Reservoir embankment construction method and reservoir embankment waterproof structure
The present invention relates to a reservoir embankment construction method and a waterproof structure for a reservoir embankment which use a waterproof structure to construct a reservoir embankment to prevent a leakage and strengthen an embankment structure. The reservoir embankment construction method forms an inner waterproof layer (20) made of mud on a center in a reservoir embankment, forms an outer waterproof layer (30) made of gravel and rocks on a surface layer of the inner waterproof layer (20), pours pole members (40) of a pile form along a path where the embankment of the reservoir is formed to be continuously erected, installs a fixing member (50) on upper ends of the pole members (40), installs a waterproof sheet (60) on an outer side of the pole members (40), and then completely buries the pole members (40), the fixing member (50), and the waterproof sheet (60) by the mud making up the inner waterproof layer (20) to be fixed by a soil pressure. According to the present invention, a leakage prevention effect of a reservoir embankment is excellent, and structural stability of the embankment is strengthened to prevent erosion or collapse of the embankment. Construction convenience is excellent to allow precise and accurate construction.
본 발명은 차수구조물을 이용해 저수지 제방을 축조하여 누수를 방지하면서 제방 구조를 견고히 할 수 있게 한 저수지 제방 축조 방법 및 저수지 제방용 차수구조물에 관한 것이다.본 발명의 저수지 제방 축조 방법은 저수지 제방의 내부 중앙에 진흙으로 구성되는 내부차수층(20)을 형성하고, 내부차수층(20)의 표층에 자갈과 암석으로 구성되는 외부차수층(30)을 형성하되, 저수지의 제방이 형성되는 경로를 따라서 말뚝 형태로 된 지주부재(40)를 연속적으로 직립되게 타설하고, 상기 지주부재(40) 상단부에는 고정부재(50)를 설치하며, 지주부재(40)의 외측에는 방수시트(60)를 설치한 후, 상기 내부차수층(20)을 구성하는 진흙으로 상기 지주부재(40), 고정부재(50), 방수시트(60)를 완전 매립하여 토압에 의해 고정되게 한 구성이다.본 발명에 따르면, 저수지 제방의 누수 방지 효과가 탁월하고, 제방의 구조적 안정성을 강화하여 제방의 침식이나 붕괴를 방지할 수 있으며, 시공편의성이 우수하여 더욱 정밀하고 정확한 시공이 가능케 되는 효과가 있다.
Reservoir embankment construction method and reservoir embankment waterproof structure
The present invention relates to a reservoir embankment construction method and a waterproof structure for a reservoir embankment which use a waterproof structure to construct a reservoir embankment to prevent a leakage and strengthen an embankment structure. The reservoir embankment construction method forms an inner waterproof layer (20) made of mud on a center in a reservoir embankment, forms an outer waterproof layer (30) made of gravel and rocks on a surface layer of the inner waterproof layer (20), pours pole members (40) of a pile form along a path where the embankment of the reservoir is formed to be continuously erected, installs a fixing member (50) on upper ends of the pole members (40), installs a waterproof sheet (60) on an outer side of the pole members (40), and then completely buries the pole members (40), the fixing member (50), and the waterproof sheet (60) by the mud making up the inner waterproof layer (20) to be fixed by a soil pressure. According to the present invention, a leakage prevention effect of a reservoir embankment is excellent, and structural stability of the embankment is strengthened to prevent erosion or collapse of the embankment. Construction convenience is excellent to allow precise and accurate construction.
본 발명은 차수구조물을 이용해 저수지 제방을 축조하여 누수를 방지하면서 제방 구조를 견고히 할 수 있게 한 저수지 제방 축조 방법 및 저수지 제방용 차수구조물에 관한 것이다.본 발명의 저수지 제방 축조 방법은 저수지 제방의 내부 중앙에 진흙으로 구성되는 내부차수층(20)을 형성하고, 내부차수층(20)의 표층에 자갈과 암석으로 구성되는 외부차수층(30)을 형성하되, 저수지의 제방이 형성되는 경로를 따라서 말뚝 형태로 된 지주부재(40)를 연속적으로 직립되게 타설하고, 상기 지주부재(40) 상단부에는 고정부재(50)를 설치하며, 지주부재(40)의 외측에는 방수시트(60)를 설치한 후, 상기 내부차수층(20)을 구성하는 진흙으로 상기 지주부재(40), 고정부재(50), 방수시트(60)를 완전 매립하여 토압에 의해 고정되게 한 구성이다.본 발명에 따르면, 저수지 제방의 누수 방지 효과가 탁월하고, 제방의 구조적 안정성을 강화하여 제방의 침식이나 붕괴를 방지할 수 있으며, 시공편의성이 우수하여 더욱 정밀하고 정확한 시공이 가능케 되는 효과가 있다.
Reservoir embankment construction method and reservoir embankment waterproof structure
저수지 제방 축조 방법 및 저수지 제방용 차수구조물
KIM KYUNG SOO (author)
2018-02-12
Patent
Electronic Resource
Korean
South Florida Reservoir Embankment Study
NTIS | 2009
|Hugo Reservoir Embankment Depression Study
HENRY – Federal Waterways Engineering and Research Institute (BAW) | 2002
|Subsidence in earth reservoir embankment
Engineering Index Backfile | 1949
|South Florida Reservoir Alternative Embankment Study
British Library Conference Proceedings | 2009
|