Pre-embedded column root slurry leakage prevention device and construction method thereof
The invention discloses a pre-embedded column root slurry leakage prevention device and a construction method thereof.The angle steel frame comprises first angle steel and second angle steel, the angle steel frame is composed of four pieces of angle steel, the first angle steel is arranged at one symmetrical position, the second angle steel is arranged at the other symmetrical position, and the first angle steel and the second angle steel are fixedly connected through welding; round holes are symmetrically formed in the second angle steel and the first angle steel; in the pouring construction process of the building concrete column, good slurry leakage prevention treatment can be conducted, conveying is easy, the effect is excellent, convenience is brought to follow-up construction of the building concrete column, and material waste is avoided; the leakage-proof device can be correspondingly regulated and controlled according to construction requirements in time, good construction flexibility is achieved, convenience is brought to workers, and then working efficiency and construction economic benefits are improved.
本发明公开了一种预埋式柱根部防漏浆装置及其施工方法,角钢架包含有第一角钢、第二角钢,并且角钢架由四个角钢组成,其中一对称位置设置有第一角钢,另一对称位置设置有第二角钢,第一角钢与第二角钢通过焊接固定连接,并且第二角钢与第一角钢上都对称设置有圆孔;在建筑混凝土柱进行浇筑施工过程中,能够进行很好的防漏浆处理,送简单,效果优良,给其后续施工带来便捷,避免材料的浪费,并且通过设置的连接杆件和定位组件、卡紧组件进行配合使用,对于防漏装置能够根据时施工需求进行相应的调控,具有很好的施工灵活性,给工作人员带来便利,进而提供工作效率和施工经济效益。
Pre-embedded column root slurry leakage prevention device and construction method thereof
The invention discloses a pre-embedded column root slurry leakage prevention device and a construction method thereof.The angle steel frame comprises first angle steel and second angle steel, the angle steel frame is composed of four pieces of angle steel, the first angle steel is arranged at one symmetrical position, the second angle steel is arranged at the other symmetrical position, and the first angle steel and the second angle steel are fixedly connected through welding; round holes are symmetrically formed in the second angle steel and the first angle steel; in the pouring construction process of the building concrete column, good slurry leakage prevention treatment can be conducted, conveying is easy, the effect is excellent, convenience is brought to follow-up construction of the building concrete column, and material waste is avoided; the leakage-proof device can be correspondingly regulated and controlled according to construction requirements in time, good construction flexibility is achieved, convenience is brought to workers, and then working efficiency and construction economic benefits are improved.
本发明公开了一种预埋式柱根部防漏浆装置及其施工方法,角钢架包含有第一角钢、第二角钢,并且角钢架由四个角钢组成,其中一对称位置设置有第一角钢,另一对称位置设置有第二角钢,第一角钢与第二角钢通过焊接固定连接,并且第二角钢与第一角钢上都对称设置有圆孔;在建筑混凝土柱进行浇筑施工过程中,能够进行很好的防漏浆处理,送简单,效果优良,给其后续施工带来便捷,避免材料的浪费,并且通过设置的连接杆件和定位组件、卡紧组件进行配合使用,对于防漏装置能够根据时施工需求进行相应的调控,具有很好的施工灵活性,给工作人员带来便利,进而提供工作效率和施工经济效益。
Pre-embedded column root slurry leakage prevention device and construction method thereof
一种预埋式柱根部防漏浆装置及其施工方法
YAN LEI (Autor:in) / DIAO WEI (Autor:in) / ZHONG HAORAN (Autor:in) / YAO YIFENG (Autor:in)
05.04.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2022
|Staggered wall column slab staggering and slurry leakage prevention construction method
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2024
|Concrete slurry leakage prevention device and construction method
Europäisches Patentamt | 2022
|Prefabricated laminated slab slurry leakage prevention device and construction method thereof
Europäisches Patentamt | 2023
|