Construction method of independent basement roof planting roof
The invention relates to a construction method of an independent basement roof planting roof. The construction method comprises the steps of S1, casting basement cross beam roofs in place; S2, laying a cement mortar leveling layer with the thickness of 20 mm; S3, constructing the 4.0-thickness SBS waterproof coiled material by adopting a pre-paving and full-sticking method; S4, constructing a puncture-resistant SBS waterproof coiled material; S5, performing a roof rain test; S6, fully paving a polyethylene film; S7, installing a phi 6 two-way 150 steel bar mesh; S8, pouring C20 shrinkage-compensating fine aggregate concrete; S9, dividing the grid seams by using a knife plate cutting machine, and filling the grid seams by using a polymer sealant; S10, installing a finished product drainage plate; S11, installing a 40-thickness polyvinyl chloride foam plastic water storage layer; S12, laying a layer of non-woven fabric; and S13, laying loose planting soil. According to the construction method, refined management and control key points are carried out on roof waterproof construction, precision control over the waterproof construction process is enhanced, and the roof planting construction quality is ensured.
本发明涉及一种独立地下室顶板种植屋面的建造方法,步骤一:现浇地下室井字梁顶板;步骤二:铺设20厚水泥砂浆找平层;步骤三:采用预铺满粘法施工4.0厚SBS防水卷材;步骤四:施工耐穿刺型SBS防水卷材;步骤五:进行屋面淋雨试验;步骤六:满铺聚乙烯薄膜;步骤七:安装Φ6双向@150钢筋网片;步骤八:浇筑C20补偿收缩细石混凝土;步骤九:用刀版切割机划分格缝并用高分子密封胶填缝;步骤十:安装成品排水版;步骤十一:安装40厚聚氯乙烯泡沫塑料蓄水层;步骤十二:铺设一层无纺布;步骤十三:铺设松散性种植土。本发明针对屋面防水施工进行精细化管理控制要点,加强防水施工过程的精度控制,确保屋面种植施工质量。
Construction method of independent basement roof planting roof
The invention relates to a construction method of an independent basement roof planting roof. The construction method comprises the steps of S1, casting basement cross beam roofs in place; S2, laying a cement mortar leveling layer with the thickness of 20 mm; S3, constructing the 4.0-thickness SBS waterproof coiled material by adopting a pre-paving and full-sticking method; S4, constructing a puncture-resistant SBS waterproof coiled material; S5, performing a roof rain test; S6, fully paving a polyethylene film; S7, installing a phi 6 two-way 150 steel bar mesh; S8, pouring C20 shrinkage-compensating fine aggregate concrete; S9, dividing the grid seams by using a knife plate cutting machine, and filling the grid seams by using a polymer sealant; S10, installing a finished product drainage plate; S11, installing a 40-thickness polyvinyl chloride foam plastic water storage layer; S12, laying a layer of non-woven fabric; and S13, laying loose planting soil. According to the construction method, refined management and control key points are carried out on roof waterproof construction, precision control over the waterproof construction process is enhanced, and the roof planting construction quality is ensured.
本发明涉及一种独立地下室顶板种植屋面的建造方法,步骤一:现浇地下室井字梁顶板;步骤二:铺设20厚水泥砂浆找平层;步骤三:采用预铺满粘法施工4.0厚SBS防水卷材;步骤四:施工耐穿刺型SBS防水卷材;步骤五:进行屋面淋雨试验;步骤六:满铺聚乙烯薄膜;步骤七:安装Φ6双向@150钢筋网片;步骤八:浇筑C20补偿收缩细石混凝土;步骤九:用刀版切割机划分格缝并用高分子密封胶填缝;步骤十:安装成品排水版;步骤十一:安装40厚聚氯乙烯泡沫塑料蓄水层;步骤十二:铺设一层无纺布;步骤十三:铺设松散性种植土。本发明针对屋面防水施工进行精细化管理控制要点,加强防水施工过程的精度控制,确保屋面种植施工质量。
Construction method of independent basement roof planting roof
独立地下室顶板种植屋面的建造方法
CHEN LIANJIAN (Autor:in) / GONG JIN (Autor:in) / HUANG YIFAN (Autor:in) / WU XIANGHUA (Autor:in) / ZHANG JIE (Autor:in) / FANG BIN (Autor:in) / WANG YONG (Autor:in)
20.04.2021
Patent
Elektronische Ressource
Chinesisch
Waterproof construction method for roof, basement exterior wall and basement roof
Europäisches Patentamt | 2021
|Basement roof construction hoist foundation construction method
Europäisches Patentamt | 2023
|