Method for tunnel construction using grouting technology
The present invention relates to a method for tunnel construction using a grouting method, which inserts a grout steel pipe into the ground in which a tunnel is to be excavated, before a grouting material is injected through the grout steel pipe, thereby reinforcing the ground of a tunnel section that is to be excavated and constructing the tunnel, and comprises: a step (a) that a grout steel pipe with a length corresponding to a reinforcing section length (L) is inserted at a predetermined angle with respect to a tunnel excavation direction, before a grouting material is injected into the grout steel pipe and the grouting material is cured for a predetermined reference curing time; a step (b) which is a step that an initial excavation is performed from a starting point of tunnel excavation to a section corresponding to the length of (L/2) - (ΔB), wherein (L/2) is a unit excavation section, and a section corresponding to (ΔB) has a predetermined length with respect to a distal end section of the unit excavation section (L/2) which can be immediately excavated because the grouting material is cured in the step (a); and a step (c) that, after the step (b), the grouting method is repeated with respect to each of the remaining unit excavation sections to construct a remaining tunnel section. When the grouting method is applied to each of the remaining unit excavation sections, the grout steel pipe inserted into the ground has a length corresponding to the reinforcing section length (L) + (ΔB). Resultantly, after the grouting material is inserted into the grout steel pipe, an excavation process is seamlessly performed without the curing process of the grouting material being performed.
본 발명은, 그라우트 강관을 터널 굴착 지반에 삽입한 후 상기 그라우트 강관을 통해 그라우트재를 주입하여 굴착 공사가 진행될 터널 구간의 지반을 보강하고 터널을 시공하는 그라우트 공법을 이용한 터널 시공 방법에 있어서, (a) 보강 구간 길이 L에 대응되는 길이를 가진 그라우트 강관을 터널 굴착 방향과 소정 각도로 삽입한 후 상기 그라우트 강관에 그라우재를 주입하고 미리 정한 기준 양생 시간 동안 그라우트재를 양생하는 단계; (b) 상기 터널 굴착 시작 지점부터 L/2-△B의 길이에 해당하는 구간까지 초기 굴착을 진행하는 단계로서, L/2은 단위 굴착 구간이고 상기 △B에 해당하는 구간은 상기 (a) 단계에서 이루어진 그라우트재의 양생으로 인해 굴착이 바로 가능한 상기 단위 굴착 구간 L/2의 말단 구간에 대해 미리 설정된 길이를 가지는 것이 특징인 단계; 및 (c) 상기 (b) 단계 이후에, 그라우트 공법을 남아 있는 단위 굴착 구간의 각각에 대해 반복함으로써 잔여 터널 구간을 시공하는 단계를 포함하고, 상기 그라우트 공법을 남아 있는 각각의 단위 굴착 구간에 적용함에 있어서 지반에 삽입되는 그라우트 강관은 보강 구간 길이 L+△B에 대응되는 길이를 가지며, 그라우트 강관에 그라우트재를 주입한 후 그라우트재의 양생 과정을 진행하지 않고 굴착 공정을 무순단으로 진행하는 것을 특징으로 한다.
Method for tunnel construction using grouting technology
The present invention relates to a method for tunnel construction using a grouting method, which inserts a grout steel pipe into the ground in which a tunnel is to be excavated, before a grouting material is injected through the grout steel pipe, thereby reinforcing the ground of a tunnel section that is to be excavated and constructing the tunnel, and comprises: a step (a) that a grout steel pipe with a length corresponding to a reinforcing section length (L) is inserted at a predetermined angle with respect to a tunnel excavation direction, before a grouting material is injected into the grout steel pipe and the grouting material is cured for a predetermined reference curing time; a step (b) which is a step that an initial excavation is performed from a starting point of tunnel excavation to a section corresponding to the length of (L/2) - (ΔB), wherein (L/2) is a unit excavation section, and a section corresponding to (ΔB) has a predetermined length with respect to a distal end section of the unit excavation section (L/2) which can be immediately excavated because the grouting material is cured in the step (a); and a step (c) that, after the step (b), the grouting method is repeated with respect to each of the remaining unit excavation sections to construct a remaining tunnel section. When the grouting method is applied to each of the remaining unit excavation sections, the grout steel pipe inserted into the ground has a length corresponding to the reinforcing section length (L) + (ΔB). Resultantly, after the grouting material is inserted into the grout steel pipe, an excavation process is seamlessly performed without the curing process of the grouting material being performed.
본 발명은, 그라우트 강관을 터널 굴착 지반에 삽입한 후 상기 그라우트 강관을 통해 그라우트재를 주입하여 굴착 공사가 진행될 터널 구간의 지반을 보강하고 터널을 시공하는 그라우트 공법을 이용한 터널 시공 방법에 있어서, (a) 보강 구간 길이 L에 대응되는 길이를 가진 그라우트 강관을 터널 굴착 방향과 소정 각도로 삽입한 후 상기 그라우트 강관에 그라우재를 주입하고 미리 정한 기준 양생 시간 동안 그라우트재를 양생하는 단계; (b) 상기 터널 굴착 시작 지점부터 L/2-△B의 길이에 해당하는 구간까지 초기 굴착을 진행하는 단계로서, L/2은 단위 굴착 구간이고 상기 △B에 해당하는 구간은 상기 (a) 단계에서 이루어진 그라우트재의 양생으로 인해 굴착이 바로 가능한 상기 단위 굴착 구간 L/2의 말단 구간에 대해 미리 설정된 길이를 가지는 것이 특징인 단계; 및 (c) 상기 (b) 단계 이후에, 그라우트 공법을 남아 있는 단위 굴착 구간의 각각에 대해 반복함으로써 잔여 터널 구간을 시공하는 단계를 포함하고, 상기 그라우트 공법을 남아 있는 각각의 단위 굴착 구간에 적용함에 있어서 지반에 삽입되는 그라우트 강관은 보강 구간 길이 L+△B에 대응되는 길이를 가지며, 그라우트 강관에 그라우트재를 주입한 후 그라우트재의 양생 과정을 진행하지 않고 굴착 공정을 무순단으로 진행하는 것을 특징으로 한다.
Method for tunnel construction using grouting technology
그라우트 공법을 이용한 터널 시공 방법
SONG YOUNG SU (author)
2019-12-30