A platform for research: civil engineering, architecture and urbanism
Cast-in-place pile using reinforced grouting and construction method
The present invention relates to a construction method of an in-situ pile using reinforcing grouting. The construction method of an in-situ pile using reinforcing grouting comprises: a first step of excavating ground in a longitudinal direction which is a vertical direction with or without insertion of a casing; a second step of inserting a reinforcing bar cage including a reinforcing bar mesh including axial bars circumferentially separated from each other and installed in the longitudinal direction and stirrups binding the axial bars in a lateral direction which is a horizontal direction, and injection pipes coupled to the axial bars and the stirrups and installed in the longitudinal direction, wherein lower portions thereof are connected to each other, into an excavation portion of the ground; a third step of depositing concrete on the excavation portion of the ground by using a tremie pipe; and a fourth step of pressurizing and injecting grout into the ground by using the injection pipes after a prescribed time elapses from the concrete deposition. The steps are performed in the order listed above. The grout is pressurized and injected into the ground by using the injection pipes and injection rings after depositing concrete on the excavation portion of the ground by using the tremie pipe to carry out reinforcing grouting on loss end surfaces of concrete occurring in a sand gravel layer and a ground layer with running water flow to additionally reinforce the loss end surfaces to increase the bearing power of an in-situ pile, particularly the skin friction force of the pile.
본 발명은 보강그라우팅을 이용한 현장타설 말뚝 시공방법에 있어서, 케이싱을 삽입하거나 케이싱 삽입 없이 지반을 연직방향인 종방향으로 굴착하는 1단계; 원주방향으로 서로 이격되면서 종방향으로 설치되는 축철근들과 상기 축철근들을 수평방향인 횡방향으로 결속하는 띠철근들과, 상기 축철근 또는 띠철근에 결합되는 것으로 종방향으로 설치되고 하부가 서로 연결되는 주입관들을 포함하는 철근케이지를 상기 지반의 굴착 부분에 삽입하는 2단계; 트레미관을 이용하여 상기 지반의 굴착 부분에 콘크리트를 타설하는 3단계; 및 상기 콘크리트 타설로부터 일정 시간 경과 후 상기 주입관을 이용하여 지반속으로 그라우트를 가압 주입하는 4단계;순으로 시공하는 것을 특징으로 하는 보강그라우팅을 이용한 현장타설 말뚝 시공방법에 관한 것으로서, 지반의 굴착 부분에 트레미관을 이용하여 콘크리트를 타설한 이후 주입관 및 주입링을 이용하여 지반속으로 그라우트를 가압 주입함으로써, 모래자갈층 및 유수의 흐름이 있는 지층에서 발생되는 콘크리트의 손실단면에 보강그라우팅을 실시하여 추가 보강함으로써, 현장타설말뚝의 지지력, 특히 말뚝의 주면마찰력이 증대되는 효과를 제공할 수 있다.
Cast-in-place pile using reinforced grouting and construction method
The present invention relates to a construction method of an in-situ pile using reinforcing grouting. The construction method of an in-situ pile using reinforcing grouting comprises: a first step of excavating ground in a longitudinal direction which is a vertical direction with or without insertion of a casing; a second step of inserting a reinforcing bar cage including a reinforcing bar mesh including axial bars circumferentially separated from each other and installed in the longitudinal direction and stirrups binding the axial bars in a lateral direction which is a horizontal direction, and injection pipes coupled to the axial bars and the stirrups and installed in the longitudinal direction, wherein lower portions thereof are connected to each other, into an excavation portion of the ground; a third step of depositing concrete on the excavation portion of the ground by using a tremie pipe; and a fourth step of pressurizing and injecting grout into the ground by using the injection pipes after a prescribed time elapses from the concrete deposition. The steps are performed in the order listed above. The grout is pressurized and injected into the ground by using the injection pipes and injection rings after depositing concrete on the excavation portion of the ground by using the tremie pipe to carry out reinforcing grouting on loss end surfaces of concrete occurring in a sand gravel layer and a ground layer with running water flow to additionally reinforce the loss end surfaces to increase the bearing power of an in-situ pile, particularly the skin friction force of the pile.
본 발명은 보강그라우팅을 이용한 현장타설 말뚝 시공방법에 있어서, 케이싱을 삽입하거나 케이싱 삽입 없이 지반을 연직방향인 종방향으로 굴착하는 1단계; 원주방향으로 서로 이격되면서 종방향으로 설치되는 축철근들과 상기 축철근들을 수평방향인 횡방향으로 결속하는 띠철근들과, 상기 축철근 또는 띠철근에 결합되는 것으로 종방향으로 설치되고 하부가 서로 연결되는 주입관들을 포함하는 철근케이지를 상기 지반의 굴착 부분에 삽입하는 2단계; 트레미관을 이용하여 상기 지반의 굴착 부분에 콘크리트를 타설하는 3단계; 및 상기 콘크리트 타설로부터 일정 시간 경과 후 상기 주입관을 이용하여 지반속으로 그라우트를 가압 주입하는 4단계;순으로 시공하는 것을 특징으로 하는 보강그라우팅을 이용한 현장타설 말뚝 시공방법에 관한 것으로서, 지반의 굴착 부분에 트레미관을 이용하여 콘크리트를 타설한 이후 주입관 및 주입링을 이용하여 지반속으로 그라우트를 가압 주입함으로써, 모래자갈층 및 유수의 흐름이 있는 지층에서 발생되는 콘크리트의 손실단면에 보강그라우팅을 실시하여 추가 보강함으로써, 현장타설말뚝의 지지력, 특히 말뚝의 주면마찰력이 증대되는 효과를 제공할 수 있다.
Cast-in-place pile using reinforced grouting and construction method
보강그라우팅을 이용한 현장타설 말뚝 및 그 시공방법
ROH KYUNG BEOM (author)
2021-01-27
Patent
Electronic Resource
Korean
IPC:
E02D
FOUNDATIONS
,
Gründungen
Cast-in-place pile using reinforced grouting and construction method
European Patent Office | 2021
Cast-in-place pile using Pressurized grouting and construction method
European Patent Office | 2021
|Cast-in-place pile using Pressurized grouting and construction method
European Patent Office | 2021
Grouting pipe construction method for post grouting of cast-in-place pile
European Patent Office | 2022
|