The embodiment of the invention discloses a demolition construction method and device for an upper structure of a steel box girder type pedestrian trestle, electronic equipment and a storage medium, and relates to the technical field of bridge engineering construction. Comprising the following steps of early-stage preparation, construction preparation, bridge accessory structure and decoration dismantling, steel box girder dismantling, pier column and bearing platform dismantling, waste treatment and resource recovery and later-stage inspection and acceptance. Through fine design, the steel box girder is divided into a plurality of modules to be disassembled one by one, and the technical means of oxygen acetylene gas cutting, mechanical crushing and the like are adopted, so that rapid and accurate construction is ensured. Meanwhile, environmental protection measures are taken, waste is treated in a classified mode, and resources are recycled. According to the scheme, the dismantling efficiency is improved, the construction cost is reduced, the influence on the surrounding environment is remarkably reduced, and it is ensured that the dismantling process is safe and controllable.
本发明实施例公开了一种钢箱梁式人行栈桥上部结构拆除施工方法、装置、电子设备及存储介质,涉及桥梁工程施工技术领域。包括以下步骤:前期准备,施工准备,桥梁附属结构及装饰拆除,钢箱梁拆除,墩柱及承台拆除,废弃物处理与资源回收,后期检查与验收。本发明通过精细化设计,将钢箱梁划分为多个模块逐一拆除,采用氧气乙炔气割和机械化破碎等技术手段,确保施工快速精准。同时,实施环保措施,分类处理废弃物并回收资源。此方案不仅提高了拆除效率,降低了施工成本,还显著减少了对周边环境的影响,确保了拆除过程的安全可控。
Construction method for dismantling upper structure of steel box girder type pedestrian trestle
The embodiment of the invention discloses a demolition construction method and device for an upper structure of a steel box girder type pedestrian trestle, electronic equipment and a storage medium, and relates to the technical field of bridge engineering construction. Comprising the following steps of early-stage preparation, construction preparation, bridge accessory structure and decoration dismantling, steel box girder dismantling, pier column and bearing platform dismantling, waste treatment and resource recovery and later-stage inspection and acceptance. Through fine design, the steel box girder is divided into a plurality of modules to be disassembled one by one, and the technical means of oxygen acetylene gas cutting, mechanical crushing and the like are adopted, so that rapid and accurate construction is ensured. Meanwhile, environmental protection measures are taken, waste is treated in a classified mode, and resources are recycled. According to the scheme, the dismantling efficiency is improved, the construction cost is reduced, the influence on the surrounding environment is remarkably reduced, and it is ensured that the dismantling process is safe and controllable.
本发明实施例公开了一种钢箱梁式人行栈桥上部结构拆除施工方法、装置、电子设备及存储介质,涉及桥梁工程施工技术领域。包括以下步骤:前期准备,施工准备,桥梁附属结构及装饰拆除,钢箱梁拆除,墩柱及承台拆除,废弃物处理与资源回收,后期检查与验收。本发明通过精细化设计,将钢箱梁划分为多个模块逐一拆除,采用氧气乙炔气割和机械化破碎等技术手段,确保施工快速精准。同时,实施环保措施,分类处理废弃物并回收资源。此方案不仅提高了拆除效率,降低了施工成本,还显著减少了对周边环境的影响,确保了拆除过程的安全可控。
Construction method for dismantling upper structure of steel box girder type pedestrian trestle
钢箱梁式人行栈桥上部结构拆除施工方法
LIU LIANG (author) / HAN ZHIFANG (author) / ZHANG JIANTONG (author) / XIONG QIANG (author) / LIANG YUNQIAO (author) / NING PEILIN (author) / LI YITING (author) / HUANG LIANGQING (author) / WANG XUDAN (author) / LI XIAOQIANG (author)
2024-11-26
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Deep foundation pit trestle post-dismantling construction method
European Patent Office | 2024
|Fabricated steel trestle structure and steel trestle construction method
European Patent Office | 2023
|European Patent Office | 2023
|