POLE ORIGINAL POSITION RECONSTRUCTION STRUCTURE, AND POLE ORIGINAL POSITION RECONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a pole original position reconstruction structure capable of shortening a construction period, reducing noise during the construction period and securing sufficient rigidity and strength, and a pole original position reconstruction method.SOLUTION: A pole original position reconstruction structure 1 in which a pole is reconstructed at an original position of an existing pole 3 comprises: a base part 3A of the existing pole of which the upper part is cut; multiple steel pipe divided bodies 4 which are installed around the base part 3A, engaged and joined with each other; mortar 9 filling gaps between the base part 3A of the pole 3 and the multiple steel pipe divided bodies 4; and a steel pipe pole 10 that is fitted into upper parts of the multiple steel pipe divided bodies 4. Any one steel pipe divided body 4 among the multiple steel pipe divided bodies 4 includes a bracket 4A for fitting a temporary receiving member which temporarily supports a structure supported by the existing pole 3 during reconstruction.SELECTED DRAWING: Figure 1
【課題】施工期間が短くて静かで済み、かつ十分な剛性、強度を確保することのできる、柱の元位置建替え構造、及び柱の元位置建替え方法を提供すること。【解決手段】既存の柱3の元位置に柱が建て替えられた柱の元位置建替え構造1は、上部が切断された既存の柱の基部3Aと、この基部3Aの回りを囲むように設置され、互いに係合接合された複数の鋼管分割体4と、柱3の基部3Aと複数の鋼管分割体4の隙間に充填されたモルタル9と、複数の鋼管分割体4の上部にはめ込まれる鋼管柱10と、を備え、複数の鋼管分割体4のいずれかの鋼管分割体4には、既存の柱3が支持していた構造体を、建替え中に仮支持する仮受け部材を取り付けるブラケット4Aが設けられている。【選択図】図1
POLE ORIGINAL POSITION RECONSTRUCTION STRUCTURE, AND POLE ORIGINAL POSITION RECONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a pole original position reconstruction structure capable of shortening a construction period, reducing noise during the construction period and securing sufficient rigidity and strength, and a pole original position reconstruction method.SOLUTION: A pole original position reconstruction structure 1 in which a pole is reconstructed at an original position of an existing pole 3 comprises: a base part 3A of the existing pole of which the upper part is cut; multiple steel pipe divided bodies 4 which are installed around the base part 3A, engaged and joined with each other; mortar 9 filling gaps between the base part 3A of the pole 3 and the multiple steel pipe divided bodies 4; and a steel pipe pole 10 that is fitted into upper parts of the multiple steel pipe divided bodies 4. Any one steel pipe divided body 4 among the multiple steel pipe divided bodies 4 includes a bracket 4A for fitting a temporary receiving member which temporarily supports a structure supported by the existing pole 3 during reconstruction.SELECTED DRAWING: Figure 1
【課題】施工期間が短くて静かで済み、かつ十分な剛性、強度を確保することのできる、柱の元位置建替え構造、及び柱の元位置建替え方法を提供すること。【解決手段】既存の柱3の元位置に柱が建て替えられた柱の元位置建替え構造1は、上部が切断された既存の柱の基部3Aと、この基部3Aの回りを囲むように設置され、互いに係合接合された複数の鋼管分割体4と、柱3の基部3Aと複数の鋼管分割体4の隙間に充填されたモルタル9と、複数の鋼管分割体4の上部にはめ込まれる鋼管柱10と、を備え、複数の鋼管分割体4のいずれかの鋼管分割体4には、既存の柱3が支持していた構造体を、建替え中に仮支持する仮受け部材を取り付けるブラケット4Aが設けられている。【選択図】図1
POLE ORIGINAL POSITION RECONSTRUCTION STRUCTURE, AND POLE ORIGINAL POSITION RECONSTRUCTION METHOD
柱の元位置建替え構造、及び柱の元位置建替え方法
TOMINAGA NORIYOSHI (author) / SATO NAOKI (author)
2018-10-04
Patent
Electronic Resource
Japanese
POLE ORIGINAL POSITION RECONSTRUCTION STRUCTURE, AND POLE ORIGINAL POSITION RECONSTRUCTION METHOD
European Patent Office | 2018
|UTILITY POLE ORIGINAL HOLE RECONSTRUCTION TOOL EQUIPPED VEHICLE
European Patent Office | 2018
|UTILITY POLE ORIGINAL HOLE RECONSTRUCTION OVERHEAD WIRE TEMPORARY RELOCATION TOOL
European Patent Office | 2018
|European Patent Office | 2019
|ORIGINAL POSITION BUILDING COLUMN METHOD AND ORIGINAL POSITION BUILDING COLUMN STRUCTURE
European Patent Office | 2019
|