A platform for research: civil engineering, architecture and urbanism
PILE INSTALLATION METHOD
To provide a pile installation method capable of reducing a work inside an underground pit.SOLUTION: A pile installation method comprises the steps of: drilling a slab 14 of an underground skeleton to form an insertion hole 14B penetrating from above ground to an underground pit; inserting a pile 30 into the insertion hole 14B; and placing concrete into the underground pit P where a tip of the pile 30 is inserted.SELECTED DRAWING: Figure 5
【課題】地下ピット内での作業を削減できる杭の設置方法を提供する。【解決手段】杭の設置方法は、地下躯体のスラブ14を穿孔して地上から地下ピットまで貫通する挿入孔14Bを形成する工程と、挿入孔14Bへ杭30を挿入する工程と、杭30の先端が挿入された地下ピットPへコンクリートを打設する工程と、を備えている。【選択図】図5
PILE INSTALLATION METHOD
To provide a pile installation method capable of reducing a work inside an underground pit.SOLUTION: A pile installation method comprises the steps of: drilling a slab 14 of an underground skeleton to form an insertion hole 14B penetrating from above ground to an underground pit; inserting a pile 30 into the insertion hole 14B; and placing concrete into the underground pit P where a tip of the pile 30 is inserted.SELECTED DRAWING: Figure 5
【課題】地下ピット内での作業を削減できる杭の設置方法を提供する。【解決手段】杭の設置方法は、地下躯体のスラブ14を穿孔して地上から地下ピットまで貫通する挿入孔14Bを形成する工程と、挿入孔14Bへ杭30を挿入する工程と、杭30の先端が挿入された地下ピットPへコンクリートを打設する工程と、を備えている。【選択図】図5
PILE INSTALLATION METHOD
杭の設置方法
SATO TAKAYUKI (author) / TAKEDA TSUTOMU (author) / TADAISHI KYOTA (author)
2021-07-01
Patent
Electronic Resource
Japanese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2024
|PILE INSTALLATION POSITION TEACHING DEVICE, AND PILE INSTALLATION METHOD
European Patent Office | 2020
|BATTER PILE INSTALLATION CRADLE AND BATTER PILE INSTALLATION METHOD
European Patent Office | 2021
|