Construction method of steel box girder using concrete filled steel tube
Provided is a method for constructing a steel box girder using a concrete filled steel pipe. The method for constructing the steel box girder using the concrete filled steel pipe of the present invention comprises: an installation step of placing a plurality of spacers at the steel pipe interior and installing a paper formwork in a space between the spacers; a pouring step of inserting a steel bar into the formwork and pouring a concrete into a formwork interior space; a prestressing step of applying prestressing using the steel bar; a filling step of filling a non-shrinking mortar or an expanded concrete between the steel pipe and the paper formwork; a curing step of curing the non-shrinking mortar or the expanded concrete filled in the filling step; a steel pipe attachment step of attaching the steel pipe to a steel box; and a release step of releasing the prestressing applied to the steel pipe. An objective of the present invention is to simplify a process and control constraints arising from cast-in-place construction.
본 발명은 강관 내부에 복수의 간격재가 배치되며, 상기 간격재의 사이공간에 종이 거푸집을 설치하는 설치 단계, 상기 거푸집 내 강봉을 삽입하고, 거푸집 내부 공간에 콘크리트를 타설하는 타설 단계, 상기 강봉을 이용하여 프리스트레싱을 가하는 프리스트레싱 단계, 상기 강관과 상기 종이거푸집 사이에 무수축 모르타르 또는 팽창 콘크리트 채움 단계, 상기 채움 단계에서 채워진 무수축 모르타르 또는 팽창 콘크리트를 양생하는 양생 단계, 강관을 강박스에 부착하는 강관 부착 단계 및 상기 강관에 가해지는 프리스트레싱을 해제하는 해제 단계를 포함하는 콘크리트 충전강관을 이용한 강박스 거더 시공방법을 제공한다.
Construction method of steel box girder using concrete filled steel tube
Provided is a method for constructing a steel box girder using a concrete filled steel pipe. The method for constructing the steel box girder using the concrete filled steel pipe of the present invention comprises: an installation step of placing a plurality of spacers at the steel pipe interior and installing a paper formwork in a space between the spacers; a pouring step of inserting a steel bar into the formwork and pouring a concrete into a formwork interior space; a prestressing step of applying prestressing using the steel bar; a filling step of filling a non-shrinking mortar or an expanded concrete between the steel pipe and the paper formwork; a curing step of curing the non-shrinking mortar or the expanded concrete filled in the filling step; a steel pipe attachment step of attaching the steel pipe to a steel box; and a release step of releasing the prestressing applied to the steel pipe. An objective of the present invention is to simplify a process and control constraints arising from cast-in-place construction.
본 발명은 강관 내부에 복수의 간격재가 배치되며, 상기 간격재의 사이공간에 종이 거푸집을 설치하는 설치 단계, 상기 거푸집 내 강봉을 삽입하고, 거푸집 내부 공간에 콘크리트를 타설하는 타설 단계, 상기 강봉을 이용하여 프리스트레싱을 가하는 프리스트레싱 단계, 상기 강관과 상기 종이거푸집 사이에 무수축 모르타르 또는 팽창 콘크리트 채움 단계, 상기 채움 단계에서 채워진 무수축 모르타르 또는 팽창 콘크리트를 양생하는 양생 단계, 강관을 강박스에 부착하는 강관 부착 단계 및 상기 강관에 가해지는 프리스트레싱을 해제하는 해제 단계를 포함하는 콘크리트 충전강관을 이용한 강박스 거더 시공방법을 제공한다.
Construction method of steel box girder using concrete filled steel tube
콘크리트 충전강관을 이용한 강박스 거더 시공방법
KIM JIN KOOK (author) / KIM YU A (author)
2023-05-10
Patent
Electronic Resource
Korean
IPC:
E01D
BRIDGES
,
Brücken
Construction method of steel box girder using concrete filled steel tube
European Patent Office | 2023
Ultra-high performance concrete filled steel tube box girder
European Patent Office | 2023
|Joint structure of concrete-filled steel tube column and steel girder
European Patent Office | 2019
|European Patent Office | 2018
|Steel structure and construction method using concrete filled steel tube
European Patent Office | 2024
|