Tower column cross beam support overall lowering construction method
The invention relates to a tower column cross beam support overall lowering construction method which comprises the following steps: arranging hoisting equipment at the upper end of a cross beam, arranging a rope on the hoisting equipment, making the rope penetrate through the cross beam, and connecting the rope with a cross beam support at the lower end; hoisting the cross beam support by utilizing the hoisting equipment; cutting off corbels for supporting the cross beam support; and lowering the cross beam support to a working plane below by using the hoisting equipment. According to the tower column cross beam support overall lowering construction method, dismantling of the cross beam support is transferred to work on the working plane from aloft work, and the construction risk is greatly reduced.
本申请涉及一种塔柱横梁支架整体下放施工方法,其包括如下步骤:在横梁的上端设置吊取设备,在吊取设备上设置绳索,将该绳索穿过横梁,并与下端的横梁支架连接;利用吊取设备吊住横梁支架;割除支撑该横梁支架的牛腿;利用吊取设备下放横梁支架至下方的工作平面。该塔柱横梁支架整体下放施工方法将横梁支架的拆除从高空作业转移到工作平面作业,大大降低了施工风险。
Tower column cross beam support overall lowering construction method
The invention relates to a tower column cross beam support overall lowering construction method which comprises the following steps: arranging hoisting equipment at the upper end of a cross beam, arranging a rope on the hoisting equipment, making the rope penetrate through the cross beam, and connecting the rope with a cross beam support at the lower end; hoisting the cross beam support by utilizing the hoisting equipment; cutting off corbels for supporting the cross beam support; and lowering the cross beam support to a working plane below by using the hoisting equipment. According to the tower column cross beam support overall lowering construction method, dismantling of the cross beam support is transferred to work on the working plane from aloft work, and the construction risk is greatly reduced.
本申请涉及一种塔柱横梁支架整体下放施工方法,其包括如下步骤:在横梁的上端设置吊取设备,在吊取设备上设置绳索,将该绳索穿过横梁,并与下端的横梁支架连接;利用吊取设备吊住横梁支架;割除支撑该横梁支架的牛腿;利用吊取设备下放横梁支架至下方的工作平面。该塔柱横梁支架整体下放施工方法将横梁支架的拆除从高空作业转移到工作平面作业,大大降低了施工风险。
Tower column cross beam support overall lowering construction method
一种塔柱横梁支架整体下放施工方法
FAN ZHIFEI (Autor:in) / CHEN KAIQIAO (Autor:in) / LIU LIYUN (Autor:in) / TUO SHOUJIAN (Autor:in) / ZHU LIANGHONG (Autor:in) / LI YONGBO (Autor:in) / LI XIANWU (Autor:in) / CHAI QIANG (Autor:in) / SHEN GUOJUN (Autor:in) / DONG WENKE (Autor:in)
28.09.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Overall lowering and dismantling method for upper cross beam support of cable bent tower
Europäisches Patentamt | 2023
|Tower column cross beam support ground pre-pressing device and method
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2024
|