METHOD OF REMOVING CONCRETE SLAB AND METHOD OF NEWLY CONSTRUCTING CONCRETE SLAB
PROBLEM TO BE SOLVED: To remove a concrete slab from a flange of a girder while reducing labor of the operation, and noise and vibration.SOLUTION: In a method of removing a concrete slab which removes a concrete slab 20 joined to a flange 11 of a girder 10 from the flange 11 of the girder 10 by covering a dowel such as a stud dowel 14 which projects from a top surface 12 of the flange 11 of the girder 10 with a hardener such as concrete 21 which forms the concrete slab 20, a drilling process drills a hole 40 which extends to the top face 12 of the flange 11 so that the periphery of the stud dowel 14 is hollowed from an under surface 13 of the flange 11, and a slab separation process separates the concrete slab 20 together with the stud dowel 14 covered with the concrete 21 from the flange 11 of the girder 10. Therefore, the concrete slab 20 can be removed from the flange 11 while reducing labor of the operation of shaving off the concrete directly above the top face 12 of the flange 11 of the girder 10.SELECTED DRAWING: Figure 4
【課題】作業の労力や騒音及び振動を低減しつつコンクリート床版を桁のフランジから撤去する。【解決手段】コンクリート床版20を形成するコンクリート21等の硬化材により桁10のフランジ11の上面12から突出したスタッドジベル14等のジベルが包含されることによって桁10のフランジ11と接合されたコンクリート床版20を桁10のフランジ11から撤去するためのコンクリート床版の撤去方法において、削孔工程によりフランジ11の下面13からスタッドジベル14の周囲をくり抜くようにフランジ11の上面12に達する孔40が削孔され、床版分離工程により、コンクリート21により包含されたスタッドジベル14と一緒に桁10のフランジ11からコンクリート床版20が分離されるため、桁10のフランジ11の上面12の直上のコンクリートを斫る作業の労力を低減しつつコンクリート床版20をフランジ11から撤去することができる。【選択図】図4
METHOD OF REMOVING CONCRETE SLAB AND METHOD OF NEWLY CONSTRUCTING CONCRETE SLAB
PROBLEM TO BE SOLVED: To remove a concrete slab from a flange of a girder while reducing labor of the operation, and noise and vibration.SOLUTION: In a method of removing a concrete slab which removes a concrete slab 20 joined to a flange 11 of a girder 10 from the flange 11 of the girder 10 by covering a dowel such as a stud dowel 14 which projects from a top surface 12 of the flange 11 of the girder 10 with a hardener such as concrete 21 which forms the concrete slab 20, a drilling process drills a hole 40 which extends to the top face 12 of the flange 11 so that the periphery of the stud dowel 14 is hollowed from an under surface 13 of the flange 11, and a slab separation process separates the concrete slab 20 together with the stud dowel 14 covered with the concrete 21 from the flange 11 of the girder 10. Therefore, the concrete slab 20 can be removed from the flange 11 while reducing labor of the operation of shaving off the concrete directly above the top face 12 of the flange 11 of the girder 10.SELECTED DRAWING: Figure 4
【課題】作業の労力や騒音及び振動を低減しつつコンクリート床版を桁のフランジから撤去する。【解決手段】コンクリート床版20を形成するコンクリート21等の硬化材により桁10のフランジ11の上面12から突出したスタッドジベル14等のジベルが包含されることによって桁10のフランジ11と接合されたコンクリート床版20を桁10のフランジ11から撤去するためのコンクリート床版の撤去方法において、削孔工程によりフランジ11の下面13からスタッドジベル14の周囲をくり抜くようにフランジ11の上面12に達する孔40が削孔され、床版分離工程により、コンクリート21により包含されたスタッドジベル14と一緒に桁10のフランジ11からコンクリート床版20が分離されるため、桁10のフランジ11の上面12の直上のコンクリートを斫る作業の労力を低減しつつコンクリート床版20をフランジ11から撤去することができる。【選択図】図4
METHOD OF REMOVING CONCRETE SLAB AND METHOD OF NEWLY CONSTRUCTING CONCRETE SLAB
コンクリート床版の撤去方法及びコンクリート床版の新設方法
FUJISHIRO MASARU (author) / ONO TOSHIO (author) / ICHINOMIYA TOSHIMICHI (author) / KANEHARU HIDESADA (author) / KOSAKA TAKASHI (author)
2018-05-10
Patent
Electronic Resource
Japanese
IPC:
E01D
BRIDGES
,
Brücken
European Patent Office | 2017
|