A platform for research: civil engineering, architecture and urbanism
BUILDING RELOCATION METHOD
To provide a building relocation method capable of efficiently relocating a building.SOLUTION: A method of relocating a structure, in which a structure 1 is cut along at least a horizontal cutting line L1 and divided into a plurality of structures 2, and the divided structures 2 are lifted and relocated by a crane, includes: a hole drilling step of drilling a through-hole 11 on the horizontal cutting line L1 of the structure 1 before cutting the structure 1; an insertion frame installing step of inserting and installing an insertion frame in the through-hole 11; a hanging frame connecting step of connecting a hanging frame to an insertion frame; a cutting step of cutting a building 1 along the horizontal cutting line L1 in a state in which an upper part of the hanging frame is hung and supported by the crane; and a lifting step of lifting the hanging frame by the crane in a state in which the structures 2 divided by the cutting are held by the hanging frame.SELECTED DRAWING: Figure 1
【課題】効率よく建造物を移設することができる建造物の移設工法を提供する。【解決手段】建造物1を少なくとも横切断線L1に沿って切断して複数の構造物2に分割し、当該分割された構造物2をクレーンで揚重して移設する建造物の移設工法において、建造物1を切断する前に、建造物1の横切断線L1上に貫通孔11を穿設する孔穿設工程と、貫通孔11に挿入フレームを挿入して設置する挿入フレーム設置工程と、挿入フレームに吊りフレームを連結する吊りフレーム連結工程と、吊りフレームの上部をクレーンで吊り支持した状態で建造物1を横切断線L1に沿って切断する切断工程と、切断により分割された構造物2を吊りフレームに保持させた状態で、当該吊りフレームをクレーンで揚重する揚重工程と、を実行する【選択図】図1
BUILDING RELOCATION METHOD
To provide a building relocation method capable of efficiently relocating a building.SOLUTION: A method of relocating a structure, in which a structure 1 is cut along at least a horizontal cutting line L1 and divided into a plurality of structures 2, and the divided structures 2 are lifted and relocated by a crane, includes: a hole drilling step of drilling a through-hole 11 on the horizontal cutting line L1 of the structure 1 before cutting the structure 1; an insertion frame installing step of inserting and installing an insertion frame in the through-hole 11; a hanging frame connecting step of connecting a hanging frame to an insertion frame; a cutting step of cutting a building 1 along the horizontal cutting line L1 in a state in which an upper part of the hanging frame is hung and supported by the crane; and a lifting step of lifting the hanging frame by the crane in a state in which the structures 2 divided by the cutting are held by the hanging frame.SELECTED DRAWING: Figure 1
【課題】効率よく建造物を移設することができる建造物の移設工法を提供する。【解決手段】建造物1を少なくとも横切断線L1に沿って切断して複数の構造物2に分割し、当該分割された構造物2をクレーンで揚重して移設する建造物の移設工法において、建造物1を切断する前に、建造物1の横切断線L1上に貫通孔11を穿設する孔穿設工程と、貫通孔11に挿入フレームを挿入して設置する挿入フレーム設置工程と、挿入フレームに吊りフレームを連結する吊りフレーム連結工程と、吊りフレームの上部をクレーンで吊り支持した状態で建造物1を横切断線L1に沿って切断する切断工程と、切断により分割された構造物2を吊りフレームに保持させた状態で、当該吊りフレームをクレーンで揚重する揚重工程と、を実行する【選択図】図1
BUILDING RELOCATION METHOD
建造物の移設工法
MURAKAMI MASATAKE (author) / YOSHIGUCHI KATSUFUMI (author) / INAMOTO TAKAHIKO (author) / UNNO RYOTA (author) / ASAKURA TAKAHIRO (author)
2022-01-13
Patent
Electronic Resource
Japanese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
BUILDING STRUCTURE AND RELOCATION METHOD FOR KITCHEN EQUIPMENT
European Patent Office | 2017