Mounting method for accurate butt joint of steel grating and embedded part
The invention relates to the technical field of building construction, in particular to a mounting method for accurate butt joint of a steel grating and an embedded part, which comprises the following steps: S1, arranging the embedded part and mounting hoisting equipment; s2, the steel grating is hoisted after being assembled on the ground; s3, the steel grating and the embedded part are fixed in batches; in the step S2, after the steel grating is assembled, a total station with a set deviation range value A0 is used for measuring the lifting point positions of the steel grating and the positions of the embedded parts, the measured lifting point coordinates are compared with the coordinates of the embedded parts, and the deviation value Anm between each lifting point and the corresponding embedded part is calculated; the deviation value Anm is compared with the deviation range value A0, so that whether the deviation values Anm between all the lifting points and the embedded parts corresponding to the lifting points are in an acceptable range or not is determined before the steel grating is lifted, whether lifting operation can be carried out subsequently or not is judged, and the situation that the lifting points and the embedded parts are not aligned after lifting is avoided; and the situation that the steel grating needs to descend and the lifting point needs to be adjusted is avoided.
本发明涉及建筑施工技术领域,具体地说,涉及一种钢格栅与预埋件精准对接的安装方法,包括以下步骤:S1、设置预埋件与安装起吊设备;S2、地面拼装钢格栅后起吊;S3、钢格栅分次与预埋件固定;本发明通过步骤S2中,在钢格栅拼装完成后,使用已经设定偏差范围值A0的全站仪对钢格栅的吊点位置与预埋件的位置进行测量,并将测得的吊点坐标与预埋件坐标进行比对,计算每个吊点与相应预埋件之间的偏差值Anm,取偏差值Anm与偏差范围值A0做比较,从而在钢格栅起吊前,确定所有吊点与吊点对应的预埋件之间的偏差值Anm是否在可接受范围,为后续是否可以进行起吊作业做判别,避免在起吊后才发现吊点与预埋件对不齐,又需要下降钢格栅并调整吊点的情况出现。
Mounting method for accurate butt joint of steel grating and embedded part
The invention relates to the technical field of building construction, in particular to a mounting method for accurate butt joint of a steel grating and an embedded part, which comprises the following steps: S1, arranging the embedded part and mounting hoisting equipment; s2, the steel grating is hoisted after being assembled on the ground; s3, the steel grating and the embedded part are fixed in batches; in the step S2, after the steel grating is assembled, a total station with a set deviation range value A0 is used for measuring the lifting point positions of the steel grating and the positions of the embedded parts, the measured lifting point coordinates are compared with the coordinates of the embedded parts, and the deviation value Anm between each lifting point and the corresponding embedded part is calculated; the deviation value Anm is compared with the deviation range value A0, so that whether the deviation values Anm between all the lifting points and the embedded parts corresponding to the lifting points are in an acceptable range or not is determined before the steel grating is lifted, whether lifting operation can be carried out subsequently or not is judged, and the situation that the lifting points and the embedded parts are not aligned after lifting is avoided; and the situation that the steel grating needs to descend and the lifting point needs to be adjusted is avoided.
本发明涉及建筑施工技术领域,具体地说,涉及一种钢格栅与预埋件精准对接的安装方法,包括以下步骤:S1、设置预埋件与安装起吊设备;S2、地面拼装钢格栅后起吊;S3、钢格栅分次与预埋件固定;本发明通过步骤S2中,在钢格栅拼装完成后,使用已经设定偏差范围值A0的全站仪对钢格栅的吊点位置与预埋件的位置进行测量,并将测得的吊点坐标与预埋件坐标进行比对,计算每个吊点与相应预埋件之间的偏差值Anm,取偏差值Anm与偏差范围值A0做比较,从而在钢格栅起吊前,确定所有吊点与吊点对应的预埋件之间的偏差值Anm是否在可接受范围,为后续是否可以进行起吊作业做判别,避免在起吊后才发现吊点与预埋件对不齐,又需要下降钢格栅并调整吊点的情况出现。
Mounting method for accurate butt joint of steel grating and embedded part
一种钢格栅与预埋件精准对接的安装方法
CHEN YA (author) / CAO RUIXUE (author) / XIANG LI (author) / YANG KAIXUAN (author) / ZHAO XUAN (author) / CHANG KUN (author)
2025-01-03
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
European Patent Office | 2022
|Fabricated wall surface butt joint mounting piece and mounting method thereof
European Patent Office | 2022
|Steel column butt joint supporting frame and steel column butt joint construction method
European Patent Office | 2024
|