BREAKWATER CONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a construction method for a breakwater having sufficient slide resistance against an assumed tsunami wave.SOLUTION: A value W2 necessary for making a slide resistance value R equal with assumed tsunami wave force P is derived, the slide resistance value being a sum of a slide resistance value R1 of a caisson 3 calculated by multiplying a weight value W1 of the caisson 3 by a frictional coefficient value μ1 between the caisson 3 and a mound 2, and a slide resistance value R2 obtained by multiplying a total weight value W2 of wave dissipating blocks 5 piled on an inner port side of the caisson 3 by a frictional coefficient value μ2 between a wave dissipating work 4 (a structure built by piling the wave dissipating blocks 5) and the mound 2. A breakwater 1 is constructed by piling the wave dissipating blocks 5 on the inner port side of the caisson 3, the wave dissipating blocks being of a quantity that makes the total weight greater than the value W2.SELECTED DRAWING: Figure 1
【課題】想定される津波に対し十分な滑動抵抗力を有する防波堤を構築する方法を提供する。【解決手段】ケーソン3の重量の値W1にケーソン3とマウンド2との摩擦係数の値μ1を乗じて算出されるケーソン3の滑動抵抗力の値R1と、ケーソン3の港内側に積み上げる消波ブロック5の総重量の値W2に消波工4(消波ブロック5を積み上げて構築される構造物)とマウンド2との摩擦係数の値μ2を乗じて算出される滑動抵抗力の値R2と、を加算して算出される滑動抵抗力の値Rを、想定される津波力Pと一致させるために必要となる値W2を求め、総重量が値W2以上となる量の消波ブロック5を、ケーソン3の港内側に積み上げて、防波堤1を構築することを特徴とする。【選択図】図1
BREAKWATER CONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a construction method for a breakwater having sufficient slide resistance against an assumed tsunami wave.SOLUTION: A value W2 necessary for making a slide resistance value R equal with assumed tsunami wave force P is derived, the slide resistance value being a sum of a slide resistance value R1 of a caisson 3 calculated by multiplying a weight value W1 of the caisson 3 by a frictional coefficient value μ1 between the caisson 3 and a mound 2, and a slide resistance value R2 obtained by multiplying a total weight value W2 of wave dissipating blocks 5 piled on an inner port side of the caisson 3 by a frictional coefficient value μ2 between a wave dissipating work 4 (a structure built by piling the wave dissipating blocks 5) and the mound 2. A breakwater 1 is constructed by piling the wave dissipating blocks 5 on the inner port side of the caisson 3, the wave dissipating blocks being of a quantity that makes the total weight greater than the value W2.SELECTED DRAWING: Figure 1
【課題】想定される津波に対し十分な滑動抵抗力を有する防波堤を構築する方法を提供する。【解決手段】ケーソン3の重量の値W1にケーソン3とマウンド2との摩擦係数の値μ1を乗じて算出されるケーソン3の滑動抵抗力の値R1と、ケーソン3の港内側に積み上げる消波ブロック5の総重量の値W2に消波工4(消波ブロック5を積み上げて構築される構造物)とマウンド2との摩擦係数の値μ2を乗じて算出される滑動抵抗力の値R2と、を加算して算出される滑動抵抗力の値Rを、想定される津波力Pと一致させるために必要となる値W2を求め、総重量が値W2以上となる量の消波ブロック5を、ケーソン3の港内側に積み上げて、防波堤1を構築することを特徴とする。【選択図】図1
BREAKWATER CONSTRUCTION METHOD
防波堤の構築方法
MITSUI JUN (author) / MARUYAMA SOHEI (author)
2017-08-10
Patent
Electronic Resource
Japanese
IPC:
E02B
HYDRAULIC ENGINEERING
,