TEMPORARY COLUMN INSTALLATION METHOD
PROBLEM TO BE SOLVED: To provide a temporary column installation method enabling a temporary column supporting a temporary roof to be securely installed at a predetermined installation place.SOLUTION: The temporary column installation method comprises: a step S1 of dividing a column body of a temporary column 15 into a plurality of members 20A to 20E along a length direction, and fitting the uppermost member 20E to a temporary roof 61; a step S2 of disposing the lowermost member 20A at a prescribed position and fitting a second gate bar member 30 to the lowermost member 20A; steps S3 to S6 of fitting and assembling the remaining members 20B to 20D on top of the lowermost member 20A and fitting a first gate bar member 26 and a step-rod jack 25 to the assembled members 20A to 20D; and a step S7 of driving the step-rod jack 25 to raise the assembled members 20A to 20D and to thereby connect the assembled members 20A to 20D to the uppermost member 20E.SELECTED DRAWING: Figure 12
【課題】仮設屋根を支持する仮設柱を、所定の設置箇所に確実に設置できる仮設柱の設置方法を提供すること。【解決手段】仮設柱15の柱本体を、長さ方向に沿って複数の部材20A〜20Eに分割しておき、最上段の部材20Eを、仮設屋根61に取り付けるステップS1と、最下段の部材20Aを所定位置に配置し、この最下段の部材20Aに第2かんぬき部材30を取り付けるステップS2と、最下段の部材20Aの上に残りの部材20B〜20Dを取り付けて組み立てるとともに、この組み立てた部材20A〜20Dに、第1かんぬき部材26およびステップロッドジャッキ25を取り付けるステップS3〜S6と、ステップロッドジャッキ25を駆動して、組み立てた部材20A〜20Dを上昇させて、最上段の部材20Eに接合するステップS7と、を備える。【選択図】図12
TEMPORARY COLUMN INSTALLATION METHOD
PROBLEM TO BE SOLVED: To provide a temporary column installation method enabling a temporary column supporting a temporary roof to be securely installed at a predetermined installation place.SOLUTION: The temporary column installation method comprises: a step S1 of dividing a column body of a temporary column 15 into a plurality of members 20A to 20E along a length direction, and fitting the uppermost member 20E to a temporary roof 61; a step S2 of disposing the lowermost member 20A at a prescribed position and fitting a second gate bar member 30 to the lowermost member 20A; steps S3 to S6 of fitting and assembling the remaining members 20B to 20D on top of the lowermost member 20A and fitting a first gate bar member 26 and a step-rod jack 25 to the assembled members 20A to 20D; and a step S7 of driving the step-rod jack 25 to raise the assembled members 20A to 20D and to thereby connect the assembled members 20A to 20D to the uppermost member 20E.SELECTED DRAWING: Figure 12
【課題】仮設屋根を支持する仮設柱を、所定の設置箇所に確実に設置できる仮設柱の設置方法を提供すること。【解決手段】仮設柱15の柱本体を、長さ方向に沿って複数の部材20A〜20Eに分割しておき、最上段の部材20Eを、仮設屋根61に取り付けるステップS1と、最下段の部材20Aを所定位置に配置し、この最下段の部材20Aに第2かんぬき部材30を取り付けるステップS2と、最下段の部材20Aの上に残りの部材20B〜20Dを取り付けて組み立てるとともに、この組み立てた部材20A〜20Dに、第1かんぬき部材26およびステップロッドジャッキ25を取り付けるステップS3〜S6と、ステップロッドジャッキ25を駆動して、組み立てた部材20A〜20Dを上昇させて、最上段の部材20Eに接合するステップS7と、を備える。【選択図】図12
TEMPORARY COLUMN INSTALLATION METHOD
仮設柱の設置方法
ICHIHARA HIDEKI (author) / KAYASHIMA MAKOTO (author) / AKADA TAKUMI (author) / YAGI KENTA (author) / SASA MINORU (author)
2016-04-04
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
COLUMN INSTALLATION METHOD AND COLUMN INSTALLATION STRUCTURE