Main tower steel bar construction method
The invention relates to a main tower steel bar construction method. The method comprises the steps that prefabricating a stiff framework truss structure; binding section steel bars of a main tower onthe stiff framework truss structure until all the section steel bars of the current section are bound to form a steel bar frame of the current section; adopting a tower crane to hoist the steel bar frame of the current section to a preset position; and aligning and connecting the steel bar frame of the current section and the installed steel bar frame of the previous section. According to the main tower steel bar construction method, construction is safer, the construction period is shortened, and the structure is more stable.
本申请涉及一种主塔钢筋的施工方法,所述方法包括步骤:预制劲性骨架桁架结构;在所述劲性骨架桁架结构上绑扎主塔的节段钢筋,直至绑扎完成当前节段的所有节段钢筋,形成当前节段的钢筋框架;塔式吊机吊装当前节段的钢筋框架至预设的位置;对位并连接当前节段的钢筋框架和已安装的上一节段的钢筋框架。本申请提供的主塔钢筋施工方法,施工更加安全,缩短了施工周期,结构更加稳固。
Main tower steel bar construction method
The invention relates to a main tower steel bar construction method. The method comprises the steps that prefabricating a stiff framework truss structure; binding section steel bars of a main tower onthe stiff framework truss structure until all the section steel bars of the current section are bound to form a steel bar frame of the current section; adopting a tower crane to hoist the steel bar frame of the current section to a preset position; and aligning and connecting the steel bar frame of the current section and the installed steel bar frame of the previous section. According to the main tower steel bar construction method, construction is safer, the construction period is shortened, and the structure is more stable.
本申请涉及一种主塔钢筋的施工方法,所述方法包括步骤:预制劲性骨架桁架结构;在所述劲性骨架桁架结构上绑扎主塔的节段钢筋,直至绑扎完成当前节段的所有节段钢筋,形成当前节段的钢筋框架;塔式吊机吊装当前节段的钢筋框架至预设的位置;对位并连接当前节段的钢筋框架和已安装的上一节段的钢筋框架。本申请提供的主塔钢筋施工方法,施工更加安全,缩短了施工周期,结构更加稳固。
Main tower steel bar construction method
一种主塔钢筋的施工方法
LI YONGBO (Autor:in) / HU JIABIN (Autor:in) / JIANG BENJUN (Autor:in) / SU ZIHAO (Autor:in) / WANG XINPING (Autor:in) / CHEN GANG (Autor:in) / WU JIE (Autor:in) / YU KUN (Autor:in) / GUO HUAN (Autor:in) / XU YE (Autor:in)
16.10.2020
Patent
Elektronische Ressource
Chinesisch
Automatic construction method for main tower steel bars
Europäisches Patentamt | 2023
|Integral binding construction method for main tower steel bars
Europäisches Patentamt | 2024
|Main tower top lifting system and main tower top lifting construction method
Europäisches Patentamt | 2023
|