Construction method of pile using gelled soil
The present invention relates to a method of constructing a non-displacement pile by gelled soil, which is able to insert the pile into gelled soil, which is formed by agitating relaxed soil with a gelling agent in accordance with rotation and insertion of an agitation equipment, to settle the pile on a supporting ground, and to minimize an impact on the surrounding ground by preventing excavation soil from being generated in case of a construction of the pile, thereby greatly reducing a pile construction period at the same time. The method includes (a) a step of measuring a position to construct the pile; (b) a step of non-displacement excavating the position measured at the step (a) at a point of a support ground by an excavation rod with a screw provided on an outer peripheral surface of a main pipe; (c) a step of inserting an agitation equipment into a drilled hole excavated at the step (c), and agitating the relaxed soil and the gelling agent by spraying the gelling agent, and temporarily gelling the soil; (d) a step of inserting the pile into the gelled soil by its own load and settling the pile on the supporting ground; and (e) a step of curing the gelled soil to fixate the pile. The gelling agent contains 35 to 60 wt% of inorganic binding material, 20 to 45 wt% of water, and 0.15 to 7 wt% of dispersion. The displacement excavation has a center pipe having a flow path for supplying the gelling agent in a longitudinal direction and a plurality of spray holes communicating with the flow path to spray the gelling agent, an agitation wing protruding from an outside of the center pipe, and an excavation bit engaged to a front end of the center pipe.
본 발명은 지반의 비배토 굴착 후 교반장비로 겔화제를 분사 및 토사와 교반하여 형성된 겔화된 토사에 파일을 근입하여 지지 지반에 안착시킴으로써, 파일 매입 시공시 굴착토가 발생하지 않아 주변 지반에 미치는 영향을 최소화함과 동시에 파일 시공 기간을 단축할 수 있는 토사 겔화를 이용한 비배토 굴착 파일 시공 방법에 대한 것이다. 본 발명은 지반에 파일을 근입하기 위한 것으로, (a) 파일이 시공될 위치를 측량하는 단계; (b) 메인관의 외주면에 스크류가 형성된 굴착로드를 이용하여 상기 (a) 단계에서 측량된 지점을 지지 지반까지 비배토 굴착하는 단계; (c) 굴착된 천공홀 내에 교반장비를 삽입하여 겔화제를 분사하면서 천공홀 내 토사와 겔화제를 반복적으로 교반하여 겔(gel)화된 토사로 만드는 단계; (d) 상기 겔화된 토사에 파일을 자중에 의해 근입하여 파일을 지지 지반 상에 안착시키는 단계; 및 (e) 겔화된 토사를 양생하여 상기 파일을 고정하는 단계; 를 포함하여 구성되되, 상기 겔화제는 무기결합재 35~60중량%, 물 20~45중량% 및 분산제 0.15~7%를 포함하여 구성되고, 상기 교반장비는 내부에 길이 방향으로 상기 겔화제가 공급되는 유로가 형성되고 외주면에 상기 유로와 연통되어 겔화제를 분사하는 복수의 분사구가 형성된 중앙관 및 상기 중앙관의 외부에 돌출 형성되는 교반 날개로 구성되는 것을 특징으로 한다.
Construction method of pile using gelled soil
The present invention relates to a method of constructing a non-displacement pile by gelled soil, which is able to insert the pile into gelled soil, which is formed by agitating relaxed soil with a gelling agent in accordance with rotation and insertion of an agitation equipment, to settle the pile on a supporting ground, and to minimize an impact on the surrounding ground by preventing excavation soil from being generated in case of a construction of the pile, thereby greatly reducing a pile construction period at the same time. The method includes (a) a step of measuring a position to construct the pile; (b) a step of non-displacement excavating the position measured at the step (a) at a point of a support ground by an excavation rod with a screw provided on an outer peripheral surface of a main pipe; (c) a step of inserting an agitation equipment into a drilled hole excavated at the step (c), and agitating the relaxed soil and the gelling agent by spraying the gelling agent, and temporarily gelling the soil; (d) a step of inserting the pile into the gelled soil by its own load and settling the pile on the supporting ground; and (e) a step of curing the gelled soil to fixate the pile. The gelling agent contains 35 to 60 wt% of inorganic binding material, 20 to 45 wt% of water, and 0.15 to 7 wt% of dispersion. The displacement excavation has a center pipe having a flow path for supplying the gelling agent in a longitudinal direction and a plurality of spray holes communicating with the flow path to spray the gelling agent, an agitation wing protruding from an outside of the center pipe, and an excavation bit engaged to a front end of the center pipe.
본 발명은 지반의 비배토 굴착 후 교반장비로 겔화제를 분사 및 토사와 교반하여 형성된 겔화된 토사에 파일을 근입하여 지지 지반에 안착시킴으로써, 파일 매입 시공시 굴착토가 발생하지 않아 주변 지반에 미치는 영향을 최소화함과 동시에 파일 시공 기간을 단축할 수 있는 토사 겔화를 이용한 비배토 굴착 파일 시공 방법에 대한 것이다. 본 발명은 지반에 파일을 근입하기 위한 것으로, (a) 파일이 시공될 위치를 측량하는 단계; (b) 메인관의 외주면에 스크류가 형성된 굴착로드를 이용하여 상기 (a) 단계에서 측량된 지점을 지지 지반까지 비배토 굴착하는 단계; (c) 굴착된 천공홀 내에 교반장비를 삽입하여 겔화제를 분사하면서 천공홀 내 토사와 겔화제를 반복적으로 교반하여 겔(gel)화된 토사로 만드는 단계; (d) 상기 겔화된 토사에 파일을 자중에 의해 근입하여 파일을 지지 지반 상에 안착시키는 단계; 및 (e) 겔화된 토사를 양생하여 상기 파일을 고정하는 단계; 를 포함하여 구성되되, 상기 겔화제는 무기결합재 35~60중량%, 물 20~45중량% 및 분산제 0.15~7%를 포함하여 구성되고, 상기 교반장비는 내부에 길이 방향으로 상기 겔화제가 공급되는 유로가 형성되고 외주면에 상기 유로와 연통되어 겔화제를 분사하는 복수의 분사구가 형성된 중앙관 및 상기 중앙관의 외부에 돌출 형성되는 교반 날개로 구성되는 것을 특징으로 한다.
Construction method of pile using gelled soil
토사 겔화를 이용한 비배토 굴착 파일 시공 방법
SONG KI YONG (author) / JANG SOON HO (author)
2018-07-25
Patent
Electronic Resource
Korean
Construction method of non-displacement pile by gelled soil
European Patent Office | 2018
|Stepped gelled sand gravel protective embankment and construction method
European Patent Office | 2023
|PILE CONSTRUCTION METHOD USING SOIL AND GROUTING MATERIAL
European Patent Office | 2016
|