Slope support construction method combined with building main body structure
The invention provides a slope support construction method combined with a building main body structure. The method comprises the following steps of leveling a site, excavating a construction working surface of a bottom plate of a retaining wall, building the bottom plate, a wall body and a bearing platform of the retaining wall, carrying out primary backfilling, reserving a first platform on the wall top of the retaining wall, building a foundation pipe pile of a building main body structure, performing secondary backfilling, reserving a second platform, constructing a main body foundation pipe pile, a bearing platform and an overhead structure column of the platform, performing third backfilling, reserving a third platform, constructing a main body foundation pipe pile, a bearing platform and an overhead structure column of the platform, performing final backfilling, flattening, constructing main body foundation pipe piles and finishing slope support. By flexibly adopting a combined form of vertical support and step-slope support with different heights, the building main body structure is overhead for graded step-slope, so that the aims of reducing the vertical support height, reducing the risk of an ultrahigh retaining wall, reducing the earthwork backfilling amount and saving the construction cost are fulfilled.
本发明提供一种与建筑主体结构结合的边坡支护施工方法,包括以下步骤,平整场地,开挖挡土墙的底板的施工作业面,搭建挡土墙的底板、墙身和承台,进行第一次回填,在挡土墙的墙顶预留第一平台,搭建建筑主体结构的基础管桩,进行第二次回填,预留一个第二平台,施工此平台的主体基础管桩、承台及架空结构柱,进行第三次回填,预留一个第三平台,施工此平台的主体基础管桩、承台及架空结构柱,进行最后一次回填,并进行平整,对主体基础管桩进行施工,完成边坡支护,通过灵活采用不同高度的垂直支护加放坡支护的组合形式,利用建筑主体结构架空进行分级放坡,实现减小垂直支护高度,降低超高挡土墙风险,减少土方回填量,节省工程造价的目的。
Slope support construction method combined with building main body structure
The invention provides a slope support construction method combined with a building main body structure. The method comprises the following steps of leveling a site, excavating a construction working surface of a bottom plate of a retaining wall, building the bottom plate, a wall body and a bearing platform of the retaining wall, carrying out primary backfilling, reserving a first platform on the wall top of the retaining wall, building a foundation pipe pile of a building main body structure, performing secondary backfilling, reserving a second platform, constructing a main body foundation pipe pile, a bearing platform and an overhead structure column of the platform, performing third backfilling, reserving a third platform, constructing a main body foundation pipe pile, a bearing platform and an overhead structure column of the platform, performing final backfilling, flattening, constructing main body foundation pipe piles and finishing slope support. By flexibly adopting a combined form of vertical support and step-slope support with different heights, the building main body structure is overhead for graded step-slope, so that the aims of reducing the vertical support height, reducing the risk of an ultrahigh retaining wall, reducing the earthwork backfilling amount and saving the construction cost are fulfilled.
本发明提供一种与建筑主体结构结合的边坡支护施工方法,包括以下步骤,平整场地,开挖挡土墙的底板的施工作业面,搭建挡土墙的底板、墙身和承台,进行第一次回填,在挡土墙的墙顶预留第一平台,搭建建筑主体结构的基础管桩,进行第二次回填,预留一个第二平台,施工此平台的主体基础管桩、承台及架空结构柱,进行第三次回填,预留一个第三平台,施工此平台的主体基础管桩、承台及架空结构柱,进行最后一次回填,并进行平整,对主体基础管桩进行施工,完成边坡支护,通过灵活采用不同高度的垂直支护加放坡支护的组合形式,利用建筑主体结构架空进行分级放坡,实现减小垂直支护高度,降低超高挡土墙风险,减少土方回填量,节省工程造价的目的。
Slope support construction method combined with building main body structure
一种与建筑主体结构结合的边坡支护施工方法
HUANG ZIRONG (Autor:in) / ZHANG XIANGHONG (Autor:in) / WU LINMAO (Autor:in) / XU YUNKANG (Autor:in) / LIU SHUAI (Autor:in) / KE SHAONIAN (Autor:in)
21.09.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Structure for separating main body structure from retaining wall in slope building
Europäisches Patentamt | 2023
|Formwork structure for building main body structure construction
Europäisches Patentamt | 2021
|Fabricated wallboard for building main body structure construction
Europäisches Patentamt | 2021
|Formwork construction method for cantilever structure of building main body
Europäisches Patentamt | 2021
|