A platform for research: civil engineering, architecture and urbanism
COMBINED (PILE-SLAB, PILE-BELT, PILE-COLUMNAR) FOUNDATION ERECTION METHOD
FIELD: construction.SUBSTANCE: invention relates to the field of construction, in particular to the buildings foundations arrangement methods. Building on the combined (pile-slab, pile-belt, pile-columnar) foundations erection method using the driven piles includes the “grillage foundation” with holes for the piles passage arrangement on the ground surface and embedded parts for the driving plant subsequent attachment thereto, the structure superstructures erection on the “grillage foundation”, reactive force compensation during the piles driving by the building erected part weight and the piles embedding in the grillage. Piles driving and embedment begins after the building erection to the certain number of floors, when the load on the “grillage foundation” from the erected structures weight will exceed the amount of load necessary to drive one pile, but will not be more than the soil design resistance under the “grillage foundation” sole.EFFECT: technical result consists in increase in the construction reliability, manufacturability, safety margin and cost effectiveness, reducing in the construction time.4 cl, 1 dwg
Изобретение относится к области строительства, в частности к способам устройства фундаментов зданий. Способ возведения здания на комбинированных фундаментах (свайно-плитного, свайно-ленточного, свайно-столбчатого) с использованием задавливаемых свай включает устройство на поверхности грунта «фундамента-ростверка» с отверстиями для пропуска свай и закладными деталями для последующего крепления к ним установки задавливания, возведение на «фундаменте-ростверке» верхних конструкций сооружения, компенсацию реактивного усилия при задавливании свай весом возведенной части здания и замоноличивание свай в ростверке. Задавливание и замоноличивание свай начинают после возведения здания до определенного количества этажей, когда нагрузка на «фундамент-ростверк» от веса возводимых конструкций превысит величину нагрузки, необходимой для задавливания одной сваи, но будет не больше расчетного сопротивления грунта под подошвой «фундамента-ростверка». Технический результат состоит в повышении надежности, технологичности, запаса прочности и экономичности строительства, снижении сроков строительства. 3 з.п. ф-лы, 1 ил.
COMBINED (PILE-SLAB, PILE-BELT, PILE-COLUMNAR) FOUNDATION ERECTION METHOD
FIELD: construction.SUBSTANCE: invention relates to the field of construction, in particular to the buildings foundations arrangement methods. Building on the combined (pile-slab, pile-belt, pile-columnar) foundations erection method using the driven piles includes the “grillage foundation” with holes for the piles passage arrangement on the ground surface and embedded parts for the driving plant subsequent attachment thereto, the structure superstructures erection on the “grillage foundation”, reactive force compensation during the piles driving by the building erected part weight and the piles embedding in the grillage. Piles driving and embedment begins after the building erection to the certain number of floors, when the load on the “grillage foundation” from the erected structures weight will exceed the amount of load necessary to drive one pile, but will not be more than the soil design resistance under the “grillage foundation” sole.EFFECT: technical result consists in increase in the construction reliability, manufacturability, safety margin and cost effectiveness, reducing in the construction time.4 cl, 1 dwg
Изобретение относится к области строительства, в частности к способам устройства фундаментов зданий. Способ возведения здания на комбинированных фундаментах (свайно-плитного, свайно-ленточного, свайно-столбчатого) с использованием задавливаемых свай включает устройство на поверхности грунта «фундамента-ростверка» с отверстиями для пропуска свай и закладными деталями для последующего крепления к ним установки задавливания, возведение на «фундаменте-ростверке» верхних конструкций сооружения, компенсацию реактивного усилия при задавливании свай весом возведенной части здания и замоноличивание свай в ростверке. Задавливание и замоноличивание свай начинают после возведения здания до определенного количества этажей, когда нагрузка на «фундамент-ростверк» от веса возводимых конструкций превысит величину нагрузки, необходимой для задавливания одной сваи, но будет не больше расчетного сопротивления грунта под подошвой «фундамента-ростверка». Технический результат состоит в повышении надежности, технологичности, запаса прочности и экономичности строительства, снижении сроков строительства. 3 з.п. ф-лы, 1 ил.
COMBINED (PILE-SLAB, PILE-BELT, PILE-COLUMNAR) FOUNDATION ERECTION METHOD
Способ возведения комбинированного фундамента (свайно-плитного, свайно-ленточного, свайно-столбчатого)
VLASOV ALEKSANDR NIKOLAEVICH (author) / KOROLEV MIKHAIL VLADIMIROVICH (author) / KOROLEV PETR MIKHAJLOVICH (author)
2018-09-17
Patent
Electronic Resource
Russian
IPC:
E02D
FOUNDATIONS
,
Gründungen
METHOD OF PILE-SLAB FOUNDATION AND SLAB-PILE FOUNDATION CONSTRUCTED IN THIS WAY
European Patent Office | 2018
|European Patent Office | 2024
|