Improved method for construction of reserved slot at downstream dam surface for cooling pipe installation
An improved method for construction of a reserved slot at the downstream dam surface for cooling pipe installation comprises the steps that 1, after a template (5) below a pouring bin position is installed, geotechnical cloth (2) is tied to the exposed end of a cooling pipe (1) and is then smeared with concrete separating materials, and the exposed end of the cooling pipe (1) is made to be attached to the template (5); 2, the lower template (5) is detached, then the geotechnical cloth (2) at the exposed end of the cooling pipe (1) is detached, and concrete near the end is removed to enable the end to be exposed by a length enough for welding a sleeve (3); 3, the sleeve (3) is welded to the exposed end of the cooling pipe (1) to enable the cooling pipe (1) to be communicated with an external pipe (4), normal water supply is ensured, construction cost is reduced, working efficiency is improved, and construction quality is guaranteed.
Improved method for construction of reserved slot at downstream dam surface for cooling pipe installation
An improved method for construction of a reserved slot at the downstream dam surface for cooling pipe installation comprises the steps that 1, after a template (5) below a pouring bin position is installed, geotechnical cloth (2) is tied to the exposed end of a cooling pipe (1) and is then smeared with concrete separating materials, and the exposed end of the cooling pipe (1) is made to be attached to the template (5); 2, the lower template (5) is detached, then the geotechnical cloth (2) at the exposed end of the cooling pipe (1) is detached, and concrete near the end is removed to enable the end to be exposed by a length enough for welding a sleeve (3); 3, the sleeve (3) is welded to the exposed end of the cooling pipe (1) to enable the cooling pipe (1) to be communicated with an external pipe (4), normal water supply is ensured, construction cost is reduced, working efficiency is improved, and construction quality is guaranteed.
Improved method for construction of reserved slot at downstream dam surface for cooling pipe installation
ZHANG JIACHENG (author) / LIN DAN (author) / HUA ZHENGYANG (author) / WU SIHAO (author) / LIU MENGMENG (author) / LI GUILIN (author) / BIAN XIAOCAO (author) / WANG FENGLIAN (author) / CHAI LIN (author) / XIAO PING (author)
2015-05-20
Patent
Electronic Resource
English
IPC:
E02D
FOUNDATIONS
,
GrĂ¼ndungen
European Patent Office | 2024
|Construction method for reserved hole of drainage stand pipe
European Patent Office | 2022
|Modified construction method for reserved wide slot of dock-type lock structure
European Patent Office | 2015
|Reserved mold for wall body pipe chase and reserved method for wall body pipe chase
European Patent Office | 2015
|