METHOD FOR CONSTRUCTING EXPOSED-TYPE COLUMN BASE
To provide a method for constructing an exposed-type column base capable of properly transmitting a shearing force caused by an earthquake, wind or the like acting on a base plate in which an anchor bolt insertion hole is formed as an excessive hole to an anchor bolt, and improving the cost.SOLUTION: In a construction of an exposed-type column base in which a base plate 2 fixed to a lower end of a steel column is fixed by anchor bolts 3 projecting to an upper surface of foundation concrete 9, the anchor bolt 3 is inserted into an excessive hole 4 of the base plate 2, and fastened with two nuts 8 in a state where a nested washer 5 and a flat washer 6 composed of an upper washer and a lower washer are inserted; and when the inside of a cup-shaped container 13 is decompressed by a vacuum pump 15 in a state where the projecting part of the anchor bolt 3 is covered with the cup-shaped container 13, the inside of the excessive hole 4 of the base plate 2 becomes a vacuum state through an air flow channel 22 on an upper surface of the upper washer 20, and a grout material G is forcibly drawn in to fill a gap around the anchor bolt 3.SELECTED DRAWING: Figure 7
【課題】アンカーボルト挿通孔が過大孔として形成されているベースプレートに作用する地震や風などによるせん断力を適正にアンカーボルトに伝達することができ、コスト面でも改善された露出型柱脚の施工方法を提供する。【解決手段】鉄骨柱の下端部に固着したベースプレート2が、基礎コンクリート9の上面に突出するアンカーボルト3で固定される露出型柱脚の施工において、アンカーボルト3をベースプレート2の過大孔4に挿通し、上座金と下座金からなる入れ子座金5と平座金6を挿通した状態で2個のナット8で締結するとともに、アンカーボルト3の突出部分にカップ状容器13を被せた状態で真空ポンプ15によりカップ状容器13の内部を減圧すると、上座金20上面の空気流路22を介してベースプレート2の過大孔4内が真空状態となってグラウト材Gが強制的に引き入れられ、アンカーボルト3の周囲の隙間を充填する。【選択図】図7
METHOD FOR CONSTRUCTING EXPOSED-TYPE COLUMN BASE
To provide a method for constructing an exposed-type column base capable of properly transmitting a shearing force caused by an earthquake, wind or the like acting on a base plate in which an anchor bolt insertion hole is formed as an excessive hole to an anchor bolt, and improving the cost.SOLUTION: In a construction of an exposed-type column base in which a base plate 2 fixed to a lower end of a steel column is fixed by anchor bolts 3 projecting to an upper surface of foundation concrete 9, the anchor bolt 3 is inserted into an excessive hole 4 of the base plate 2, and fastened with two nuts 8 in a state where a nested washer 5 and a flat washer 6 composed of an upper washer and a lower washer are inserted; and when the inside of a cup-shaped container 13 is decompressed by a vacuum pump 15 in a state where the projecting part of the anchor bolt 3 is covered with the cup-shaped container 13, the inside of the excessive hole 4 of the base plate 2 becomes a vacuum state through an air flow channel 22 on an upper surface of the upper washer 20, and a grout material G is forcibly drawn in to fill a gap around the anchor bolt 3.SELECTED DRAWING: Figure 7
【課題】アンカーボルト挿通孔が過大孔として形成されているベースプレートに作用する地震や風などによるせん断力を適正にアンカーボルトに伝達することができ、コスト面でも改善された露出型柱脚の施工方法を提供する。【解決手段】鉄骨柱の下端部に固着したベースプレート2が、基礎コンクリート9の上面に突出するアンカーボルト3で固定される露出型柱脚の施工において、アンカーボルト3をベースプレート2の過大孔4に挿通し、上座金と下座金からなる入れ子座金5と平座金6を挿通した状態で2個のナット8で締結するとともに、アンカーボルト3の突出部分にカップ状容器13を被せた状態で真空ポンプ15によりカップ状容器13の内部を減圧すると、上座金20上面の空気流路22を介してベースプレート2の過大孔4内が真空状態となってグラウト材Gが強制的に引き入れられ、アンカーボルト3の周囲の隙間を充填する。【選択図】図7
METHOD FOR CONSTRUCTING EXPOSED-TYPE COLUMN BASE
露出型柱脚の施工方法