The aluminum alloy formwork construction method comprises the steps of surveying and setting out, binding of wall and column steel bars, installation of wall and column formworks, installation of beam and plate formworks, binding of beam and plate steel bars, hanging formwork installation, acceptance check of the formworks and the steel bars, concrete pouring and maintenance, dismantling of the wall and column formworks, dismantling of the beam and plate formworks and dismantling of supports and early dismantling heads. Wall and column formwork installation comprises the steps of checking a control line, installing formworks on the two sides, installing back ridges and split bolts, installing inclined struts and conducting correction and rechecking. The installation of the beam formwork and the support comprises the steps of checking a control line, installing a bottom formwork and a support, installing a beam side formwork, installing a back ridge and a split bolt, and checking the axis and the elevation. According to the method, the construction process and key links of aluminum alloy formwork construction are restrained, so that safe construction of the aluminum alloy formwork can be achieved, the safety risk can be reduced, the construction quality of a project main body structure can be guaranteed, the appearance process can be improved, the construction period can be shortened, and good application and popularization value is achieved.
本发明公开了一种铝合金模板施工方法,包括测量放线→墙、柱钢筋绑扎→墙、柱模板安装→梁、板模板安装→梁、板钢筋绑扎→吊模安装→模板、钢筋验收→混凝土浇筑及养护→墙、柱模板拆除→梁、板模板拆除→支架及早拆头拆除;墙、柱模板安装包括:校核控制线→两侧模板安装→背楞及对拉螺栓安装→斜撑安装→校正、复核。梁模板与支架安装包括:校核控制线→安装底模及支撑→安装梁侧模板→安装背楞及对拉螺栓→校核轴线、标高。本发明的方法对铝合金模板施工的施工流程,以及重点环节进行了约束,从而能够实现铝合金模板的安全施工,降低安全风险,可以保证工程主体结构施工质量、提升外观工艺、缩短工期,具有良好的推广应用价值。
The aluminum alloy formwork construction method comprises the steps of surveying and setting out, binding of wall and column steel bars, installation of wall and column formworks, installation of beam and plate formworks, binding of beam and plate steel bars, hanging formwork installation, acceptance check of the formworks and the steel bars, concrete pouring and maintenance, dismantling of the wall and column formworks, dismantling of the beam and plate formworks and dismantling of supports and early dismantling heads. Wall and column formwork installation comprises the steps of checking a control line, installing formworks on the two sides, installing back ridges and split bolts, installing inclined struts and conducting correction and rechecking. The installation of the beam formwork and the support comprises the steps of checking a control line, installing a bottom formwork and a support, installing a beam side formwork, installing a back ridge and a split bolt, and checking the axis and the elevation. According to the method, the construction process and key links of aluminum alloy formwork construction are restrained, so that safe construction of the aluminum alloy formwork can be achieved, the safety risk can be reduced, the construction quality of a project main body structure can be guaranteed, the appearance process can be improved, the construction period can be shortened, and good application and popularization value is achieved.
本发明公开了一种铝合金模板施工方法,包括测量放线→墙、柱钢筋绑扎→墙、柱模板安装→梁、板模板安装→梁、板钢筋绑扎→吊模安装→模板、钢筋验收→混凝土浇筑及养护→墙、柱模板拆除→梁、板模板拆除→支架及早拆头拆除;墙、柱模板安装包括:校核控制线→两侧模板安装→背楞及对拉螺栓安装→斜撑安装→校正、复核。梁模板与支架安装包括:校核控制线→安装底模及支撑→安装梁侧模板→安装背楞及对拉螺栓→校核轴线、标高。本发明的方法对铝合金模板施工的施工流程,以及重点环节进行了约束,从而能够实现铝合金模板的安全施工,降低安全风险,可以保证工程主体结构施工质量、提升外观工艺、缩短工期,具有良好的推广应用价值。
Fabricated aluminum alloy formwork system construction method