The invention relates to the technical field of prefabricated pipe pile construction, and discloses a construction device for a concrete pipe pile and a construction method thereof.The construction device comprises a lower moving table, a main clamping device is arranged on the lower moving table, the main clamping device comprises a moving cylinder connected with the lower moving table, and an annular sliding plate is arranged at the bottom of the moving cylinder; a sliding cavity corresponding to the sliding plate is formed in the lower moving table, a connecting plate is arranged at the bottom of the moving cylinder, and the connecting plate is connected with a driving cylinder through a bearing. According to the construction device for the concrete pipe pile and the construction method of the construction device, in the pipe pile clamping process, too large transverse acting force cannot be applied to the pipe pile, the situation that the perpendicularity of the pipe pile is affected in the pipe pile clamping process is avoided, meanwhile, in the pipe pile pressing-in process, the main clamping device can move along with the pipe pile, the perpendicularity of the pipe pile can be conveniently detected, problems can be found in time, and the construction efficiency is improved. And the pressure between one side of the pipe pile and the main clamping device can be prevented from being too large, and the pipe pile is prevented from being damaged.
本申请涉及预制管桩施工技术领域,公开了一种混凝土管桩用施工装置及其施工方法,包括下移动台,下移动台上设有主夹紧器,所述主夹紧器包括与下移动台连接的移动筒,所述移动筒的底部设有环形的滑动板,下移动台上设有与滑动板对应的滑动腔,所述移动筒的底部设有连接板,连接板通过轴承连接有驱动筒。该混凝土管桩用施工装置及其施工方法,在夹紧管桩的过程中,不会对管桩施加过大的横向作用力,避免夹紧管桩的过程中影响管桩垂直度,同时在管桩压入过程中,主夹紧器会随着管桩移动,既便于检测管桩的垂直度,及时发现问题,也能避免管桩的一侧与主夹紧器之间压力过大,避免管桩受损。
Construction device for concrete pipe pile and construction method thereof
The invention relates to the technical field of prefabricated pipe pile construction, and discloses a construction device for a concrete pipe pile and a construction method thereof.The construction device comprises a lower moving table, a main clamping device is arranged on the lower moving table, the main clamping device comprises a moving cylinder connected with the lower moving table, and an annular sliding plate is arranged at the bottom of the moving cylinder; a sliding cavity corresponding to the sliding plate is formed in the lower moving table, a connecting plate is arranged at the bottom of the moving cylinder, and the connecting plate is connected with a driving cylinder through a bearing. According to the construction device for the concrete pipe pile and the construction method of the construction device, in the pipe pile clamping process, too large transverse acting force cannot be applied to the pipe pile, the situation that the perpendicularity of the pipe pile is affected in the pipe pile clamping process is avoided, meanwhile, in the pipe pile pressing-in process, the main clamping device can move along with the pipe pile, the perpendicularity of the pipe pile can be conveniently detected, problems can be found in time, and the construction efficiency is improved. And the pressure between one side of the pipe pile and the main clamping device can be prevented from being too large, and the pipe pile is prevented from being damaged.
本申请涉及预制管桩施工技术领域,公开了一种混凝土管桩用施工装置及其施工方法,包括下移动台,下移动台上设有主夹紧器,所述主夹紧器包括与下移动台连接的移动筒,所述移动筒的底部设有环形的滑动板,下移动台上设有与滑动板对应的滑动腔,所述移动筒的底部设有连接板,连接板通过轴承连接有驱动筒。该混凝土管桩用施工装置及其施工方法,在夹紧管桩的过程中,不会对管桩施加过大的横向作用力,避免夹紧管桩的过程中影响管桩垂直度,同时在管桩压入过程中,主夹紧器会随着管桩移动,既便于检测管桩的垂直度,及时发现问题,也能避免管桩的一侧与主夹紧器之间压力过大,避免管桩受损。
Construction device for concrete pipe pile and construction method thereof
一种混凝土管桩用施工装置及其施工方法
JIANG BO (author) / HONG YONGYU (author) / WU PING (author)
2024-11-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,