CONCRETE POURING CONSTRUCTION METHOD FOR EDGE PORTION OF ROAD BASE LAYER
The present invention relates to a concrete pouring construction method for an edge portion of a road base layer, and relates to the technical field of municipal engineering road construction. The method comprises the following steps: loosening soil after a base groove is excavated; reserving formwork belts and compacting the base groove between the formwork belts; reinforcing and reserving a pipeline between the formwork belts in the base groove; fixing a steel mold onto the formwork belts; performing leveling by means of a leveling device after the concrete is poured; and filling the formwork belts to be connected to the road after the steel mold is removed. According to the present invention, by arranging the steel mold to enclose the base groove to form a mold cavity, concrete leakage is reduced, such that the steel mold is separated from the concrete in a knocking manner, such that the steel mold can be used multiple times, thereby achieving the advantage of saving resources which are used in the pouring of the edge of the road base layer.
La présente invention concerne un procédé de construction de coulée de béton pour une partie de bord d'une couche de base de route, se rapportant au domaine technique de la construction routière d'ingénierie urbaine. Le procédé comprend les étapes suivantes : l'ameublissement du sol après excavation d'une rainure de base ; la réservation de bandes de coffrage et le compactage de la rainure de base entre les bandes de coffrage ; le renforcement et la réservation d'une conduite entre les bandes de coffrage dans la rainure de base ; la fixation d'un moule en acier sur les bandes de coffrage ; la réalisation d'une mise à niveau au moyen d'un dispositif de nivellement après coulage de béton ; et le remplissage des bandes de coffrage pour être reliées à la route après retrait du moule en acier. Selon la présente invention, le moule en acier est disposé pour enfermer la rainure de base afin de former une cavité de moule permet de réduire une fuite de béton, de telle sorte que le moule en acier est séparé du béton par décloisonnement, de telle sorte que le moule en acier peut être utilisé plusieurs fois, ce qui permet d'obtenir l'avantage d'économiser des ressources qui sont utilisées dans le coulage du bord de la couche de base de route.
本申请涉及一种道路基层边缘部位混凝土浇筑施工方法,涉及市政工程道路施工技术领域,包括以下步骤:开挖基槽后松土、预留支模带并将支模带之间的基槽压实、基槽内支模带之间加固及预留管道、钢模固定于支模带上、浇筑混凝土之后抹平装置抹平、拆除钢模后将支模带填充以和道路衔接。本申请通过设置钢模对基槽进行围挡形成模腔,减少混凝土外漏,使得钢模通过敲击的方式脱离混凝土,以便于钢模能够多次利用,从而具有节约道路基层边缘浇筑所用的资源的优点。
CONCRETE POURING CONSTRUCTION METHOD FOR EDGE PORTION OF ROAD BASE LAYER
The present invention relates to a concrete pouring construction method for an edge portion of a road base layer, and relates to the technical field of municipal engineering road construction. The method comprises the following steps: loosening soil after a base groove is excavated; reserving formwork belts and compacting the base groove between the formwork belts; reinforcing and reserving a pipeline between the formwork belts in the base groove; fixing a steel mold onto the formwork belts; performing leveling by means of a leveling device after the concrete is poured; and filling the formwork belts to be connected to the road after the steel mold is removed. According to the present invention, by arranging the steel mold to enclose the base groove to form a mold cavity, concrete leakage is reduced, such that the steel mold is separated from the concrete in a knocking manner, such that the steel mold can be used multiple times, thereby achieving the advantage of saving resources which are used in the pouring of the edge of the road base layer.
La présente invention concerne un procédé de construction de coulée de béton pour une partie de bord d'une couche de base de route, se rapportant au domaine technique de la construction routière d'ingénierie urbaine. Le procédé comprend les étapes suivantes : l'ameublissement du sol après excavation d'une rainure de base ; la réservation de bandes de coffrage et le compactage de la rainure de base entre les bandes de coffrage ; le renforcement et la réservation d'une conduite entre les bandes de coffrage dans la rainure de base ; la fixation d'un moule en acier sur les bandes de coffrage ; la réalisation d'une mise à niveau au moyen d'un dispositif de nivellement après coulage de béton ; et le remplissage des bandes de coffrage pour être reliées à la route après retrait du moule en acier. Selon la présente invention, le moule en acier est disposé pour enfermer la rainure de base afin de former une cavité de moule permet de réduire une fuite de béton, de telle sorte que le moule en acier est séparé du béton par décloisonnement, de telle sorte que le moule en acier peut être utilisé plusieurs fois, ce qui permet d'obtenir l'avantage d'économiser des ressources qui sont utilisées dans le coulage du bord de la couche de base de route.
本申请涉及一种道路基层边缘部位混凝土浇筑施工方法,涉及市政工程道路施工技术领域,包括以下步骤:开挖基槽后松土、预留支模带并将支模带之间的基槽压实、基槽内支模带之间加固及预留管道、钢模固定于支模带上、浇筑混凝土之后抹平装置抹平、拆除钢模后将支模带填充以和道路衔接。本申请通过设置钢模对基槽进行围挡形成模腔,减少混凝土外漏,使得钢模通过敲击的方式脱离混凝土,以便于钢模能够多次利用,从而具有节约道路基层边缘浇筑所用的资源的优点。
CONCRETE POURING CONSTRUCTION METHOD FOR EDGE PORTION OF ROAD BASE LAYER
PROCÉDÉ DE CONSTRUCTION DE COULÉE DE BÉTON POUR PARTIE DE BORD DE COUCHE DE BASE DE ROUTE
一种道路基层边缘部位混凝土浇筑施工方法
LI YIYUAN (author) / WANG RONG (author) / LI ZAIHAI (author) / YING HAIBO (author) / WANG YE (author) / WANG YUXUAN (author) / WANG JIAN (author) / CHEN JIANGSHUAI (author) / YANG ANLONG (author) / YANG BANGWEI (author)
2023-02-16
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
Assembled road edge stone integrated pouring concrete road and construction method
European Patent Office | 2022
|Concrete pouring device and concrete pouring vehicle for road construction
European Patent Office | 2020
|Concrete pouring device and method for road construction
European Patent Office | 2024
|