A platform for research: civil engineering, architecture and urbanism
Method of Constructing Concrete Girder by Multi-tension
The present invention relates to a construction method for a concrete girder bridge. The construction method for the concrete girder bridge comprises: a concrete girder member manufacturing step of manufacturing a linear concrete girder member; a sheathing pipe installing step of installing a sheathing pipe by being arranged in a longitudinal direction of the concrete girder member; a tensioning steel material paving step of paving a tensioning steel material for prestressing on the sheathing pipe; an anchoring unit installing step of installing an anchoring unit to anchor the tensioning steel material paved on the sheathing pipe in the concrete girder member; a post-tensioning step of applying prestressed tension to the concrete girder member by a method of tensioning the tensioning steel material for the prestressing paved in the sheathing pipe using the anchoring unit installed in the anchoring unit installing step; a concrete girder member placing step of placing the concrete girder member manufactured on a bridge pier; and a slab forming step of forming a concrete slab on the concrete girder member placed in the bridge pier. As such, the construction method for the concrete girder bridge is able to apply prestressed tension to the concrete slab and is able to increase the prestressed tension capable of being applied to the concrete girder member. The construction method for the concrete girder bridge is able to facilitate work for tensioning the tensioning steel material for the prestressing.
본 발명은 콘크리트거더교량축조방법에 관한 것으로서, 직선상의 콘크리트거더부재를 제작하는 콘크리트거더부재제작단계와, 상기 콘크리트거더부재의 길이방향을 따라 배치되도록 쉬스관을 설치하는 쉬스관설치단계와, 상기 쉬스관에 프리스트레싱용 긴장강재를 포설하는 긴장강재포설단계와, 상기 쉬스관에 포설된 긴장강재를 정착하기 위한 정착구를 상기 콘크리트거더부재에 설치하는 정착구설치단계와, 상기 정착구설치단계에서 설치된 정착구를 이용하여 상기 쉬스관에 포설된 프리스트레싱용 긴장강재를 인장하는 방법으로 상기 콘크리트거더부재에 프리스트레스응력을 도입하는 포스트텐싱단계와, 상기 제작된 콘크리트거더부재를 교각에 거치하는 콘크리트거더부재거치단계와, 상기 교각에 거치된 콘크리트거더부재에 콘크리트슬래브를 형성하는 슬래브형성단계를 포함하는 콘크리트거더교량축조방법에 있어서, 상기 쉬스관설치단계는 상기 콘크리트거더부재의 길이방향을 따라 매설되고 양 종단이 상기 콘크리트거더부재의 양 종단면을 향해 배치되는 종단면쉬스관과 상기 콘크리트거더부재의 길이방향을 따라 매설되고 양 종단이 상기 콘크리트거더부재의 상면을 향해 배치되는 적어도 하나의 상면쉬스관을 갖도록 실시되고; 상기 슬래브형성단계는 상기 콘크리트슬래브의 상면을 넘어 돌출되지 않도록 정착구를 설치하기 위한 정착구홈을 갖도록 실시되고; 상기 긴장강재포설단계는 상기 종단면쉬스관과 상기 상면쉬스관에 프리스트레싱용 긴장강재가 포설되도록 실시되고; 상기 정착구설치단계는 상기 종단면쉬스관에 대응하는 정착구를 상기 콘크리트슬래브를 형성하기 전에 상기 콘크리트거더부재의 종단면에 설치하는 슬래브형성전정착구설치단계와, 상기 상면쉬스관에 대응하는 정착구를 상기 콘크리트슬래브를 형성한 후에 상기 정착구홈에 설치하는 슬래브형성후정착구설치단계를 포함하고; 상기 포스트텐싱단계는 상기 슬래브형성전정착구설치단계에서 설치된 정착구를 이용하여 상기 종단면쉬스관에 포설된 프리스트레싱용 긴장강재를 상기 콘크리트슬래브를 형성하기 전에 인장하는 방법으로 상기 콘크리트거더부재에 프리스트레스응력을 도입하는 슬래브형성전포스트텐싱단계와, 상기 슬래브형성후정착구설치단계에서 설치된 정착구를 이용하여 상기 상면쉬스관에 포설된 프리스트레싱용 긴장강재를 상기 콘크리트슬래브를 형성한 후에 인장하는 방법으로 상기 콘크리트거더부재와 상기 콘크리트슬래브에 프리스트레스응력을 도입하는 슬래브형성후포스트텐싱단계를 포함하고; 상기 콘크리트슬래브의 상면이 평탄해지도록 상기 정착구홈을 메우는 슬래브마무리단계를 포함하는 것을 특징으로 한다. 이에 의해, 콘크리트슬래브에 프리스트레스응력을 도입할 수 있고, 콘크리트거더부재에 도입할 수 있는 프리스트레스응력을 증가시킬 수 있으며, 프리스트레싱용 긴장강재를 인장하는 작업이 용이해진다.
Method of Constructing Concrete Girder by Multi-tension
The present invention relates to a construction method for a concrete girder bridge. The construction method for the concrete girder bridge comprises: a concrete girder member manufacturing step of manufacturing a linear concrete girder member; a sheathing pipe installing step of installing a sheathing pipe by being arranged in a longitudinal direction of the concrete girder member; a tensioning steel material paving step of paving a tensioning steel material for prestressing on the sheathing pipe; an anchoring unit installing step of installing an anchoring unit to anchor the tensioning steel material paved on the sheathing pipe in the concrete girder member; a post-tensioning step of applying prestressed tension to the concrete girder member by a method of tensioning the tensioning steel material for the prestressing paved in the sheathing pipe using the anchoring unit installed in the anchoring unit installing step; a concrete girder member placing step of placing the concrete girder member manufactured on a bridge pier; and a slab forming step of forming a concrete slab on the concrete girder member placed in the bridge pier. As such, the construction method for the concrete girder bridge is able to apply prestressed tension to the concrete slab and is able to increase the prestressed tension capable of being applied to the concrete girder member. The construction method for the concrete girder bridge is able to facilitate work for tensioning the tensioning steel material for the prestressing.
본 발명은 콘크리트거더교량축조방법에 관한 것으로서, 직선상의 콘크리트거더부재를 제작하는 콘크리트거더부재제작단계와, 상기 콘크리트거더부재의 길이방향을 따라 배치되도록 쉬스관을 설치하는 쉬스관설치단계와, 상기 쉬스관에 프리스트레싱용 긴장강재를 포설하는 긴장강재포설단계와, 상기 쉬스관에 포설된 긴장강재를 정착하기 위한 정착구를 상기 콘크리트거더부재에 설치하는 정착구설치단계와, 상기 정착구설치단계에서 설치된 정착구를 이용하여 상기 쉬스관에 포설된 프리스트레싱용 긴장강재를 인장하는 방법으로 상기 콘크리트거더부재에 프리스트레스응력을 도입하는 포스트텐싱단계와, 상기 제작된 콘크리트거더부재를 교각에 거치하는 콘크리트거더부재거치단계와, 상기 교각에 거치된 콘크리트거더부재에 콘크리트슬래브를 형성하는 슬래브형성단계를 포함하는 콘크리트거더교량축조방법에 있어서, 상기 쉬스관설치단계는 상기 콘크리트거더부재의 길이방향을 따라 매설되고 양 종단이 상기 콘크리트거더부재의 양 종단면을 향해 배치되는 종단면쉬스관과 상기 콘크리트거더부재의 길이방향을 따라 매설되고 양 종단이 상기 콘크리트거더부재의 상면을 향해 배치되는 적어도 하나의 상면쉬스관을 갖도록 실시되고; 상기 슬래브형성단계는 상기 콘크리트슬래브의 상면을 넘어 돌출되지 않도록 정착구를 설치하기 위한 정착구홈을 갖도록 실시되고; 상기 긴장강재포설단계는 상기 종단면쉬스관과 상기 상면쉬스관에 프리스트레싱용 긴장강재가 포설되도록 실시되고; 상기 정착구설치단계는 상기 종단면쉬스관에 대응하는 정착구를 상기 콘크리트슬래브를 형성하기 전에 상기 콘크리트거더부재의 종단면에 설치하는 슬래브형성전정착구설치단계와, 상기 상면쉬스관에 대응하는 정착구를 상기 콘크리트슬래브를 형성한 후에 상기 정착구홈에 설치하는 슬래브형성후정착구설치단계를 포함하고; 상기 포스트텐싱단계는 상기 슬래브형성전정착구설치단계에서 설치된 정착구를 이용하여 상기 종단면쉬스관에 포설된 프리스트레싱용 긴장강재를 상기 콘크리트슬래브를 형성하기 전에 인장하는 방법으로 상기 콘크리트거더부재에 프리스트레스응력을 도입하는 슬래브형성전포스트텐싱단계와, 상기 슬래브형성후정착구설치단계에서 설치된 정착구를 이용하여 상기 상면쉬스관에 포설된 프리스트레싱용 긴장강재를 상기 콘크리트슬래브를 형성한 후에 인장하는 방법으로 상기 콘크리트거더부재와 상기 콘크리트슬래브에 프리스트레스응력을 도입하는 슬래브형성후포스트텐싱단계를 포함하고; 상기 콘크리트슬래브의 상면이 평탄해지도록 상기 정착구홈을 메우는 슬래브마무리단계를 포함하는 것을 특징으로 한다. 이에 의해, 콘크리트슬래브에 프리스트레스응력을 도입할 수 있고, 콘크리트거더부재에 도입할 수 있는 프리스트레스응력을 증가시킬 수 있으며, 프리스트레싱용 긴장강재를 인장하는 작업이 용이해진다.
Method of Constructing Concrete Girder by Multi-tension
다차긴장을 이용한 콘크리트거더교량축조방법
MIN JI HOON (author)
2017-09-20
Patent
Electronic Resource
Korean
IPC:
E01D
BRIDGES
,
Brücken
European Patent Office | 2021
|PRESTRESSED CONCRETE GIRDER AND METHOD CONSTRUCTING THE GIRDER BRIDGE USING THE SAME
European Patent Office | 2015
|METHOD AND STRUCTURE OF CONSTRUCTING CONCRETE GIRDER BRIDGE
European Patent Office | 2018
|European Patent Office | 2016
|SEGMENTAL PRESTRESSED CONCRETE GIRDER AND METHOD FOR CONSTRUCTING SAME
European Patent Office | 2016
|