Peat soil composite foundation construction method and construction platform
The invention provides a peat soil composite foundation construction method and platform, and the method comprises the steps: S1, cleaning and leveling a construction site, and determining a platform construction region and a cast-in-place pile construction region; s2, a construction platform is built on the platform construction area; s21, constructing a plurality of stumps on the platform construction area; s22, gaps among the multiple stumps are filled with branches, and a first branch layer is formed; s23, gaps among the multiple stumps are filled with clay, a first clay layer is formed above the first branch layer, and the top end of the first clay layer is flush with the top ends of the stumps; s24, a platform body is built above the tree stump and the first clay layer; and S3, a cast-in-place pile is constructed in the cast-in-place pile construction The stumps and branches in the peat soil are fully utilized, the stability of the construction platform is improved, then the pile forming quality of the cast-in-place pile is improved, and the purposes of saving materials, being environmentally friendly and shortening the construction period can be achieved.
本发明提供了一种泥炭土复合地基施工方法及施工平台,其中方法包括S1、清理并整平施工场地,确定平台施工区域和灌注桩施工区域;S2、在平台施工区域上建造施工平台;S21、在平台施工区域上施工多根树桩;S22、在多根树桩的间隙填充树枝,形成第一树枝层;S23、在多根树桩的间隙填充粘土,在第一树枝层上方形成第一粘土层,第一粘土层的顶端与树桩的顶端平齐;S24、在树桩和第一粘土层的上方建造平台主体;S3、在灌注桩施工区域施工灌注桩。本发明充分利用泥炭土内的树桩、树枝,提高施工平台的稳定性,进而提高灌注桩成桩质量,并能达到节约材料、绿色环保、缩短工期的目的。
Peat soil composite foundation construction method and construction platform
The invention provides a peat soil composite foundation construction method and platform, and the method comprises the steps: S1, cleaning and leveling a construction site, and determining a platform construction region and a cast-in-place pile construction region; s2, a construction platform is built on the platform construction area; s21, constructing a plurality of stumps on the platform construction area; s22, gaps among the multiple stumps are filled with branches, and a first branch layer is formed; s23, gaps among the multiple stumps are filled with clay, a first clay layer is formed above the first branch layer, and the top end of the first clay layer is flush with the top ends of the stumps; s24, a platform body is built above the tree stump and the first clay layer; and S3, a cast-in-place pile is constructed in the cast-in-place pile construction The stumps and branches in the peat soil are fully utilized, the stability of the construction platform is improved, then the pile forming quality of the cast-in-place pile is improved, and the purposes of saving materials, being environmentally friendly and shortening the construction period can be achieved.
本发明提供了一种泥炭土复合地基施工方法及施工平台,其中方法包括S1、清理并整平施工场地,确定平台施工区域和灌注桩施工区域;S2、在平台施工区域上建造施工平台;S21、在平台施工区域上施工多根树桩;S22、在多根树桩的间隙填充树枝,形成第一树枝层;S23、在多根树桩的间隙填充粘土,在第一树枝层上方形成第一粘土层,第一粘土层的顶端与树桩的顶端平齐;S24、在树桩和第一粘土层的上方建造平台主体;S3、在灌注桩施工区域施工灌注桩。本发明充分利用泥炭土内的树桩、树枝,提高施工平台的稳定性,进而提高灌注桩成桩质量,并能达到节约材料、绿色环保、缩短工期的目的。
Peat soil composite foundation construction method and construction platform
一种泥炭土复合地基施工方法及施工平台
LIANG JIANYUAN (author) / FENG RONGXIAN (author) / HUANG JING (author) / WANG YONGHONG (author) / ZHONG GAIBING (author) / JIN JUNLIANG (author) / MENG GUOSI (author) / XIE LIYONG (author) / YANG XIN (author) / SUN YANFEI (author)
2024-09-17
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction Treatment Method for Reinforcing Deep Peat Soil Foundation
European Patent Office | 2021
|Construction treatment method for reinforcing deep peat soil foundation
European Patent Office | 2021
|Method for foundation replacement construction of peat soil soft foundation box culvert
European Patent Office | 2020
|Gravel pile construction pile pipe for reinforcing deep peat soil soft foundation
European Patent Office | 2021
|