A platform for research: civil engineering, architecture and urbanism
Semmering Base Tunnel – Design and construction of the shaft head caverns under difficult conditions
Semmering‐Basistunnel – Planung und Bau der Schachtkopfkavernen unter erschwerten Bedingungen
In contract SBT1.1 of the Semmering Base Tunnel, the single‐track main tunnels are being driven from the portal in Gloggnitz and from a temporary intermediate starting point in Göstritz. The temporary intermediate starting point in Göstritz is being constructed in order to reduce the risk to the tunnel construction time for the Graßberg‐Schlagl fault system. During the construction phase, the contractor developed optimisations of the planned logistics concept for the intermediate access point in Göstritz, which led to a redesign of the shaft head cavern system. Shortly before the excavation of the shaft head cavern, an unexpected and geotechnically relevant fault zone was encountered in the access tunnel. In order to investigate the geological situation in the area of the shaft head, extensive additional investigation measures were carried out. Due to the updated geological forecast, the layout of the shaft head cavern and the support concept had to be changed. Thanks to the measures taken, the shaft head cavern system cold be successfully excavate without any damage to the support.
Im Baulos SBT1.1 des Semmering‐Basistunnels werden die eingleisigen Streckenröhren vom Portal in Gloggnitz und vom temporären Zwischenangriff in Göstritz aus aufgefahren. Der temporäre Zwischenangriff in Göstritz wird zur Risikominimierung hinsichtlich Bauzeit für die Vortriebe der Streckenröhren im Bereich des Graßberg‐Schlagl‐Störungssystems gebaut. Während der Ausführungsphase entwickelte der Auftragnehmer Optimierungen zum vorgesehenen Logistikkonzept für den Zwischenangriff in Göstritz. Dies hatte eine Umplanung des Schachtkopfkavernensystems zur Folge. Kurz vor dem Auffahren der Schachtkopfkavernen wurde eine nicht prognostizierte, geotechnisch relevante Störzone im Zugangstunnel angetroffen. Zur Erkundung der geologischen Situation im Bereich des Schachtkopfs wurden umfangreiche zusätzliche Erkundungsmaßnahmen durchgeführt. Aufgrund der aktualisierten geologischen Prognose musste das Layout der Schachtkopfkavernen sowie das Ausbaukonzept angepasst werden. Durch die getroffenen Maßnahmen konnte das Schachtkopfkavernensystem erfolgreich und ohne Schäden am Ausbau aufgefahren werden.
Semmering Base Tunnel – Design and construction of the shaft head caverns under difficult conditions
Semmering‐Basistunnel – Planung und Bau der Schachtkopfkavernen unter erschwerten Bedingungen
In contract SBT1.1 of the Semmering Base Tunnel, the single‐track main tunnels are being driven from the portal in Gloggnitz and from a temporary intermediate starting point in Göstritz. The temporary intermediate starting point in Göstritz is being constructed in order to reduce the risk to the tunnel construction time for the Graßberg‐Schlagl fault system. During the construction phase, the contractor developed optimisations of the planned logistics concept for the intermediate access point in Göstritz, which led to a redesign of the shaft head cavern system. Shortly before the excavation of the shaft head cavern, an unexpected and geotechnically relevant fault zone was encountered in the access tunnel. In order to investigate the geological situation in the area of the shaft head, extensive additional investigation measures were carried out. Due to the updated geological forecast, the layout of the shaft head cavern and the support concept had to be changed. Thanks to the measures taken, the shaft head cavern system cold be successfully excavate without any damage to the support.
Im Baulos SBT1.1 des Semmering‐Basistunnels werden die eingleisigen Streckenröhren vom Portal in Gloggnitz und vom temporären Zwischenangriff in Göstritz aus aufgefahren. Der temporäre Zwischenangriff in Göstritz wird zur Risikominimierung hinsichtlich Bauzeit für die Vortriebe der Streckenröhren im Bereich des Graßberg‐Schlagl‐Störungssystems gebaut. Während der Ausführungsphase entwickelte der Auftragnehmer Optimierungen zum vorgesehenen Logistikkonzept für den Zwischenangriff in Göstritz. Dies hatte eine Umplanung des Schachtkopfkavernensystems zur Folge. Kurz vor dem Auffahren der Schachtkopfkavernen wurde eine nicht prognostizierte, geotechnisch relevante Störzone im Zugangstunnel angetroffen. Zur Erkundung der geologischen Situation im Bereich des Schachtkopfs wurden umfangreiche zusätzliche Erkundungsmaßnahmen durchgeführt. Aufgrund der aktualisierten geologischen Prognose musste das Layout der Schachtkopfkavernen sowie das Ausbaukonzept angepasst werden. Durch die getroffenen Maßnahmen konnte das Schachtkopfkavernensystem erfolgreich und ohne Schäden am Ausbau aufgefahren werden.
Semmering Base Tunnel – Design and construction of the shaft head caverns under difficult conditions
Semmering‐Basistunnel – Planung und Bau der Schachtkopfkavernen unter erschwerten Bedingungen
Wieland, Gerd (author) / Prall, Karoline (author) / Lenz, Gerold (author) / Schachinger, Tobias (author) / Gobiet, Gerhard (author)
Geomechanics and Tunnelling ; 11 ; 462-470
2018-10-01
9 pages
Article (Journal)
Electronic Resource
German