A platform for research: civil engineering, architecture and urbanism
Municipal drainage pipeline construction method
The invention discloses a municipal drainage pipeline construction method. The municipal drainage pipeline construction method comprises the following steps that S1, a groove is excavated; s2, a pipeline supporting device is arranged in the groove, and a to-be-installed pipeline is placed on the pipeline supporting device; s3, aligning the two adjacent to-be-mounted pipelines by using a pipeline aligning assembly; s4, after the two pipelines are aligned and spliced, the pipeline supporting device and the alignment assembly are moved, the other pipelines are aligned and spliced, after all the pipelines are aligned and spliced, the pipeline supporting device and the alignment assembly are moved out, and soil is backfilled; the pipeline supporting device comprises a base and fixing blocks, the four fixing blocks are distributed in a rectangular array mode, a two-way threaded rod is rotationally installed between two fixing blocks, a guide rod parallel to the two-way threaded rod is fixed between the other two fixing blocks, and the two-way threaded rod and the guide rod are jointly provided with a movable block. Clamping assemblies are arranged at the two ends of each movable block. The efficiency of axis alignment and mutual splicing of the two pipelines is improved.
本申请公开了一种市政排水管道施工方法,包括如下步骤:S1、开挖沟槽;S2、在沟槽内设置管道支撑装置,将待安装的管道放置在管道支撑装置上;S3、使用管道对齐组件对相邻的两个待安装的管道进行对准;S4、两个管道对准拼接后,移动管道支撑装置和对齐组件,对其余管道进行对准和拼接,全部管道均对准拼接后移出管道支撑装置和对齐组件,回填土壤;管道支撑装置包括底座及固定块,固定块设有四个并呈矩形阵列分布,其中两个固定块之间转动安装有双向螺纹杆,另外两个固定块之间固定有与双向螺纹杆平行设置的导向杆,双向螺纹杆与导向杆上共同设置有活动块,每个活动块两端均设置有夹持组件。本申请加快了两个管道轴线对准并相互拼接的效率。
Municipal drainage pipeline construction method
The invention discloses a municipal drainage pipeline construction method. The municipal drainage pipeline construction method comprises the following steps that S1, a groove is excavated; s2, a pipeline supporting device is arranged in the groove, and a to-be-installed pipeline is placed on the pipeline supporting device; s3, aligning the two adjacent to-be-mounted pipelines by using a pipeline aligning assembly; s4, after the two pipelines are aligned and spliced, the pipeline supporting device and the alignment assembly are moved, the other pipelines are aligned and spliced, after all the pipelines are aligned and spliced, the pipeline supporting device and the alignment assembly are moved out, and soil is backfilled; the pipeline supporting device comprises a base and fixing blocks, the four fixing blocks are distributed in a rectangular array mode, a two-way threaded rod is rotationally installed between two fixing blocks, a guide rod parallel to the two-way threaded rod is fixed between the other two fixing blocks, and the two-way threaded rod and the guide rod are jointly provided with a movable block. Clamping assemblies are arranged at the two ends of each movable block. The efficiency of axis alignment and mutual splicing of the two pipelines is improved.
本申请公开了一种市政排水管道施工方法,包括如下步骤:S1、开挖沟槽;S2、在沟槽内设置管道支撑装置,将待安装的管道放置在管道支撑装置上;S3、使用管道对齐组件对相邻的两个待安装的管道进行对准;S4、两个管道对准拼接后,移动管道支撑装置和对齐组件,对其余管道进行对准和拼接,全部管道均对准拼接后移出管道支撑装置和对齐组件,回填土壤;管道支撑装置包括底座及固定块,固定块设有四个并呈矩形阵列分布,其中两个固定块之间转动安装有双向螺纹杆,另外两个固定块之间固定有与双向螺纹杆平行设置的导向杆,双向螺纹杆与导向杆上共同设置有活动块,每个活动块两端均设置有夹持组件。本申请加快了两个管道轴线对准并相互拼接的效率。
Municipal drainage pipeline construction method
一种市政排水管道施工方法
PAN LIMIN (author) / LIN XIAOXIAO (author) / LUO WEI (author) / FAN HAIHUI (author) / LIU JINYAN (author) / SUN XIAOXUE (author) / ZHAO HUIGE (author) / CHEN NINI (author) / YU YONGQI (author) / WANG YANLONG (author)
2024-10-08
Patent
Electronic Resource
Chinese
IPC:
E03F
SEWERS
,
Abwasserkanäle
Municipal drainage pipeline and construction method thereof
European Patent Office | 2021
|