Rapid installation system for high-rise unit type curtain wall
The invention discloses a high-rise unit type curtain wall rapid installation system, and relates to the technical field of building curtain wall construction, and the technical scheme is that the high-rise unit type curtain wall rapid installation system comprises a supporting unit, a vertical hoisting unit and a transverse walking unit, and the supporting unit is provided with a first track for the transverse walking unit to walk; the vertical lifting unit comprises a winch, two first transverse supports, a second transverse support, a first steel wire rope, a second steel wire rope, a U-shaped buckle and a fixing plate, the first transverse supports and the second transverse support are both fixedly connected with a roof lower layer plate, and first directional pulleys are arranged at the front ends of the first transverse supports. By arranging the vertical hoisting unit and the transverse walking unit, vertical movement and horizontal movement of the curtain wall unit body are achieved, the system solves the problems that a traditional tower crane or crane is low in hoisting speed and affected by a construction elevator, the construction period cost is reduced, and the system has the advantages of being high in installation speed, safe and reliable in working performance, high in practicability and the like. And all the components can be recycled.
本发明公开了一种高层单元式幕墙快速安装系统,涉及建筑幕墙施工技术领域,其技术方案为,包括支撑单元、竖向吊起单元、横向行走单元,所述支撑单元上设有供横向行走单元行走的第一轨道,所述竖向吊起单元包括卷扬机、第一横撑、第二横撑、第一钢丝绳、第二钢丝绳、U型扣、固定板,所述第一横撑设有两个,所述第一横撑、第二横撑均与屋面下层板固定连接,所述第一横撑的前端设有第一定向滑轮。通过设置竖向吊起单元以及横向行走单元,进而实现幕墙单元体竖向移动,以及水平移动,本系统解决了传统塔吊或者吊车起吊时的速度慢、施工电梯的影响的问题,减少工期成本、且具有安装速度快、工作性能安全可靠,而且组成部件均可周转使用。
Rapid installation system for high-rise unit type curtain wall
The invention discloses a high-rise unit type curtain wall rapid installation system, and relates to the technical field of building curtain wall construction, and the technical scheme is that the high-rise unit type curtain wall rapid installation system comprises a supporting unit, a vertical hoisting unit and a transverse walking unit, and the supporting unit is provided with a first track for the transverse walking unit to walk; the vertical lifting unit comprises a winch, two first transverse supports, a second transverse support, a first steel wire rope, a second steel wire rope, a U-shaped buckle and a fixing plate, the first transverse supports and the second transverse support are both fixedly connected with a roof lower layer plate, and first directional pulleys are arranged at the front ends of the first transverse supports. By arranging the vertical hoisting unit and the transverse walking unit, vertical movement and horizontal movement of the curtain wall unit body are achieved, the system solves the problems that a traditional tower crane or crane is low in hoisting speed and affected by a construction elevator, the construction period cost is reduced, and the system has the advantages of being high in installation speed, safe and reliable in working performance, high in practicability and the like. And all the components can be recycled.
本发明公开了一种高层单元式幕墙快速安装系统,涉及建筑幕墙施工技术领域,其技术方案为,包括支撑单元、竖向吊起单元、横向行走单元,所述支撑单元上设有供横向行走单元行走的第一轨道,所述竖向吊起单元包括卷扬机、第一横撑、第二横撑、第一钢丝绳、第二钢丝绳、U型扣、固定板,所述第一横撑设有两个,所述第一横撑、第二横撑均与屋面下层板固定连接,所述第一横撑的前端设有第一定向滑轮。通过设置竖向吊起单元以及横向行走单元,进而实现幕墙单元体竖向移动,以及水平移动,本系统解决了传统塔吊或者吊车起吊时的速度慢、施工电梯的影响的问题,减少工期成本、且具有安装速度快、工作性能安全可靠,而且组成部件均可周转使用。
Rapid installation system for high-rise unit type curtain wall
一种高层单元式幕墙快速安装系统
HAO CHENGCHENG (author) / YANG HAICHUAN (author) / LIU XUEJIE (author) / KONG LINGXUAN (author) / GONG TAO (author) / FU XIAOWEI (author)
2024-11-15
Patent
Electronic Resource
Chinese
CURTAIN WALL UNIT, CURTAIN WALL INSTALLATION STRUCTURE, AND INSTALLATION METHOD OF CURTAIN WALL
European Patent Office | 2017
|European Patent Office | 2023
|Position adjusting installation method for suspended high-rise unit curtain wall