The invention discloses an underground structure construction method utilizing an existing underground diaphragm wall. The underground structure construction method comprises the steps that the integrity and perpendicularity of the existing underground diaphragm wall are confirmed; a newly-built underground diaphragm wall is constructed, and the foundation pit area is divided into a plurality of small foundation pits through the existing underground diaphragm wall; a first layer of earthwork is excavated for the multiple small foundation pits, and horizontal supports are constructed; excavating a second layer of earthwork and a third layer of earthwork for the plurality of small foundation pits, and constructing horizontal supports; excavating the fourth and fifth layers of earthwork of the middle small foundation pit, and excavating the small foundation pits on the two sides close to the existing underground diaphragm wall in a sloping manner; a middle bottom plate and a middle underground structure of the middle small foundation pit; construction of a middle underground structure is completed; excavating fourth-layer earthwork of the small foundation pits on the two sides, and constructing a fourth horizontal support; excavating the fifth-layer earth of the small foundation pits on the two sides, and constructing bottom plates on the two sides; construction of underground structures on the two sides is completed; an underground structure is formed through the floor slab and the bottom plate. The problem that an existing underground diaphragm wall affects the construction progress of a foundation pit and an underground building can be solved.
本发明公开了一种利用既有地下连续墙的地下结构施工方法,包括步骤:确认既有地下连续墙完整性和垂直度;施工新建地下连续墙,既有地下连续墙将基坑区域分隔成若干小基坑;若干小基坑开挖第一层土方,施工水平支撑;若干个小基坑开挖第二、三层土方,施工水平支撑;中部小基坑第四、五层土方开挖,两侧部小基坑在临近既有地下连续墙侧放坡开挖;中部小基坑中部底板、中部地下结构;完成中部地下结构施工;两侧部小基坑第四层土方开挖,施工第四道水平支撑;两侧部小基坑第五层土方开挖,施工两侧部底板;完成两侧部地下结构施工;贯通楼板和底板形成地下结构。本发明能解决既有地下连续墙影响基坑和地下建筑物施工进度的问题。
Underground structure construction method using existing underground diaphragm wall
The invention discloses an underground structure construction method utilizing an existing underground diaphragm wall. The underground structure construction method comprises the steps that the integrity and perpendicularity of the existing underground diaphragm wall are confirmed; a newly-built underground diaphragm wall is constructed, and the foundation pit area is divided into a plurality of small foundation pits through the existing underground diaphragm wall; a first layer of earthwork is excavated for the multiple small foundation pits, and horizontal supports are constructed; excavating a second layer of earthwork and a third layer of earthwork for the plurality of small foundation pits, and constructing horizontal supports; excavating the fourth and fifth layers of earthwork of the middle small foundation pit, and excavating the small foundation pits on the two sides close to the existing underground diaphragm wall in a sloping manner; a middle bottom plate and a middle underground structure of the middle small foundation pit; construction of a middle underground structure is completed; excavating fourth-layer earthwork of the small foundation pits on the two sides, and constructing a fourth horizontal support; excavating the fifth-layer earth of the small foundation pits on the two sides, and constructing bottom plates on the two sides; construction of underground structures on the two sides is completed; an underground structure is formed through the floor slab and the bottom plate. The problem that an existing underground diaphragm wall affects the construction progress of a foundation pit and an underground building can be solved.
本发明公开了一种利用既有地下连续墙的地下结构施工方法,包括步骤:确认既有地下连续墙完整性和垂直度;施工新建地下连续墙,既有地下连续墙将基坑区域分隔成若干小基坑;若干小基坑开挖第一层土方,施工水平支撑;若干个小基坑开挖第二、三层土方,施工水平支撑;中部小基坑第四、五层土方开挖,两侧部小基坑在临近既有地下连续墙侧放坡开挖;中部小基坑中部底板、中部地下结构;完成中部地下结构施工;两侧部小基坑第四层土方开挖,施工第四道水平支撑;两侧部小基坑第五层土方开挖,施工两侧部底板;完成两侧部地下结构施工;贯通楼板和底板形成地下结构。本发明能解决既有地下连续墙影响基坑和地下建筑物施工进度的问题。
Underground structure construction method using existing underground diaphragm wall
利用既有地下连续墙的地下结构施工方法
ZHOU HUANGSONG (author) / TIAN ZHIYONG (author) / DONG RUI (author) / YANG JINLONG (author) / ZHANG ZHENGHONG (author) / HUANG YONGFEI (author) / HE YAMIN (author) / XU WENFEI (author) / ZHU JUN (author) / ZHAO ZIWEI (author)
2024-08-16
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of underground diaphragm wall in existing underground structure
European Patent Office | 2023
|Foundation pit construction method using existing underground diaphragm wall
European Patent Office | 2024
|European Patent Office | 2021
|Construction method of underground diaphragm wall and underground diaphragm wall
European Patent Office | 2020
|Underground diaphragm wall joint and construction method of underground diaphragm wall
European Patent Office | 2023
|