METHOD FOR INSTALLING METAL PILES IN PERMAFROST SOIL
The invention relates to foundation engineering and can be used for installing drill-inserted pipeline supports and power transmission line supports, and also in installing buildings and structures on permafrost soil. The aim of the invention consists in developing a pile-installation process which makes it possible to prevent soil slurry and groundwater from entering a bore-hole during the summer installation of drill-inserted piles in permafrost soil in the presence of water-laden soil in the seasonal freezing and thawing layer, and also in preventing the possible effect of frost heaving forces arising from heaving deformations in seasonal freezing conditions. The present method involves driving a casing pipe to the depth of the seasonal freezing and thawing of the soil, drilling a pilot hole to a depth of no less than the standard depth of the freezing of the soil, pouring in a hardening material in an amount necessary to fill the cavities between the pilot hole and the piles from the bottom of the pilot hole to the bottom of the level of the seasonal freezing and thawing layer of the soil, inserting the piles, and filling the empty space between a pile and the casing pipe using a non-heaving inert particulate material.
L'invention se rapporte à la construction de fondations et peut être utilisée lors de la construction de supports sur pilotis de conduits, de supports de lignes de transmission d'électricité, ainsi que lors de la construction de bâtiments et de structures sur des pergélisols. Le but de l'invention est d'élaborer des techniques de montage de pylônes permettant d'exclure toute possibilité de chute dans le puits de boues du sol et d'eaux de ruissellement lors de la menée des travaux lors de la construction de pylônes sur pilotis dans des pergélisols en période estivale dans des sols inondés de la couche de gel-fonte saisonniers, et d'exclure toute possibilité d'action des forces de soulèvement par le gel qui sont dues à la déformation par soulèvement dans des conditions de gel saisonnier. Le procédé consiste à enfoncer un coffrage à la profondeur de gel-fonte saisonniers du sol, à forer un puits de tête à une profondeur au moins égale à la profondeur normative de gel du sol, à couler un matériau durcissable dans le volume nécessaire pour remplir la cavité entre le puits de tête et le pylône depuis le fond du puits de tête jusqu'au bas du niveau de la couche de gel-fonte saisonniers du sol, à descendre le pylône, à remplir la cavité entre le pylône et le coffrage avec un matériau neutre en vrac et non gonflant.
Изобретение относится к фундаментостроению и может быть использовано как при устройстве буроопускных опор трубопроводов, опор линий электропередач, так и при устройстве зданий и сооружений на вечномерзлых грунтах. Задачей изобретения является разработка технологии монтажа свай, позволяющей исключить возможность попадания в скважину грунтового шлама и грунтовых вод при производстве работ по устройству буроопускных свай в вечномерзлых грунтах в летний период при обводненных грунтах слоя сезонного промерзания - оттаивания и исключения возможности влияния сил морозного пучения, возникающих от деформаций пучения в условиях сезонного промерзания. Способ включает забивку обсадной трубы на глубину сезонного промерзания-оттаивания грунта, бурение лидерной скважины на глубину не менее нормативной глубины промерзания грунтов, заливку твердеющего материала в объеме необходимом для заполнения полостей между лидерной скважиной и сваей от низа лидерной скважины до низа уровня слоя сезонного промерзания-оттаивания грунта, погружение сваи, заполнение полости между сваей и обсадной трубой непучинистым сыпучим инертным материалом.
METHOD FOR INSTALLING METAL PILES IN PERMAFROST SOIL
The invention relates to foundation engineering and can be used for installing drill-inserted pipeline supports and power transmission line supports, and also in installing buildings and structures on permafrost soil. The aim of the invention consists in developing a pile-installation process which makes it possible to prevent soil slurry and groundwater from entering a bore-hole during the summer installation of drill-inserted piles in permafrost soil in the presence of water-laden soil in the seasonal freezing and thawing layer, and also in preventing the possible effect of frost heaving forces arising from heaving deformations in seasonal freezing conditions. The present method involves driving a casing pipe to the depth of the seasonal freezing and thawing of the soil, drilling a pilot hole to a depth of no less than the standard depth of the freezing of the soil, pouring in a hardening material in an amount necessary to fill the cavities between the pilot hole and the piles from the bottom of the pilot hole to the bottom of the level of the seasonal freezing and thawing layer of the soil, inserting the piles, and filling the empty space between a pile and the casing pipe using a non-heaving inert particulate material.
L'invention se rapporte à la construction de fondations et peut être utilisée lors de la construction de supports sur pilotis de conduits, de supports de lignes de transmission d'électricité, ainsi que lors de la construction de bâtiments et de structures sur des pergélisols. Le but de l'invention est d'élaborer des techniques de montage de pylônes permettant d'exclure toute possibilité de chute dans le puits de boues du sol et d'eaux de ruissellement lors de la menée des travaux lors de la construction de pylônes sur pilotis dans des pergélisols en période estivale dans des sols inondés de la couche de gel-fonte saisonniers, et d'exclure toute possibilité d'action des forces de soulèvement par le gel qui sont dues à la déformation par soulèvement dans des conditions de gel saisonnier. Le procédé consiste à enfoncer un coffrage à la profondeur de gel-fonte saisonniers du sol, à forer un puits de tête à une profondeur au moins égale à la profondeur normative de gel du sol, à couler un matériau durcissable dans le volume nécessaire pour remplir la cavité entre le puits de tête et le pylône depuis le fond du puits de tête jusqu'au bas du niveau de la couche de gel-fonte saisonniers du sol, à descendre le pylône, à remplir la cavité entre le pylône et le coffrage avec un matériau neutre en vrac et non gonflant.
Изобретение относится к фундаментостроению и может быть использовано как при устройстве буроопускных опор трубопроводов, опор линий электропередач, так и при устройстве зданий и сооружений на вечномерзлых грунтах. Задачей изобретения является разработка технологии монтажа свай, позволяющей исключить возможность попадания в скважину грунтового шлама и грунтовых вод при производстве работ по устройству буроопускных свай в вечномерзлых грунтах в летний период при обводненных грунтах слоя сезонного промерзания - оттаивания и исключения возможности влияния сил морозного пучения, возникающих от деформаций пучения в условиях сезонного промерзания. Способ включает забивку обсадной трубы на глубину сезонного промерзания-оттаивания грунта, бурение лидерной скважины на глубину не менее нормативной глубины промерзания грунтов, заливку твердеющего материала в объеме необходимом для заполнения полостей между лидерной скважиной и сваей от низа лидерной скважины до низа уровня слоя сезонного промерзания-оттаивания грунта, погружение сваи, заполнение полости между сваей и обсадной трубой непучинистым сыпучим инертным материалом.
METHOD FOR INSTALLING METAL PILES IN PERMAFROST SOIL
PROCÉDÉ DE MONTAGE DE PYLÔNES MÉTALLIQUES SUR DES PERGÉLISOLS
СПОСОБ МОНТАЖА МЕТАЛЛИЧЕСКИХ СВАЙ НА ВЕЧНОМЕРЗЛЫХ ГРУНТАХ
SAPSAI ALEKSEI NIKOLAEVICH (author) / SMIRNOV NIKOLAI VLADIMIROVICH (author) / KUMALLAGOV VITALY ALEKSANDROVICH (author) / SEMIN EVGENY EVGENIEVICH (author) / IVAKIN ALEKSANDR VLADIMIROVICH (author) / BOGATENKOV YURY VASILEVICH (author)
2015-10-01
Patent
Electronic Resource
Russian
IPC:
E02D
FOUNDATIONS
,
Gründungen