METHOD FOR CONSTRUCTING NOVEL STARTER DAM SUITABLE FOR UPSTREAM TAILINGS POND
Disclosed is a method for constructing a novel starter dam suitable for an upstream tailings pond, comprising: laying a starter dam body bottom anti-seepage layer; providing a starter dam upstream seepage drainage prism body (1) and a starter dam downstream seepage drainage prism body (1,) respectively on the upstream and downstream of the starter dam, and laying a starter dam seepage drainage mattress (2) on the starter dam body bottom anti-seepage layer, lower ends of vertical seepage drainage blind ditch pipe (3) being in communication with the starter dam seepage drainage mattress (2); pre-embedding inclined drainage blind ditches at positions where the starter dam contacts mountain bodies, and pre-embedding transverse blind ditches at positions where the starter dam contacts the mountain bodies; and building the starter dam layer by layer from bottom to top, and compacting same in a layered manner, and constructing an anti-seepage protective slope layer (5) on an upstream slope surface of the starter dam. The present invention has advantages of low construction cost, small amount of stones used, and good water-permeable effect. By designing a drainage facility inside a starter earth dam, the earth dam meets the requirement of a water-permeable dam.
L'invention concerne un procédé de construction d'une nouvelle digue initiale appropriée pour un étang de résidus en amont, comprenant : la pose d'une couche anti-infiltration de fond de corps de digue initiale ; la fourniture d'un corps de prisme de drainage d'infiltration en amont de digue initiale (1) et d'un corps de prisme de drainage d'infiltration en aval de digue initiale (1,) respectivement en amont et en aval de la digue initiale, et la pose d'un matelas de drainage d'infiltration de digue initiale (2) sur la couche anti-infiltration de fond de corps de digue initiale, les extrémités inférieures d'un tuyau de tranchée aveugle de drainage d'infiltration verticale (3) étant en communication avec le matelas de drainage d'infiltration de digue initiale (2) ; la pré-incorporation de fossés aveugles de drainage inclinés dans des positions où la digue initiale entre en contact avec des corps de montagne, et la pré-intégration de fossés aveugles transversaux à des positions où de la digue initiale entre en contact avec les corps de montagne ; et la construction de la couche de digue initiale par couche de bas en haut, et le compactage de celle-ci d'une manière stratifiée, et la construction d'une couche de pente de protection anti-infiltration (5) sur une surface de pente amont de la digue initiale. La présente invention présente les avantages d'un faible coût de construction, d'une petite quantité de pierres utilisées et d'un bon effet de perméabilité à l'eau. En concevant une installation de drainage à l'intérieur d'une digue initiale de terre, la digue de terre satisfait l'exigence d'une digue perméable à l'eau.
本发明公开了一种适于上游式尾矿库的新型初期坝的建设方法,先铺设初期坝体底部防渗层,在初期坝上、下游分别设置初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1,),在初期坝体底部防渗层上铺设初期坝排渗褥垫(2),竖向排渗盲沟管(3)的下端与初期坝排渗褥垫(2)连通;在初期坝与山体接触部位预埋斜向排水盲沟,在初期坝与山体接触部位预埋横向盲沟;自下而上逐层堆筑初期坝,并分层压实,在初期坝上游坡面上施工防渗护坡层(5)。本发明具有建设成本低、石料使用量小、透水效果好的优点,通过在初期土坝内部设计排水设施使土坝达到透水坝的要求。
METHOD FOR CONSTRUCTING NOVEL STARTER DAM SUITABLE FOR UPSTREAM TAILINGS POND
Disclosed is a method for constructing a novel starter dam suitable for an upstream tailings pond, comprising: laying a starter dam body bottom anti-seepage layer; providing a starter dam upstream seepage drainage prism body (1) and a starter dam downstream seepage drainage prism body (1,) respectively on the upstream and downstream of the starter dam, and laying a starter dam seepage drainage mattress (2) on the starter dam body bottom anti-seepage layer, lower ends of vertical seepage drainage blind ditch pipe (3) being in communication with the starter dam seepage drainage mattress (2); pre-embedding inclined drainage blind ditches at positions where the starter dam contacts mountain bodies, and pre-embedding transverse blind ditches at positions where the starter dam contacts the mountain bodies; and building the starter dam layer by layer from bottom to top, and compacting same in a layered manner, and constructing an anti-seepage protective slope layer (5) on an upstream slope surface of the starter dam. The present invention has advantages of low construction cost, small amount of stones used, and good water-permeable effect. By designing a drainage facility inside a starter earth dam, the earth dam meets the requirement of a water-permeable dam.
L'invention concerne un procédé de construction d'une nouvelle digue initiale appropriée pour un étang de résidus en amont, comprenant : la pose d'une couche anti-infiltration de fond de corps de digue initiale ; la fourniture d'un corps de prisme de drainage d'infiltration en amont de digue initiale (1) et d'un corps de prisme de drainage d'infiltration en aval de digue initiale (1,) respectivement en amont et en aval de la digue initiale, et la pose d'un matelas de drainage d'infiltration de digue initiale (2) sur la couche anti-infiltration de fond de corps de digue initiale, les extrémités inférieures d'un tuyau de tranchée aveugle de drainage d'infiltration verticale (3) étant en communication avec le matelas de drainage d'infiltration de digue initiale (2) ; la pré-incorporation de fossés aveugles de drainage inclinés dans des positions où la digue initiale entre en contact avec des corps de montagne, et la pré-intégration de fossés aveugles transversaux à des positions où de la digue initiale entre en contact avec les corps de montagne ; et la construction de la couche de digue initiale par couche de bas en haut, et le compactage de celle-ci d'une manière stratifiée, et la construction d'une couche de pente de protection anti-infiltration (5) sur une surface de pente amont de la digue initiale. La présente invention présente les avantages d'un faible coût de construction, d'une petite quantité de pierres utilisées et d'un bon effet de perméabilité à l'eau. En concevant une installation de drainage à l'intérieur d'une digue initiale de terre, la digue de terre satisfait l'exigence d'une digue perméable à l'eau.
本发明公开了一种适于上游式尾矿库的新型初期坝的建设方法,先铺设初期坝体底部防渗层,在初期坝上、下游分别设置初期坝上游排渗棱体(1)、初期坝下游排渗棱体(1,),在初期坝体底部防渗层上铺设初期坝排渗褥垫(2),竖向排渗盲沟管(3)的下端与初期坝排渗褥垫(2)连通;在初期坝与山体接触部位预埋斜向排水盲沟,在初期坝与山体接触部位预埋横向盲沟;自下而上逐层堆筑初期坝,并分层压实,在初期坝上游坡面上施工防渗护坡层(5)。本发明具有建设成本低、石料使用量小、透水效果好的优点,通过在初期土坝内部设计排水设施使土坝达到透水坝的要求。
METHOD FOR CONSTRUCTING NOVEL STARTER DAM SUITABLE FOR UPSTREAM TAILINGS POND
PROCÉDÉ DE CONSTRUCTION D'UNE NOUVELLE DIGUE INITIALE APPROPRIÉE POUR UN ÉTANG DE RÉSIDUS EN AMONT
一种适于上游式尾矿库的新型初期坝的建设方法
XU CHUANHUA (author) / DUAN WEIPING (author) / MAO ZHIYUAN (author) / QIU YU (author) / YANG QIANGSHENG (author) / TIAN WEIHU (author) / NI QIANG (author) / OU MINGJIANG (author) / WENG JINHONG (author) / WU GUANGFU (author)
2022-08-04
Patent
Electronic Resource
Chinese
European Patent Office | 2015
|Anti-seepage system for wet upstream tailings pond of iron mine
European Patent Office | 2023
|Numerical Analysis of an Upstream Tailings Dam Subjected to Pond Filling Rates
BASE | 2021
|New method for constructing combined drainage and seepage system of valley-type tailings pond
European Patent Office | 2024
|European Patent Office | 2015
|