Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Method for synchronous construction of road base and inspection well
The invention discloses a method for synchronously construction of a road base and an inspection well. The method comprises the following steps: S1, manufacturing a reinforced concrete walling crib integrated plate template; S2, inspecting a well foundation and a well body; S3, paving a road bottom concrete layer; paving a road bottom layer, wherein the surface elevation of the road bottom layer is consistent with the outer edge elevation of the reinforced concrete walling crib integrated plate; S4, paving a road base concrete layer; and S5, paving a road surface concrete layer. The reinforced concrete walling crib integrated plate of an integrated structure is obtained by pouring concrete into the walling crib, the walling crib can be installed by installing the reinforced concrete walling crib integrated plate during construction, construction is simplified, the cost is reduced, inspection well construction and road base laying can be conducted synchronously, the construction efficiency is improved and the construction period is shortened.
本发明公开了一种道路基层与检查井同步施工的方法,包括如下步骤:S1制作钢筋混凝土井圈一体板模板;S2检查井基础和井身;S3铺设道路底层混凝土层;摊铺道路路底层,道路路底层的表面标高与钢筋混凝土井圈一体板的外缘标高一致;S4铺设道路基层混凝土层;S5铺设道路面层混凝土层。本发明通过对井圈浇筑混凝土得到一体式结构的钢筋混凝土井圈一体板,施工时通过安装钢筋混凝土井圈一体板即可实现对井圈的安装,有利于简化施工降低成本,能够与检查井施工和道路基层铺设同步进行,有利于提高施工效率缩短施工周期。
Method for synchronous construction of road base and inspection well
The invention discloses a method for synchronously construction of a road base and an inspection well. The method comprises the following steps: S1, manufacturing a reinforced concrete walling crib integrated plate template; S2, inspecting a well foundation and a well body; S3, paving a road bottom concrete layer; paving a road bottom layer, wherein the surface elevation of the road bottom layer is consistent with the outer edge elevation of the reinforced concrete walling crib integrated plate; S4, paving a road base concrete layer; and S5, paving a road surface concrete layer. The reinforced concrete walling crib integrated plate of an integrated structure is obtained by pouring concrete into the walling crib, the walling crib can be installed by installing the reinforced concrete walling crib integrated plate during construction, construction is simplified, the cost is reduced, inspection well construction and road base laying can be conducted synchronously, the construction efficiency is improved and the construction period is shortened.
本发明公开了一种道路基层与检查井同步施工的方法,包括如下步骤:S1制作钢筋混凝土井圈一体板模板;S2检查井基础和井身;S3铺设道路底层混凝土层;摊铺道路路底层,道路路底层的表面标高与钢筋混凝土井圈一体板的外缘标高一致;S4铺设道路基层混凝土层;S5铺设道路面层混凝土层。本发明通过对井圈浇筑混凝土得到一体式结构的钢筋混凝土井圈一体板,施工时通过安装钢筋混凝土井圈一体板即可实现对井圈的安装,有利于简化施工降低成本,能够与检查井施工和道路基层铺设同步进行,有利于提高施工效率缩短施工周期。
Method for synchronous construction of road base and inspection well
一种道路基层与检查井同步施工的方法
SHAO JIYOU (Autor:in) / YANG TIAN (Autor:in) / WANG HONGWEI (Autor:in) / FAN MING (Autor:in)
09.11.2021
Patent
Elektronische Ressource
Chinesisch
Multi-layer modular inspection well and road synchronous construction method
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2022
|Repairing construction method of road inspection well
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2020
|