FLOOR SLAB REPLACING METHOD
To provide a floor slab replacement method capable of opening traffic without carrying out reinforcement work even in the middle of the floor slab replacement work of an existing composite girder and minimizing a traffic blocking period.SOLUTION: In a floor slab replacing method for removing an existing floor slab 3a of an existing composite girder and sequentially replacing it with a new floor slab 3b, a temporary floor slab 5 having strength capable of being regarded as a rigid body against a force acting in a bridge axis direction is installed at a removal place of the existing floor slab 3a at least on a main girder 2, and an axial force is transmitted to the existing floor slab 3a before removal and the new floor slab 3b via the temporary floor slab 5 on the main girder 2.SELECTED DRAWING: Figure 4
【課題】既設合成桁の床版取替え工事の途中であっても、補強工事を行うことなく交通を開放でき、交通遮断期間を最小限にすることができる床版取替工法を提供する。【解決手段】既設合成桁の既設床版3aを撤去して新設床版3bに順次取替える床版取替工法であって、少なくとも主桁2上において、橋軸方向に作用する力に対して剛体とみなすことができる強度を備えた仮設床版5を既設床版3aの撤去箇所に設置し、主桁2上において、撤去前の既設床版3aと新設床版3bとに仮設床版5を介して軸力を伝達させる。【選択図】図4
FLOOR SLAB REPLACING METHOD
To provide a floor slab replacement method capable of opening traffic without carrying out reinforcement work even in the middle of the floor slab replacement work of an existing composite girder and minimizing a traffic blocking period.SOLUTION: In a floor slab replacing method for removing an existing floor slab 3a of an existing composite girder and sequentially replacing it with a new floor slab 3b, a temporary floor slab 5 having strength capable of being regarded as a rigid body against a force acting in a bridge axis direction is installed at a removal place of the existing floor slab 3a at least on a main girder 2, and an axial force is transmitted to the existing floor slab 3a before removal and the new floor slab 3b via the temporary floor slab 5 on the main girder 2.SELECTED DRAWING: Figure 4
【課題】既設合成桁の床版取替え工事の途中であっても、補強工事を行うことなく交通を開放でき、交通遮断期間を最小限にすることができる床版取替工法を提供する。【解決手段】既設合成桁の既設床版3aを撤去して新設床版3bに順次取替える床版取替工法であって、少なくとも主桁2上において、橋軸方向に作用する力に対して剛体とみなすことができる強度を備えた仮設床版5を既設床版3aの撤去箇所に設置し、主桁2上において、撤去前の既設床版3aと新設床版3bとに仮設床版5を介して軸力を伝達させる。【選択図】図4
FLOOR SLAB REPLACING METHOD
床版取替工法
OBA SEIDO (author) / OKA SHIGEHIRO (author) / IWAKI TAKAYUKI (author) / NAKADA TAKAFUMI (author)
2022-01-13
Patent
Electronic Resource
Japanese
IPC:
E01D
BRIDGES
,
Brücken
FLOOR SLAB REPLACING STRUCTURE AND FLOOR SLAB REPLACING METHOD