A platform for research: civil engineering, architecture and urbanism
BORING METHOD AND APPARATUS
PROBLEM TO BE SOLVED: To improve a work's efficiency of boring in a horizontal direction and a ground improvement.SOLUTION: In the method, firstly a guide box 7 having a bent hole 8 penetrating from a top surface to a side surface in an arc shape is installed in a main borehole 5 formed by drilling a ground in a vertical direction. Then, by inserting a flexible boring member 10 into the bent hole 8 of the guide box 7, the boring member 10 is guided to the horizontal direction and a horizontal borehole 15 is formed by drilling, and next chemical liquid is injected. Thereafter, after changing at least one of a depth position of the guide box 7 and a rotational angle position in the horizontal plane in the main borehole 5, by inserting the boring member 10 again, formation of a horizontal borehole and injection of a chemical liquid are performed in a plurality of boreholes.SELECTED DRAWING: Figure 3
【課題】 水平方向ボーリング及び地盤改良作業の効率を改善する。【解決手段】 地盤を鉛直方向に削孔して形成した基幹ボーリング孔5内に、上面から側面へ円弧状に貫通する曲がり孔8を有するガイド箱7を設置する。そして、ガイド箱7の曲がり孔8に可撓性のボーリング部材10を挿入することで、ボーリング部材10を横向きにして、横向きのボーリング孔15を形成し、薬液を注入する。その後、基幹ボーリング孔5内でのガイド箱7の深度位置及び水平面内の回転角度位置の少なくとも一方を変更した後、ボーリング部材10を再度挿入することで、ボーリング及び薬液注入を複数孔で実施する。【選択図】 図3
BORING METHOD AND APPARATUS
PROBLEM TO BE SOLVED: To improve a work's efficiency of boring in a horizontal direction and a ground improvement.SOLUTION: In the method, firstly a guide box 7 having a bent hole 8 penetrating from a top surface to a side surface in an arc shape is installed in a main borehole 5 formed by drilling a ground in a vertical direction. Then, by inserting a flexible boring member 10 into the bent hole 8 of the guide box 7, the boring member 10 is guided to the horizontal direction and a horizontal borehole 15 is formed by drilling, and next chemical liquid is injected. Thereafter, after changing at least one of a depth position of the guide box 7 and a rotational angle position in the horizontal plane in the main borehole 5, by inserting the boring member 10 again, formation of a horizontal borehole and injection of a chemical liquid are performed in a plurality of boreholes.SELECTED DRAWING: Figure 3
【課題】 水平方向ボーリング及び地盤改良作業の効率を改善する。【解決手段】 地盤を鉛直方向に削孔して形成した基幹ボーリング孔5内に、上面から側面へ円弧状に貫通する曲がり孔8を有するガイド箱7を設置する。そして、ガイド箱7の曲がり孔8に可撓性のボーリング部材10を挿入することで、ボーリング部材10を横向きにして、横向きのボーリング孔15を形成し、薬液を注入する。その後、基幹ボーリング孔5内でのガイド箱7の深度位置及び水平面内の回転角度位置の少なくとも一方を変更した後、ボーリング部材10を再度挿入することで、ボーリング及び薬液注入を複数孔で実施する。【選択図】 図3
BORING METHOD AND APPARATUS
ボーリング方法及び装置
FUJISAKI KATSUTOSHI (author) / SAKATA NOBORU (author) / MATSUI MASAKI (author) / ABE HIROYUKI (author)
2018-04-12
Patent
Electronic Resource
Japanese