Reservoir water intake control well construction method
The invention relates to a construction method of a reservoir water intake control well. The construction method comprises the following steps: step 1, early-stage construction preparation and upper slope support construction; secondly, the vertical shaft is excavated and supported to the bottom of the vertical shaft, and concrete is used for sealing the bottom; 3, low-water-level water taking pipe construction; 4, water is introduced into a low-water-level water taking pipe; 5, high-water-level water taking pipe construction; sixthly, a high platform (a steel platform) is constructed; seventhly, the steel platform is utilized, and the control well continues to be constructed to the top; and 8, subsequent construction is ended, the formwork and the steel platform are dismantled, and control well construction is completed. According to the method, the construction period is shortened, the cost is reduced, the engineering quality is guaranteed, beneficial practical experience and theoretical guidance are provided for development of the construction technology of the water intake control well of the reservoir, and beneficial reference can be provided for implementation of subsequent similar engineering.
本发明涉及一种水库取水节制井施工方法,步骤一:前期施工准备及上边坡支护施工;步骤二:竖井边开挖边支护至竖井底部,混凝土封底;步骤三:低水位取水管施工;步骤四:低水位取水管通水;步骤五:高水位取水管施工;步骤六:施工高平台(钢平台);步骤七:利用钢平台,继续施工节制井至顶部;步骤八:后续施工收尾,拆除模架及钢平台,完成节制井施工。本发明缩短工期、降低成本并保障工程质量的效果,为水库取水节制井施工技术发展提供了有益的实践经验和理论指导,并可为后续类似工程实施提供有益借鉴。
Reservoir water intake control well construction method
The invention relates to a construction method of a reservoir water intake control well. The construction method comprises the following steps: step 1, early-stage construction preparation and upper slope support construction; secondly, the vertical shaft is excavated and supported to the bottom of the vertical shaft, and concrete is used for sealing the bottom; 3, low-water-level water taking pipe construction; 4, water is introduced into a low-water-level water taking pipe; 5, high-water-level water taking pipe construction; sixthly, a high platform (a steel platform) is constructed; seventhly, the steel platform is utilized, and the control well continues to be constructed to the top; and 8, subsequent construction is ended, the formwork and the steel platform are dismantled, and control well construction is completed. According to the method, the construction period is shortened, the cost is reduced, the engineering quality is guaranteed, beneficial practical experience and theoretical guidance are provided for development of the construction technology of the water intake control well of the reservoir, and beneficial reference can be provided for implementation of subsequent similar engineering.
本发明涉及一种水库取水节制井施工方法,步骤一:前期施工准备及上边坡支护施工;步骤二:竖井边开挖边支护至竖井底部,混凝土封底;步骤三:低水位取水管施工;步骤四:低水位取水管通水;步骤五:高水位取水管施工;步骤六:施工高平台(钢平台);步骤七:利用钢平台,继续施工节制井至顶部;步骤八:后续施工收尾,拆除模架及钢平台,完成节制井施工。本发明缩短工期、降低成本并保障工程质量的效果,为水库取水节制井施工技术发展提供了有益的实践经验和理论指导,并可为后续类似工程实施提供有益借鉴。
Reservoir water intake control well construction method
一种水库取水节制井施工方法
XU KEFENG (author) / LIU JIE (author) / WU LIJUN (author) / ZHU CHANGGEN (author) / WANG HUI (author) / YANG WEIHUA (author)
2024-12-27
Patent
Electronic Resource
Chinese
Pipe jacking construction method for water intake of reservoir
European Patent Office | 2024
|Well pipe assembly, water intake structure and construction method of water intake structure
European Patent Office | 2023
|Construction method for building artificial rock plug body and water intake in reservoir
European Patent Office | 2021
|Construction method for building water intake in built reservoir by adopting island building method
European Patent Office | 2023
|