PARTIAL TOP-DOWN CONSTRUCTION METHOD FOR BUILDING UNDERGROUND STRUCTURES
The present invention relates to a partial top-down construction method for constructing an underground structure, wherein a top-down construction method is partially performed when an underground structure is constructed and a bottom-up construction method after excavation is performed for a part of the underground structure. According to the present invention, as a temporary steel frame column is used as a frame of a column of an actual underground structure, there is no need to dismantle the temporary steel frame column. The temporary steel frame column to be used as the actual structure column is reinforced, and a horizontal steel frame structure is constructed using the steel frame column. And, a slab is constructed so that the structure corresponds to earth pressure. The center of the underground structure remains as an open space to be used for a space of underground structure construction. Therefore, work convenience and work conditions are remarkably improved. Also, the temporary steel frame column is hardly used as the structure column due to a design error, and the design error of the temporary steel frame column and the structure column can be removed in the partial top-down construction method. Therefore, the temporary steel frame column can be used as the structure column.
본 발명은, 지하 구조물 구축시 부분적으로 탑다운 공법을 시행하면서 일부는 굴토후의 순타공법을 수행하는 지하 구조물 구축을 위한 부분 탑다운 공법에 관한 것이다. 이러한 본 발명은 가설 철골기둥을 실제 지하 구조물의 구조물 기둥의 뼈대로 사용하여 가설 철골기둥의 해체가 필요없고, 실제 구조물 기둥으로 사용될 가설 철골기둥을 보강하고 그 철골기둥을 이용하여 수평 철골구조물을 축조한 후 슬래브를 구축하여 이러한 구조물에 의해 토압에 대응하도록 하고 지하 구조물의 중앙부는 지하 구조물 구축 공사 공간으로 사용하도록 개방된 공간으로 남겨 두어 작업 편의성 및 작업 여견이 현저히 개선될 수 있으며, 가설 철골기둥을 구조물 기둥으로 사용하기 어려웠던 가설 철골기둥과 구조물 기둥과의 설계 오차를 해소할 수 있어 가설 철골기둥을 그대로 구조물 기둥으로 활용할 수 있다.
PARTIAL TOP-DOWN CONSTRUCTION METHOD FOR BUILDING UNDERGROUND STRUCTURES
The present invention relates to a partial top-down construction method for constructing an underground structure, wherein a top-down construction method is partially performed when an underground structure is constructed and a bottom-up construction method after excavation is performed for a part of the underground structure. According to the present invention, as a temporary steel frame column is used as a frame of a column of an actual underground structure, there is no need to dismantle the temporary steel frame column. The temporary steel frame column to be used as the actual structure column is reinforced, and a horizontal steel frame structure is constructed using the steel frame column. And, a slab is constructed so that the structure corresponds to earth pressure. The center of the underground structure remains as an open space to be used for a space of underground structure construction. Therefore, work convenience and work conditions are remarkably improved. Also, the temporary steel frame column is hardly used as the structure column due to a design error, and the design error of the temporary steel frame column and the structure column can be removed in the partial top-down construction method. Therefore, the temporary steel frame column can be used as the structure column.
본 발명은, 지하 구조물 구축시 부분적으로 탑다운 공법을 시행하면서 일부는 굴토후의 순타공법을 수행하는 지하 구조물 구축을 위한 부분 탑다운 공법에 관한 것이다. 이러한 본 발명은 가설 철골기둥을 실제 지하 구조물의 구조물 기둥의 뼈대로 사용하여 가설 철골기둥의 해체가 필요없고, 실제 구조물 기둥으로 사용될 가설 철골기둥을 보강하고 그 철골기둥을 이용하여 수평 철골구조물을 축조한 후 슬래브를 구축하여 이러한 구조물에 의해 토압에 대응하도록 하고 지하 구조물의 중앙부는 지하 구조물 구축 공사 공간으로 사용하도록 개방된 공간으로 남겨 두어 작업 편의성 및 작업 여견이 현저히 개선될 수 있으며, 가설 철골기둥을 구조물 기둥으로 사용하기 어려웠던 가설 철골기둥과 구조물 기둥과의 설계 오차를 해소할 수 있어 가설 철골기둥을 그대로 구조물 기둥으로 활용할 수 있다.
PARTIAL TOP-DOWN CONSTRUCTION METHOD FOR BUILDING UNDERGROUND STRUCTURES
지하 구조물 구축을 위한 부분 탑다운 공법
PARK KWANG HO (author)
2016-12-16
Patent
Electronic Resource
Korean
Stress Variation of Underground Building Structure during Top-Down Construction
BASE | 2017
|