METHOD FOR BURYING HEAT EXCHANGE PIPE FOR UNDERGROUND HEAT
PROBLEM TO BE SOLVED: To make it possible to bury a heat exchange pipe by efficiently lowering the heat exchange pipe even when an obstacle such as a lump of mud exists in a pile hole.SOLUTION: A method for burying a heat exchange pipe for underground heat includes: excavating a pile hole 42 from the ground 41 to bury a concrete precast pile 43 having a hollow 44 into the pile hole 42 (a); inserting a heat exchange pipe 1 with the lower end to which a weight member 20 and propulsion device 10 are attached into the hollow 44 of the precast pile 43 (b), (c); when an obstacle such as a lump of mud exists in the course of its descent, supplying high-pressure water from the ground 41 to a supply pipe 13 to inject high-pressure water upwards from injection ports 12, 12 of the propulsion device 10 (d) before descending to the bottom of the precast pile 43 (e); and stopping the propulsion device 10's injection before drawing up only the propulsion device 10 to the ground 41 while holding the heat exchange pipe 1 on the ground 41 (f).SELECTED DRAWING: Figure 2
【課題】杭穴内に泥塊などの障害物があっても、熱交換パイプを効率良く下降して埋設できる。【解決手段】地上41から杭穴42を掘削して、杭穴42内に中空部44を有するコンクリート製の既製杭43を埋設する(a)。下端部に錘部材20及び推進具10を取り付けた熱交換パイプ1を、既製杭43の中空部44に挿入する(b)(c)。下降途中で、泥塊等の障害があった場合には、地上41から供給パイプ13に高圧水を供給して、推進具10の噴射口12、12から上方に高圧水を噴射して(d)、既製杭43の底部まで下降する(e)。推進具10の噴射を止め熱交換パイプ1を地上41で保持して、推進具10のみを地上41まで引き上げる(f)。【選択図】図2
METHOD FOR BURYING HEAT EXCHANGE PIPE FOR UNDERGROUND HEAT
PROBLEM TO BE SOLVED: To make it possible to bury a heat exchange pipe by efficiently lowering the heat exchange pipe even when an obstacle such as a lump of mud exists in a pile hole.SOLUTION: A method for burying a heat exchange pipe for underground heat includes: excavating a pile hole 42 from the ground 41 to bury a concrete precast pile 43 having a hollow 44 into the pile hole 42 (a); inserting a heat exchange pipe 1 with the lower end to which a weight member 20 and propulsion device 10 are attached into the hollow 44 of the precast pile 43 (b), (c); when an obstacle such as a lump of mud exists in the course of its descent, supplying high-pressure water from the ground 41 to a supply pipe 13 to inject high-pressure water upwards from injection ports 12, 12 of the propulsion device 10 (d) before descending to the bottom of the precast pile 43 (e); and stopping the propulsion device 10's injection before drawing up only the propulsion device 10 to the ground 41 while holding the heat exchange pipe 1 on the ground 41 (f).SELECTED DRAWING: Figure 2
【課題】杭穴内に泥塊などの障害物があっても、熱交換パイプを効率良く下降して埋設できる。【解決手段】地上41から杭穴42を掘削して、杭穴42内に中空部44を有するコンクリート製の既製杭43を埋設する(a)。下端部に錘部材20及び推進具10を取り付けた熱交換パイプ1を、既製杭43の中空部44に挿入する(b)(c)。下降途中で、泥塊等の障害があった場合には、地上41から供給パイプ13に高圧水を供給して、推進具10の噴射口12、12から上方に高圧水を噴射して(d)、既製杭43の底部まで下降する(e)。推進具10の噴射を止め熱交換パイプ1を地上41で保持して、推進具10のみを地上41まで引き上げる(f)。【選択図】図2
METHOD FOR BURYING HEAT EXCHANGE PIPE FOR UNDERGROUND HEAT
地中熱の熱交換パイプの埋設方法
HASHIZUME YOSHIMITSU (author)
2017-06-01
Patent
Electronic Resource
Japanese
CONSTRUCTION METHOD FOR BURYING UNDERGROUND HEAT EXCHANGER IN STEEL PIPE PILE
European Patent Office | 2016
|BASE FOR UNDERGROUND PIPE AND METHOD FOR RE-BURYING UNDERGROUND PIPE
European Patent Office | 2017
|DRAINAGE PIPE BURYING DEVICE AND DRAINAGE PIPE BURYING METHOD
European Patent Office | 2021
|