CONCRETE FLOOR SLAB REMOVAL METHOD AND CONCRETE FLOOR SLAB CONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To remove a concrete floor slab from top face of a girder while reducing work labor.SOLUTION: Holes 40 are drilled into a haunch part 22 by a drilling process. Cracks 60 are initiated with stud dowels 13 on the haunch part 22 by a crack initiation process that uses the holes 40 as starting points. The stud dowels 13 on the inside of the haunch part 22 are broken off from the cracks 60 by a dowel breaking process. A concrete floor slab 20 is then separated from a girder 10 by a floor slab separation process that uses the cracks 60 as a boundary. Only remaining portions of the concrete floor slab 20 portion under the cracks 60 and the stud dowel 13 remain on a top face 11 of the girder 10, after the separation process. Thereby, it is possible to remove the concrete floor slab 20 from the top face 11 of the girder 10 while reducing the labor for performing cutting work of the concrete 21 on the top face 11 of the girder 10 and removal work of the existing stud dowel 13.SELECTED DRAWING: Figure 5
【課題】作業の労力を低減しつつコンクリート床版を桁の上面から撤去する。【解決手段】削孔工程によりハンチ部22に孔40が削孔され、亀裂発生工程により孔40を起点としてハンチ部22にスタッドジベル13に到達する亀裂60が発生させられ、ジベル切断工程により亀裂60からハンチ部22の内部のスタッドジベル13が切断され、床版分離工程により亀裂60を境界として桁10からコンクリート床版20が分離される。分離工程後には、桁10の上面11に亀裂60の下のコンクリート床版20及びスタッドジベル13の残部のみが残る。したがって、桁10の上面11のコンクリート21を斫る作業や既設のスタッドジベル13を除去する作業の労力を低減しつつコンクリート床版20を桁10の上面11から撤去することができる。【選択図】図5
CONCRETE FLOOR SLAB REMOVAL METHOD AND CONCRETE FLOOR SLAB CONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To remove a concrete floor slab from top face of a girder while reducing work labor.SOLUTION: Holes 40 are drilled into a haunch part 22 by a drilling process. Cracks 60 are initiated with stud dowels 13 on the haunch part 22 by a crack initiation process that uses the holes 40 as starting points. The stud dowels 13 on the inside of the haunch part 22 are broken off from the cracks 60 by a dowel breaking process. A concrete floor slab 20 is then separated from a girder 10 by a floor slab separation process that uses the cracks 60 as a boundary. Only remaining portions of the concrete floor slab 20 portion under the cracks 60 and the stud dowel 13 remain on a top face 11 of the girder 10, after the separation process. Thereby, it is possible to remove the concrete floor slab 20 from the top face 11 of the girder 10 while reducing the labor for performing cutting work of the concrete 21 on the top face 11 of the girder 10 and removal work of the existing stud dowel 13.SELECTED DRAWING: Figure 5
【課題】作業の労力を低減しつつコンクリート床版を桁の上面から撤去する。【解決手段】削孔工程によりハンチ部22に孔40が削孔され、亀裂発生工程により孔40を起点としてハンチ部22にスタッドジベル13に到達する亀裂60が発生させられ、ジベル切断工程により亀裂60からハンチ部22の内部のスタッドジベル13が切断され、床版分離工程により亀裂60を境界として桁10からコンクリート床版20が分離される。分離工程後には、桁10の上面11に亀裂60の下のコンクリート床版20及びスタッドジベル13の残部のみが残る。したがって、桁10の上面11のコンクリート21を斫る作業や既設のスタッドジベル13を除去する作業の労力を低減しつつコンクリート床版20を桁10の上面11から撤去することができる。【選択図】図5
CONCRETE FLOOR SLAB REMOVAL METHOD AND CONCRETE FLOOR SLAB CONSTRUCTION METHOD
コンクリート床版の撤去方法及びコンクリート床版の新設方法
ONO TOSHIO (author) / ICHINOMIYA TOSHIMICHI (author) / FUJISHIRO MASARU (author) / KANEHARU HIDESADA (author) / KOSAKA TAKASHI (author)
2018-06-14
Patent
Electronic Resource
Japanese
IPC:
E01D
BRIDGES
,
Brücken
LIGHTWEIGHT CONCRETE FLOOR SLAB AND LIGHTWEIGHT CONCRETE FLOOR SLAB CONSTRUCTION METHOD
European Patent Office | 2023
|CONCRETE FLOOR SLAB AND CONCRETE FLOOR SLAB FORMING METHOD
European Patent Office | 2021
|European Patent Office | 2019
|Construction method and construction device of concrete floor slab and concrete floor slab
European Patent Office | 2023
|