Design and construction method of flower basket type steel structure between buildings
The invention discloses an inter-building flower basket type steel structure design and construction method. The method comprises the following steps that 1, a steel frame structure on a building structure is positioned and installed; 2, the flower basket type steel structure is divided into four truss units according to the four faces of the flower basket type steel structure, and each truss unit is divided into an upper module truss and a lower module truss; 3, ground hardening treatment is carried out, and the embedded parts are positioned and installed; 4, the truss units are assembled on the ground, and the single-pipe supports and the lower module truss are welded and fixed; 5, the truss units on the side connected with the building structure are installed firstly, then the truss units on the other two sides are installed, and when each truss unit is hoisted, lower module trusses are integrally hoisted firstly; positioning and mounting a supporting jig frame and hoisting an upper module truss section by section; and 6, the supporting jig frame is unloaded in a graded mode, and then the single-pipe support is dismantled. A new structural form is provided for the channel structure between the buildings, the appearance is attractive, the site is wider, and personnel flow is better facilitated.
本发明公开了一种建筑间花篮式钢结构设计及施工方法,包括以下步骤:步骤1:建筑结构上钢架结构定位安装;步骤2:将花篮式钢结构按照其四个面分为四个桁架单元,每个桁架单元分为上下两个模块桁架;步骤3:地面硬化处理,并定位安装预埋件;步骤4:桁架单元地面拼装,并将单管支撑与下部模块桁架焊接固定;步骤5:先进行与建筑结构连接侧的桁架单元安装,后进行另外两侧桁架单元安装,每个桁架单元吊装时,先进行下部模块桁架整体吊装;后进行支撑胎架定位安装以及上部模块桁架分段吊装;步骤6:支撑胎架分级卸载,后拆除单管支撑。本申请为建筑间通道结构提供一种新的结构形式,造型美观、场地更加空广,更加利于人员流动。
Design and construction method of flower basket type steel structure between buildings
The invention discloses an inter-building flower basket type steel structure design and construction method. The method comprises the following steps that 1, a steel frame structure on a building structure is positioned and installed; 2, the flower basket type steel structure is divided into four truss units according to the four faces of the flower basket type steel structure, and each truss unit is divided into an upper module truss and a lower module truss; 3, ground hardening treatment is carried out, and the embedded parts are positioned and installed; 4, the truss units are assembled on the ground, and the single-pipe supports and the lower module truss are welded and fixed; 5, the truss units on the side connected with the building structure are installed firstly, then the truss units on the other two sides are installed, and when each truss unit is hoisted, lower module trusses are integrally hoisted firstly; positioning and mounting a supporting jig frame and hoisting an upper module truss section by section; and 6, the supporting jig frame is unloaded in a graded mode, and then the single-pipe support is dismantled. A new structural form is provided for the channel structure between the buildings, the appearance is attractive, the site is wider, and personnel flow is better facilitated.
本发明公开了一种建筑间花篮式钢结构设计及施工方法,包括以下步骤:步骤1:建筑结构上钢架结构定位安装;步骤2:将花篮式钢结构按照其四个面分为四个桁架单元,每个桁架单元分为上下两个模块桁架;步骤3:地面硬化处理,并定位安装预埋件;步骤4:桁架单元地面拼装,并将单管支撑与下部模块桁架焊接固定;步骤5:先进行与建筑结构连接侧的桁架单元安装,后进行另外两侧桁架单元安装,每个桁架单元吊装时,先进行下部模块桁架整体吊装;后进行支撑胎架定位安装以及上部模块桁架分段吊装;步骤6:支撑胎架分级卸载,后拆除单管支撑。本申请为建筑间通道结构提供一种新的结构形式,造型美观、场地更加空广,更加利于人员流动。
Design and construction method of flower basket type steel structure between buildings
一种建筑间花篮式钢结构设计及施工方法
HAN JUNG-HO (author) / CHONG JINSONG (author) / YUAN SHUAI (author) / HAN MINZHANG (author) / CHEN JUN (author) / HE PAN (author)
2024-08-23
Patent
Electronic Resource
Chinese
Construction method of flower basket type cantilever scaffold
European Patent Office | 2022
|Construction method for flower-basket-shaped support of steel structure water tower
European Patent Office | 2015
|Construction method of fabricated external flower basket type cantilever scaffold
European Patent Office | 2023
|