Modular prefabrication and installation method for pipe gallery
The invention provides a modular prefabrication and installation method for a pipe gallery, the whole pipe gallery is divided into a plurality of pipe gallery modules, the installation of a steel structure, a pipeline, electricity and heat preservation of each pipe gallery module is completed in a prefabrication yard, and the installation of the steel structure comprises the steps of prefabrication yard foundation treatment, assembling, sheet forming and framing and installation in place; the step of assembling the door-shaped frames into pieces and framing comprises side piece assembling and door-shaped frame assembling, before assembling, 300 * 300 * 500 concrete buttresses are used as temporary supports to be used for a component assembling platform, the levelness and perpendicularity of component assembling are ensured, the step of mounting in place adopts segmented, piece-by-piece and layered mounting, the door-shaped frames on the two sides of each section of steel structure are mounted in place, then the side piece frames on the two sides are mounted, and the door-shaped frames on the two sides of each section of steel structure are mounted in place. And finally, each layer of cross beams and horizontal supporting components are installed from low to high. The modular design of the pipe gallery is innovatively adopted, the whole pipe gallery is divided into a plurality of pipe gallery modules, all installation is completed in a prefabricating field, and the overall installation efficiency and quality of the pipe gallery are greatly improved.
本发明提供了管廊模块化预制安装方法,将整体管廊分成若干管廊模块,且各管廊模块在预制场完成钢结构、管道、电气、保温的安装,其中,钢结构安装包括预制场基础处理、组对成片成框和安装就位,所述组对成片成框包括侧片组对和门型框组对,组对前使用300*300*500混凝土支墩作为临时支撑用于构件拼装平台,确保构件组对水平度、垂直度,所述安装就位采用分段、分片、分层安装,先将每段钢结构两侧门型框安装就位,然后安装两侧侧片框架,最后由低至高安装每层横梁和水平支撑构件。本发明创新性的采用管廊模块化设计,将整体管廊分成若干管廊模块,在预制场完成全部安装,大幅提升了管廊整体的安装效率和质量。
Modular prefabrication and installation method for pipe gallery
The invention provides a modular prefabrication and installation method for a pipe gallery, the whole pipe gallery is divided into a plurality of pipe gallery modules, the installation of a steel structure, a pipeline, electricity and heat preservation of each pipe gallery module is completed in a prefabrication yard, and the installation of the steel structure comprises the steps of prefabrication yard foundation treatment, assembling, sheet forming and framing and installation in place; the step of assembling the door-shaped frames into pieces and framing comprises side piece assembling and door-shaped frame assembling, before assembling, 300 * 300 * 500 concrete buttresses are used as temporary supports to be used for a component assembling platform, the levelness and perpendicularity of component assembling are ensured, the step of mounting in place adopts segmented, piece-by-piece and layered mounting, the door-shaped frames on the two sides of each section of steel structure are mounted in place, then the side piece frames on the two sides are mounted, and the door-shaped frames on the two sides of each section of steel structure are mounted in place. And finally, each layer of cross beams and horizontal supporting components are installed from low to high. The modular design of the pipe gallery is innovatively adopted, the whole pipe gallery is divided into a plurality of pipe gallery modules, all installation is completed in a prefabricating field, and the overall installation efficiency and quality of the pipe gallery are greatly improved.
本发明提供了管廊模块化预制安装方法,将整体管廊分成若干管廊模块,且各管廊模块在预制场完成钢结构、管道、电气、保温的安装,其中,钢结构安装包括预制场基础处理、组对成片成框和安装就位,所述组对成片成框包括侧片组对和门型框组对,组对前使用300*300*500混凝土支墩作为临时支撑用于构件拼装平台,确保构件组对水平度、垂直度,所述安装就位采用分段、分片、分层安装,先将每段钢结构两侧门型框安装就位,然后安装两侧侧片框架,最后由低至高安装每层横梁和水平支撑构件。本发明创新性的采用管廊模块化设计,将整体管廊分成若干管廊模块,在预制场完成全部安装,大幅提升了管廊整体的安装效率和质量。
Modular prefabrication and installation method for pipe gallery
管廊模块化预制安装方法
XU QINIAN (author) / JIN XIAOHU (author) / WAN ZHONGDANG (author) / ZHAO BAOYONG (author) / WANG WEI (author)
2024-10-22
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Principles of prefabrication in house pipe line installation
Engineering Index Backfile | 1963
|Curb prefabrication and installation construction method
European Patent Office | 2024
|Pipe gallery prefabricated installation construction method
European Patent Office | 2020
|