Construction method of precast concrete column
A precast concrete column construction method is disclosed. According to one aspect of the present invention, provided is a precast concrete column construction method including preparing a mold for a bottom pad at a factory and pouring and curing concrete to produce a bottom pad for match casting on an upper surface; forming a column segment mold at a factory with the top surface of the bottom pad as a bottom surface so as to match-cast the upper surface of the bottom pad and pouring and curing concrete to form a column segment; separating the column segment from the bottom pad and transporting the bottom pad to a construction site; installing a support structure supporting the bottom pad at the construction site and a concrete foundation mold to surround the support structure; lifting the bottom pad carried to the construction site over the support structure; and pouring and curing concrete in the concrete foundation mold to form a concrete base.
프리캐스트 콘크리트 기둥 시공 방법이 개시된다. 본 발명의 일 측면에 따르면, 프리캐스트 콘크리트 기둥 시공 방법으로서, 공장에서 저부패드용 거푸집을 가설하고 콘크리트를 타설하고 양생하여 상면의 매치 캐스팅(match casting)를 위한 저부패드를 제작하는 단계와; 공장에서 상기 저부패드의 상면과 매스 캐스팅(match casting)이 되도록 상기 저부패드의 상면을 바닥면으로 하여 기둥 세그먼트용 거푸집을 형성하고 콘크리트를 타설하고 양생하여 기둥 세그먼트를 제작하는 단계와; 상기 저부패드에서 상기 기둥 세그먼트를 분리하고, 상기 저부패드를 시공 현장으로 운송하는 단계와; 시공 현장에서 상기 저부패드를 지지하는 지지구조체와, 상기 지지구조체를 포위하도록 콘크리트 기초용 거푸집을 설치하는 단계와; 시공 현장으로 운송된 상기 저부패드를 상기 지지구조체 상부에 인양하는 단계와; 상기 콘크리트 기초용 거푸집에 콘크리트를 타설하고 양생하여, 콘크리트 기초를 형성하는 단계를 포함하는, 프리캐스트 콘크리트 기둥 시공 방법이 제공된다.
Construction method of precast concrete column
A precast concrete column construction method is disclosed. According to one aspect of the present invention, provided is a precast concrete column construction method including preparing a mold for a bottom pad at a factory and pouring and curing concrete to produce a bottom pad for match casting on an upper surface; forming a column segment mold at a factory with the top surface of the bottom pad as a bottom surface so as to match-cast the upper surface of the bottom pad and pouring and curing concrete to form a column segment; separating the column segment from the bottom pad and transporting the bottom pad to a construction site; installing a support structure supporting the bottom pad at the construction site and a concrete foundation mold to surround the support structure; lifting the bottom pad carried to the construction site over the support structure; and pouring and curing concrete in the concrete foundation mold to form a concrete base.
프리캐스트 콘크리트 기둥 시공 방법이 개시된다. 본 발명의 일 측면에 따르면, 프리캐스트 콘크리트 기둥 시공 방법으로서, 공장에서 저부패드용 거푸집을 가설하고 콘크리트를 타설하고 양생하여 상면의 매치 캐스팅(match casting)를 위한 저부패드를 제작하는 단계와; 공장에서 상기 저부패드의 상면과 매스 캐스팅(match casting)이 되도록 상기 저부패드의 상면을 바닥면으로 하여 기둥 세그먼트용 거푸집을 형성하고 콘크리트를 타설하고 양생하여 기둥 세그먼트를 제작하는 단계와; 상기 저부패드에서 상기 기둥 세그먼트를 분리하고, 상기 저부패드를 시공 현장으로 운송하는 단계와; 시공 현장에서 상기 저부패드를 지지하는 지지구조체와, 상기 지지구조체를 포위하도록 콘크리트 기초용 거푸집을 설치하는 단계와; 시공 현장으로 운송된 상기 저부패드를 상기 지지구조체 상부에 인양하는 단계와; 상기 콘크리트 기초용 거푸집에 콘크리트를 타설하고 양생하여, 콘크리트 기초를 형성하는 단계를 포함하는, 프리캐스트 콘크리트 기둥 시공 방법이 제공된다.
Construction method of precast concrete column
프리캐스트 콘크리트 기둥 시공 방법
SHIM CHANG SU (author) / PARK SEUNG JUN (author)
2019-03-08
Patent
Electronic Resource
Korean
European Patent Office | 2025
Precast concrete column structure and construction method thereof
European Patent Office | 2020
|