SUPER-LONG PRESTRESSING STEEL TENDON CONSTRUCTION METHOD
A super-long prestressing steel tendon construction method, comprising the following steps: prestressing duct positioning and installation; top-surface prestressing steel tendon threading; top-surface prestress tensioning; top-surface prestressing tendon duct grouting; and top-surface prestress anchorage sealing. By using a construction method of "a traction cable being pulled by means of a mechanical method to perform whole-hole threading; performing cable threading, tensioning, and grouting by using reserved hole positions; and adding tensioning and anchorage sealing notches at tensioning ports", the problems of having limited space, being time-consuming and labor-consuming, steel strands tending to damage a hole wall, the grouting not being full, and the anchorage sealing construction being difficult during the construction of a top-surface super-long prestressing steel tendon are solved.
L'invention concerne un procédé de construction de tendon d'acier de précontrainte super long, comprenant les étapes suivantes consistant à : positionner et installer un conduit de précontrainte ; fileter un tendon d'acier de précontrainte de surface supérieure ; mettre sous tension une précontrainte de surface supérieure ; joindre le conduit de tendon de précontrainte de surface supérieure ; et sceller par ancrage une précontrainte de surface supérieure. En utilisant un procédé de construction dans laquelle " un câble de traction est tiré au moyen d'un procédé mécanique pour réaliser un filetage de trou entier ; la réalisation d'un filetage, d'une mise sous tension et d'une jonction de câbles à l'aide de positions de trou réservées ; et l'ajout des encoches d'étanchéité de mise sous tension et d'ancrage au niveau des orifices de mise sous tension ", les problèmes associés à un espace limité, à une consommation de temps et de main d'œuvre, à des torons d'acier tendant à endommager une paroi de trou, à une jonction qui n'est pas complète et à une construction d'étanchéité d'ancrage difficile lors de la construction d'un tendon d'acier de précontrainte super-long de surface supérieure sont résolus.
一种超长预应力钢束施工方法,包括以下步骤:预应力管道定位安装;顶面预应力钢束穿束;顶面预应力张拉;顶面预应力束管道压浆;顶面预应力封锚。通过采用"机械法拉动引索整孔穿设+穿索、张拉、压浆采用预留孔位+在张拉端口增加张拉、封锚槽口"的施工方法,解决顶面超长预应力钢束在施工时空间受限、费时费工、钢绞线易造成孔壁破坏、压浆不饱满、封锚施工难的问题。
SUPER-LONG PRESTRESSING STEEL TENDON CONSTRUCTION METHOD
A super-long prestressing steel tendon construction method, comprising the following steps: prestressing duct positioning and installation; top-surface prestressing steel tendon threading; top-surface prestress tensioning; top-surface prestressing tendon duct grouting; and top-surface prestress anchorage sealing. By using a construction method of "a traction cable being pulled by means of a mechanical method to perform whole-hole threading; performing cable threading, tensioning, and grouting by using reserved hole positions; and adding tensioning and anchorage sealing notches at tensioning ports", the problems of having limited space, being time-consuming and labor-consuming, steel strands tending to damage a hole wall, the grouting not being full, and the anchorage sealing construction being difficult during the construction of a top-surface super-long prestressing steel tendon are solved.
L'invention concerne un procédé de construction de tendon d'acier de précontrainte super long, comprenant les étapes suivantes consistant à : positionner et installer un conduit de précontrainte ; fileter un tendon d'acier de précontrainte de surface supérieure ; mettre sous tension une précontrainte de surface supérieure ; joindre le conduit de tendon de précontrainte de surface supérieure ; et sceller par ancrage une précontrainte de surface supérieure. En utilisant un procédé de construction dans laquelle " un câble de traction est tiré au moyen d'un procédé mécanique pour réaliser un filetage de trou entier ; la réalisation d'un filetage, d'une mise sous tension et d'une jonction de câbles à l'aide de positions de trou réservées ; et l'ajout des encoches d'étanchéité de mise sous tension et d'ancrage au niveau des orifices de mise sous tension ", les problèmes associés à un espace limité, à une consommation de temps et de main d'œuvre, à des torons d'acier tendant à endommager une paroi de trou, à une jonction qui n'est pas complète et à une construction d'étanchéité d'ancrage difficile lors de la construction d'un tendon d'acier de précontrainte super-long de surface supérieure sont résolus.
一种超长预应力钢束施工方法,包括以下步骤:预应力管道定位安装;顶面预应力钢束穿束;顶面预应力张拉;顶面预应力束管道压浆;顶面预应力封锚。通过采用"机械法拉动引索整孔穿设+穿索、张拉、压浆采用预留孔位+在张拉端口增加张拉、封锚槽口"的施工方法,解决顶面超长预应力钢束在施工时空间受限、费时费工、钢绞线易造成孔壁破坏、压浆不饱满、封锚施工难的问题。
SUPER-LONG PRESTRESSING STEEL TENDON CONSTRUCTION METHOD
PROCÉDÉ DE CONSTRUCTION DE TENDON D'ACIER DE PRÉCONTRAINTE SUPER-LONG
一种超长预应力钢束施工方法
LIU WENSHENG (author) / ZHANG ZHIGUO (author) / LI FENGCHENG (author) / FENG CHAO (author) / WANG GAOPING (author) / CHEN ZHAOPO (author) / SHANG YAXIN (author) / SU LI (author) / MIN KUN (author) / XIE LEI (author)
2023-03-09
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Construction method of prestressing tendon storing and extracting device
European Patent Office | 2024
|Construction method of prestressed beam prestressing tendon tensioning operation platform
European Patent Office | 2024
|Optimization of Prestressing Tendon Profile
British Library Conference Proceedings | 1999
|PRESTRESSING METHOD FOR TENDON AND CONSTRUCTION METHOD FOR GIRDER USING THE SAME
European Patent Office | 2015
|