Protection treatment construction installation method for reserved embedded pipe orifice of electromechanical wire pipe
The invention discloses a protection treatment construction installation method for a reserved embedded pipe opening of an electromechanical wire pipe. The method comprises the steps that S1, civil engineering major construction plate face bottom layer reinforcing steel bars are constructed, and binding of a part of reinforcing steel bars is completed; s2, wiring pipes are laid in the electromechanical installation specialty, and binding of surface layer steel bars is completed in the civil engineering specialty; s3, a professional binding line pipe is installed, a pipe head is fixed, a sleeve used for groove pressing is installed, fixing is firm, the sleeve is perpendicular to the plate face and is not inclined, and the outer wall of the sleeve and the bottom of the sleeve are brushed with a release agent; s4, concrete is poured in civil engineering specialty, the strength of the concrete after final setting reaches 1.2 mpa, the groove pressing sleeve is dismantled, the line pipe is trimmed to be slightly lower than the ground elevation by 1-2 mm, and a pipe cap is installd.The pipe opening is slightly lower than the ground in a groove pressing mode, the groove pressing sleeve can be repeatedly used, secondary garbage cannot be generated, only the pipe cap needs to be taken down during secondary piping operation, and the construction cost is reduced. Construction is simple, convenient, clean and attractive, and the pipe orifice can be effectively prevented from being damaged in follow-up construction.
本发明公开一种机电线管预留预埋管口保护处理施工安装方法,包括:S1、土建专业施工板面底层钢筋并完成一部分钢筋绑扎;S2、机电安装专业布设线管,土建专业完成面层钢筋的绑扎;S3、安装专业绑扎线管并固定管头,并安装用于压槽的套管,固定好牢固且垂直于板面无歪斜,套管外壁包括底部刷上脱模剂;S4、土建专业浇筑混凝土,混凝土终凝后强度达到1.2mpa,拆除压槽套管,修剪线管高度略低于地面标高1‑2mm,并安装管帽,本发明通过压槽的方式使管口略低于地面,且压槽套管可重复使用,不会产生二次垃圾,二次配管作业时只需取下管帽即可,施工简单便捷干净美观,能够有效的避免管口在后续施工中被破坏。
Protection treatment construction installation method for reserved embedded pipe orifice of electromechanical wire pipe
The invention discloses a protection treatment construction installation method for a reserved embedded pipe opening of an electromechanical wire pipe. The method comprises the steps that S1, civil engineering major construction plate face bottom layer reinforcing steel bars are constructed, and binding of a part of reinforcing steel bars is completed; s2, wiring pipes are laid in the electromechanical installation specialty, and binding of surface layer steel bars is completed in the civil engineering specialty; s3, a professional binding line pipe is installed, a pipe head is fixed, a sleeve used for groove pressing is installed, fixing is firm, the sleeve is perpendicular to the plate face and is not inclined, and the outer wall of the sleeve and the bottom of the sleeve are brushed with a release agent; s4, concrete is poured in civil engineering specialty, the strength of the concrete after final setting reaches 1.2 mpa, the groove pressing sleeve is dismantled, the line pipe is trimmed to be slightly lower than the ground elevation by 1-2 mm, and a pipe cap is installd.The pipe opening is slightly lower than the ground in a groove pressing mode, the groove pressing sleeve can be repeatedly used, secondary garbage cannot be generated, only the pipe cap needs to be taken down during secondary piping operation, and the construction cost is reduced. Construction is simple, convenient, clean and attractive, and the pipe orifice can be effectively prevented from being damaged in follow-up construction.
本发明公开一种机电线管预留预埋管口保护处理施工安装方法,包括:S1、土建专业施工板面底层钢筋并完成一部分钢筋绑扎;S2、机电安装专业布设线管,土建专业完成面层钢筋的绑扎;S3、安装专业绑扎线管并固定管头,并安装用于压槽的套管,固定好牢固且垂直于板面无歪斜,套管外壁包括底部刷上脱模剂;S4、土建专业浇筑混凝土,混凝土终凝后强度达到1.2mpa,拆除压槽套管,修剪线管高度略低于地面标高1‑2mm,并安装管帽,本发明通过压槽的方式使管口略低于地面,且压槽套管可重复使用,不会产生二次垃圾,二次配管作业时只需取下管帽即可,施工简单便捷干净美观,能够有效的避免管口在后续施工中被破坏。
Protection treatment construction installation method for reserved embedded pipe orifice of electromechanical wire pipe
一种机电线管预留预埋管口保护处理施工安装方法
HE BIN (author) / FAN JUN (author) / ZHANG JIAN (author) / SHENG QUAN (author) / SUN YONG (author) / PAN JUN (author) / DING MINGZHI (author) / LU PING (author) / SUN XINGENG (author) / SHEN XINGDONG (author)
2024-11-15
Patent
Electronic Resource
Chinese
Pipe orifice leakage treatment construction method based on drainage pipe
European Patent Office | 2022
|Construction method for reserved hole of drainage stand pipe
European Patent Office | 2022
|European Patent Office | 2015
|Reserved mold for wall body pipe chase and reserved method for wall body pipe chase
European Patent Office | 2015
|