HIGH-RISE BUILDING SETTLING REINFORCING AND LIFTING CORRECTING CONSTRUCTION METHOD
A high-rise building settling reinforcing and lifting correcting construction method, comprising the following steps: drilling holes vertically downward around a foundation slab (2) of a building (1), forming multiple curtain wall holes (31) sunk into foundation soil at intervals; injecting slurry into the curtain wall holes (31), slurry ranges meshing and overlapping with one another, forming a curtain wall (3), the curtain wall (3) enclosing foundation soil under the foundation slab (2) at the base of the building (1), separating foundation soil inside and outside the range of the building (1); providing multiple vertical reinforcement slurry injection holes (41) on the foundation slab (2) and injecting slurry, fully reinforcing soil near the floor (2), forming a reinforcement body (4); drilling a hole downward, forming a lifting hole (6), the lifting hole (5) penetrating to a bottom part of the reinforcement body (4), pressure-injecting slurry into a bottom part of the lifting hole (6), and as slurry in the curtain wall (3) continuously increases and rapidly solidifies, the foundation soil is continuously filled and compressed, creating a lifting force, and the building (1) gradually rising to a determined lift height. The present construction method can effectively lift a building, and can prevent secondary settling from occurring.
Procédé de construction de renforcement de sédimentation de renforcement d'immeuble de grande hauteur et de correction de lavage, comprenant les étapes suivantes consistant à : forer des trous verticalement vers le bas autour d'une dalle de fondation (2) d'un immeuble (1), formant de multiples trous de mur-rideau (31) enfoncés dans le sol de fondation à des intervalles ; injecter de la boue dans les trous de mur-rideau (31), les étendues de boue s'engrenant et se chevauchant mutuellement, formant un mur-rideau (3), le mur-rideau (3) entourant le sol de fondation sous la dalle de fondation (2) au niveau de la base de l'immeuble (1), séparant le sol de fondation à l'intérieur et à l'extérieur de l'étendue de l'immeuble (1) ; fournir de multiples trous d'injection de boue de renforcement vertical (41) sur la dalle de fondation (2) et injecter de la boue, renforcer complètement le sol à proximité du sol (2), formant un corps de renforcement (4) ; forer un trou vers le bas, formant un trou de levage (6) pénétrant dans une partie inférieure du corps de renforcement (4), injecter par pression de la boue dans une partie inférieure du trou de levage (6), et comme la boue dans le mur-rideau (3) augmente et se solidifie rapidement, le sol de fondation est rempli et comprimé en continu, créant une force de levage, et l'immeuble (1) s'élevant progressivement jusqu'à une hauteur de levée déterminée. Le présent procédé de construction peut efficacement soulever un immeuble, et peut empêcher une sédimentation secondaire de se produire.
一种高层建筑沉降加固抬升纠偏的施工方法,其包括以下步骤:在建筑物(1)底板(2)周围竖直向下钻孔,形成多个间隔的深入地基土的帷幕孔(31);向帷幕孔(31)内注浆,注浆范围相互咬合重叠,形成帷幕墙(3),该帷幕墙(3)将建筑物(1)基础的底板(2)以下的地基土进行围闭,并将建筑物(1)范围内外的地基土隔离;在底板(2)上开设多个竖向的加固注浆孔(41),并进行注浆,将靠近底板(2)的土体全部加固,形成加固体(4);向下钻孔,形成抬升孔(6),抬升孔(6)深入至加固体(4)的底部,向抬升孔(6)底部进行压力注浆,随着帷幕墙(3)内浆液的不断增加并快速凝固,地基土不断被填充、挤密,并形成抬升力,建筑物(1)逐渐抬升至设定的抬升高度,该施工方法能够有效地将建筑物进行抬升,并能够防止二次沉降的产生。
HIGH-RISE BUILDING SETTLING REINFORCING AND LIFTING CORRECTING CONSTRUCTION METHOD
A high-rise building settling reinforcing and lifting correcting construction method, comprising the following steps: drilling holes vertically downward around a foundation slab (2) of a building (1), forming multiple curtain wall holes (31) sunk into foundation soil at intervals; injecting slurry into the curtain wall holes (31), slurry ranges meshing and overlapping with one another, forming a curtain wall (3), the curtain wall (3) enclosing foundation soil under the foundation slab (2) at the base of the building (1), separating foundation soil inside and outside the range of the building (1); providing multiple vertical reinforcement slurry injection holes (41) on the foundation slab (2) and injecting slurry, fully reinforcing soil near the floor (2), forming a reinforcement body (4); drilling a hole downward, forming a lifting hole (6), the lifting hole (5) penetrating to a bottom part of the reinforcement body (4), pressure-injecting slurry into a bottom part of the lifting hole (6), and as slurry in the curtain wall (3) continuously increases and rapidly solidifies, the foundation soil is continuously filled and compressed, creating a lifting force, and the building (1) gradually rising to a determined lift height. The present construction method can effectively lift a building, and can prevent secondary settling from occurring.
Procédé de construction de renforcement de sédimentation de renforcement d'immeuble de grande hauteur et de correction de lavage, comprenant les étapes suivantes consistant à : forer des trous verticalement vers le bas autour d'une dalle de fondation (2) d'un immeuble (1), formant de multiples trous de mur-rideau (31) enfoncés dans le sol de fondation à des intervalles ; injecter de la boue dans les trous de mur-rideau (31), les étendues de boue s'engrenant et se chevauchant mutuellement, formant un mur-rideau (3), le mur-rideau (3) entourant le sol de fondation sous la dalle de fondation (2) au niveau de la base de l'immeuble (1), séparant le sol de fondation à l'intérieur et à l'extérieur de l'étendue de l'immeuble (1) ; fournir de multiples trous d'injection de boue de renforcement vertical (41) sur la dalle de fondation (2) et injecter de la boue, renforcer complètement le sol à proximité du sol (2), formant un corps de renforcement (4) ; forer un trou vers le bas, formant un trou de levage (6) pénétrant dans une partie inférieure du corps de renforcement (4), injecter par pression de la boue dans une partie inférieure du trou de levage (6), et comme la boue dans le mur-rideau (3) augmente et se solidifie rapidement, le sol de fondation est rempli et comprimé en continu, créant une force de levage, et l'immeuble (1) s'élevant progressivement jusqu'à une hauteur de levée déterminée. Le présent procédé de construction peut efficacement soulever un immeuble, et peut empêcher une sédimentation secondaire de se produire.
一种高层建筑沉降加固抬升纠偏的施工方法,其包括以下步骤:在建筑物(1)底板(2)周围竖直向下钻孔,形成多个间隔的深入地基土的帷幕孔(31);向帷幕孔(31)内注浆,注浆范围相互咬合重叠,形成帷幕墙(3),该帷幕墙(3)将建筑物(1)基础的底板(2)以下的地基土进行围闭,并将建筑物(1)范围内外的地基土隔离;在底板(2)上开设多个竖向的加固注浆孔(41),并进行注浆,将靠近底板(2)的土体全部加固,形成加固体(4);向下钻孔,形成抬升孔(6),抬升孔(6)深入至加固体(4)的底部,向抬升孔(6)底部进行压力注浆,随着帷幕墙(3)内浆液的不断增加并快速凝固,地基土不断被填充、挤密,并形成抬升力,建筑物(1)逐渐抬升至设定的抬升高度,该施工方法能够有效地将建筑物进行抬升,并能够防止二次沉降的产生。
HIGH-RISE BUILDING SETTLING REINFORCING AND LIFTING CORRECTING CONSTRUCTION METHOD
PROCÉDÉ DE CONSTRUCTION DE RENFORCEMENT DE SÉDIMENTATION D'IMMEUBLE DE GRANDE HAUTEUR ET DE CORRECTION DE LEVAGE
一种高层建筑沉降加固抬升纠偏的施工方法
CUI XUEDONG (author) / WU JIGUANG (author) / CUI TENGYUE (author)
2021-02-18
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
HIGH-RISE BUILDING SETTLING REINFORCING AND LIFTING CORRECTING CONSTRUCTION METHOD
European Patent Office | 2022
|High-rise building settling reinforcing and lifting correcting construction method
European Patent Office | 2023
|Reinforcing and lifting method for karst foundation high-rise building
European Patent Office | 2021
|Intelligent lifting construction method for high-rise building
European Patent Office | 2020
|Building construction high-rise material lifting device premixed through lifting force
European Patent Office | 2020
|