method based on the early warning device, and the method comprises the steps: carrying out the overall construction deployment, and making a construction organization design plan; support dismounting and structural beam and slab cross construction are carried out; a detailed construction demolition operation partition plan is divided through the pre-demolition supporting area supporting structure system; pre-dismantling support construction is conducted, specifically, according to the pre-dismantling support construction zoning plan, the construction sequence of first ring support and second angle support is adopted for a pre-dismantling support area, and cutting construction operation is conducted on a supporting structure in sequence; an early warning device monitors, an early warning measuring device is installed, process fluctuation data is collected in real time, and a monitoring data recording result report is formed; optimizing a support dismounting construction scheme, and adjusting and optimizing the construction scheme in real time in the process; and after support dismantling construction is completed, whether the dismantled support structure meets related safety standards and requirements or not is checked, and completion acceptance is carried out. According to the method, by optimizing the construction scheme and timely early warning measures, the efficiency of support dismantling construction is improved.
本申请涉及一种拆撑施工预警装置及基于预警装置的拆撑施工方法,方法包括,整体施工部署,制定施工组织设计计划;拆撑及结构梁板交叉施工;通过预拆撑区域支撑结构体系划分详细的施工拆除作业分区计划;预拆撑施工,根据预拆撑施工分区计划,对预拆撑区域采用先环撑后角撑的施工顺序,依次进行支撑结构进行切割施工作业;预警装置监测,安装预警测量装置,实时采集过程波动数据,形成监测数据记录成果报告;拆撑施工方案优化,过程中实时调整优化施工方案;在拆撑施工完成后,检查拆除的支撑结构是否符合相关安全标准和要求,进行完工验收。本申请通过优化施工方案和及时的预警措施,提高了拆撑施工的效率。
Support dismounting construction early warning device and support dismounting construction method based on early warning device
The invention relates to a support dismounting construction early warning device and a support dismounting construction method based on the early warning device, and the method comprises the steps: carrying out the overall construction deployment, and making a construction organization design plan; support dismounting and structural beam and slab cross construction are carried out; a detailed construction demolition operation partition plan is divided through the pre-demolition supporting area supporting structure system; pre-dismantling support construction is conducted, specifically, according to the pre-dismantling support construction zoning plan, the construction sequence of first ring support and second angle support is adopted for a pre-dismantling support area, and cutting construction operation is conducted on a supporting structure in sequence; an early warning device monitors, an early warning measuring device is installed, process fluctuation data is collected in real time, and a monitoring data recording result report is formed; optimizing a support dismounting construction scheme, and adjusting and optimizing the construction scheme in real time in the process; and after support dismantling construction is completed, whether the dismantled support structure meets related safety standards and requirements or not is checked, and completion acceptance is carried out. According to the method, by optimizing the construction scheme and timely early warning measures, the efficiency of support dismantling construction is improved.
本申请涉及一种拆撑施工预警装置及基于预警装置的拆撑施工方法,方法包括,整体施工部署,制定施工组织设计计划;拆撑及结构梁板交叉施工;通过预拆撑区域支撑结构体系划分详细的施工拆除作业分区计划;预拆撑施工,根据预拆撑施工分区计划,对预拆撑区域采用先环撑后角撑的施工顺序,依次进行支撑结构进行切割施工作业;预警装置监测,安装预警测量装置,实时采集过程波动数据,形成监测数据记录成果报告;拆撑施工方案优化,过程中实时调整优化施工方案;在拆撑施工完成后,检查拆除的支撑结构是否符合相关安全标准和要求,进行完工验收。本申请通过优化施工方案和及时的预警措施,提高了拆撑施工的效率。
Support dismounting construction early warning device and support dismounting construction method based on early warning device
一种拆撑施工预警装置及基于预警装置的拆撑施工方法
YAN RONGFEI (author) / LI CHUNLIANG (author) / XIA LEI (author) / SHI XIN (author) / HAN HUA (author)
2024-08-02
Patent
Electronic Resource
Chinese
Early-dismounting head and early-dismounting formwork device
European Patent Office | 2020
|Large venue steel structure support dismounting device and construction method
European Patent Office | 2020
|