METHOD FOR CONSTRUCTING COLLECTING WELLS BASED ON LARGE-SCALE EXCAVATION AND GROUND IMPROVEMENT AND A COLLECTING WELL CONSTRUCTED BY THE METHOD
Disclosed are a method for constructing a suction well using large diameter evacuation and ground improvement, and the suction well constructed through the method. The method for constructing the suction-well comprises: a step of excavating a first well to install a cylindrical pipe-shaped first casing so as to enable a selected circumference of a suction hole installation position to have a portion where is overlapped with the suction hole installation position, filling the inside of the first casing with filter media, and removing the first casing to install a first filter media pillar; a step of repeatedly installing a second filter media pillar having a portion of overlapping with the first filter media pillar in accordance with an installation method of the first filter media pillar to install a plurality of filter media pillars on the circumference of the suction-hole installation position; a step of excavating a second well on the suction-hole installation position surrounded by the filter media pillars to install a cylindrical pipe-shaped second casing, and installing a suction hole screen on an inner wall of the second casing; and a step of removing the second casing.
대구경 굴착과 지반 개량을 활용하는 취수정 시공 방법 및 이 방법에 의해 시공된 취수공이 개시된다. 취수정 시공 방법은, 선정된 취수공 설치 위치 둘레에 취수공 설치 위치와 중첩되는 부분이 있도록 제1 관정을 굴착하고 원통 배관 형태의 제1 케이싱을 설치하고, 제1 케이싱 내부에 여재를 채우고, 제1 케이싱을 제거하여 제1 여재 기둥을 설치하는 단계, 제1 여재 기둥의 설치 방법에 따라 제1 여재 기둥과 중첩되는 부분을 갖는 제2 여재 기둥을 설치하고 이를 반복하여 취수공 설치 위치 둘레에 복수의 여재 기둥들을 설치하는 단계, 복수의 여재 기둥들에 둘러싸인 취수공 설치 위치에 제2 관정을 굴착하고 원통 배관 형태의 제2 케이싱을 설치하고, 제2 케이싱 내벽에 취수공 스크린을 설치하는 단계, 및 제2 케이싱을 제거하는 단계를 포함한다.
METHOD FOR CONSTRUCTING COLLECTING WELLS BASED ON LARGE-SCALE EXCAVATION AND GROUND IMPROVEMENT AND A COLLECTING WELL CONSTRUCTED BY THE METHOD
Disclosed are a method for constructing a suction well using large diameter evacuation and ground improvement, and the suction well constructed through the method. The method for constructing the suction-well comprises: a step of excavating a first well to install a cylindrical pipe-shaped first casing so as to enable a selected circumference of a suction hole installation position to have a portion where is overlapped with the suction hole installation position, filling the inside of the first casing with filter media, and removing the first casing to install a first filter media pillar; a step of repeatedly installing a second filter media pillar having a portion of overlapping with the first filter media pillar in accordance with an installation method of the first filter media pillar to install a plurality of filter media pillars on the circumference of the suction-hole installation position; a step of excavating a second well on the suction-hole installation position surrounded by the filter media pillars to install a cylindrical pipe-shaped second casing, and installing a suction hole screen on an inner wall of the second casing; and a step of removing the second casing.
대구경 굴착과 지반 개량을 활용하는 취수정 시공 방법 및 이 방법에 의해 시공된 취수공이 개시된다. 취수정 시공 방법은, 선정된 취수공 설치 위치 둘레에 취수공 설치 위치와 중첩되는 부분이 있도록 제1 관정을 굴착하고 원통 배관 형태의 제1 케이싱을 설치하고, 제1 케이싱 내부에 여재를 채우고, 제1 케이싱을 제거하여 제1 여재 기둥을 설치하는 단계, 제1 여재 기둥의 설치 방법에 따라 제1 여재 기둥과 중첩되는 부분을 갖는 제2 여재 기둥을 설치하고 이를 반복하여 취수공 설치 위치 둘레에 복수의 여재 기둥들을 설치하는 단계, 복수의 여재 기둥들에 둘러싸인 취수공 설치 위치에 제2 관정을 굴착하고 원통 배관 형태의 제2 케이싱을 설치하고, 제2 케이싱 내벽에 취수공 스크린을 설치하는 단계, 및 제2 케이싱을 제거하는 단계를 포함한다.
METHOD FOR CONSTRUCTING COLLECTING WELLS BASED ON LARGE-SCALE EXCAVATION AND GROUND IMPROVEMENT AND A COLLECTING WELL CONSTRUCTED BY THE METHOD
대구경 굴착과 지반 개량을 활용하는 취수정 시공 방법 및 이 방법에 의해 시공된 취수정
JUNG JAE HOON (author)
2018-03-12
Patent
Electronic Resource
Korean
IPC:
E03B
Anlagen oder Verfahren zum Gewinnen, Sammeln oder Verteilen von Wasser
,
INSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
Method for constructing ballastless track railroad bed water-collecting well