Hub joint upside-down hanging structure mounting method
The invention discloses a hub joint upside-down hanging structure mounting method. The hub joint upside-down hanging structure mounting method comprises the following steps that (1), a scaffold is erected; (2), a joint angle adjusting frame is mounted for accurate in-position of hub joints; (3), a chord member angle adjusting frame is mounted to perform auxiliary supporting on chord members; (4), the chord members are connected with the hub joints; and (5), the whole hub joint upside-down hanging structure is mounted according to a regular sequence. Precise positioning of the hub joints in the mounting process is guaranteed through the joint angle adjusting frame, auxiliary supporting and positioning of the chord members are achieved through the chord member angle adjusting frame, precise positioning between the hub joints and the chord members is achieved through the two frame bodies, the overall bearing and stress performance of a mounted part is improved, in the whole mounting process, layer-by-layer mounting is carried out according to the sequence from top to bottom, in each layer, the chord members contained on one hub joint are firstly mounted, then the chord members on other hub joints on the same layer are mounted in sequence till mounting of the parts contained on the hub joints on the same layer is completed, and then mounting of the next layer is carried out.
本发明公开了一种毂节点倒挂结构安装方法,包括如下步骤:1)搭设脚手架;2)安装节点角度调节架进行毂节点的精准就位;3)安装弦杆角度调节架对弦杆进行辅助支撑;4)弦杆与毂节点连接;5)按规律顺序进行整个毂节点倒挂结构的安装。本发明中通过节点角度调节架确保节毂节点安装过程中的精准就位,而通过弦杆角度调节架实现对弦杆的辅助支撑定位,采用两个架体实现毂节点与弦杆之间的精准就位,提高安装后的构件整体承载受力性能,整个安装过程中,按照从上往下的顺序进行逐层安装,每一层中先进行一个毂节点上所含弦杆的安装,再依次进行同层的其他毂节点上弦杆的安装,直至完成同一层的毂节点所含构件的安装,再进行下一层的安装。
Hub joint upside-down hanging structure mounting method
The invention discloses a hub joint upside-down hanging structure mounting method. The hub joint upside-down hanging structure mounting method comprises the following steps that (1), a scaffold is erected; (2), a joint angle adjusting frame is mounted for accurate in-position of hub joints; (3), a chord member angle adjusting frame is mounted to perform auxiliary supporting on chord members; (4), the chord members are connected with the hub joints; and (5), the whole hub joint upside-down hanging structure is mounted according to a regular sequence. Precise positioning of the hub joints in the mounting process is guaranteed through the joint angle adjusting frame, auxiliary supporting and positioning of the chord members are achieved through the chord member angle adjusting frame, precise positioning between the hub joints and the chord members is achieved through the two frame bodies, the overall bearing and stress performance of a mounted part is improved, in the whole mounting process, layer-by-layer mounting is carried out according to the sequence from top to bottom, in each layer, the chord members contained on one hub joint are firstly mounted, then the chord members on other hub joints on the same layer are mounted in sequence till mounting of the parts contained on the hub joints on the same layer is completed, and then mounting of the next layer is carried out.
本发明公开了一种毂节点倒挂结构安装方法,包括如下步骤:1)搭设脚手架;2)安装节点角度调节架进行毂节点的精准就位;3)安装弦杆角度调节架对弦杆进行辅助支撑;4)弦杆与毂节点连接;5)按规律顺序进行整个毂节点倒挂结构的安装。本发明中通过节点角度调节架确保节毂节点安装过程中的精准就位,而通过弦杆角度调节架实现对弦杆的辅助支撑定位,采用两个架体实现毂节点与弦杆之间的精准就位,提高安装后的构件整体承载受力性能,整个安装过程中,按照从上往下的顺序进行逐层安装,每一层中先进行一个毂节点上所含弦杆的安装,再依次进行同层的其他毂节点上弦杆的安装,直至完成同一层的毂节点所含构件的安装,再进行下一层的安装。
Hub joint upside-down hanging structure mounting method
一种毂节点倒挂结构安装方法
SHEN HAIYING (Autor:in) / WU XIAOYU (Autor:in) / JIANG YONGYANG (Autor:in) / LI XIAOTIAN (Autor:in) / DAI JIALE (Autor:in) / WANG JING (Autor:in) / LU SIMIN (Autor:in)
19.11.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Upside-down hanging protective shed and mounting and dismounting method thereof
Europäisches Patentamt | 2021
|Elevator shaft upside-down mounting construction method
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2024
|