Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction method for anti-hollowing and anti-cracking concrete leveling layer of industrial building floor
The invention discloses a construction method for an anti-hollowing and anti-cracking concrete leveling layer of an industrial building floor, which comprises the following steps of: carrying out construction treatment on a floor slab base layer to completely expose the concrete floor slab base layer; a leveling layer formwork is erected; setting a control network; watering to wet the concrete base layer; slurry sweeping: uniformly brushing a layer of cement slurry on the concrete base layer; c25 fine aggregate concrete is poured into the leveling layer formwork; light receiving; curing the concrete; dividing the grid joints; construction of expansion joints: filling the expansion joints with asphalt mortar; and protecting and transferring finished products. The method has the beneficial effects that the hollowing damage of the concrete leveling layer can be effectively prevented, and the cracking damage of the concrete leveling layer can be effectively controlled and prevented.
本发明公开了工业楼地面防空鼓抗裂混凝土找平层施工方法,包括如下步骤:楼板基层施工处理,完整露出混凝土楼板基层;支设找平层模板;设置控制网;洒水润湿混凝土基层;扫浆:混凝土基层均匀涂刷一层水泥浆;在找平层模板内浇筑C25细石混凝土;收光;养护混凝土;切分格缝;伸缩缝施工:伸缩缝采用沥青砂浆填充;成品保护并移交。本发明的有益效果为:本发明可有效预防混凝土找平层空鼓破损,又可有效控制并预防混凝土找平层开裂破损。
Construction method for anti-hollowing and anti-cracking concrete leveling layer of industrial building floor
The invention discloses a construction method for an anti-hollowing and anti-cracking concrete leveling layer of an industrial building floor, which comprises the following steps of: carrying out construction treatment on a floor slab base layer to completely expose the concrete floor slab base layer; a leveling layer formwork is erected; setting a control network; watering to wet the concrete base layer; slurry sweeping: uniformly brushing a layer of cement slurry on the concrete base layer; c25 fine aggregate concrete is poured into the leveling layer formwork; light receiving; curing the concrete; dividing the grid joints; construction of expansion joints: filling the expansion joints with asphalt mortar; and protecting and transferring finished products. The method has the beneficial effects that the hollowing damage of the concrete leveling layer can be effectively prevented, and the cracking damage of the concrete leveling layer can be effectively controlled and prevented.
本发明公开了工业楼地面防空鼓抗裂混凝土找平层施工方法,包括如下步骤:楼板基层施工处理,完整露出混凝土楼板基层;支设找平层模板;设置控制网;洒水润湿混凝土基层;扫浆:混凝土基层均匀涂刷一层水泥浆;在找平层模板内浇筑C25细石混凝土;收光;养护混凝土;切分格缝;伸缩缝施工:伸缩缝采用沥青砂浆填充;成品保护并移交。本发明的有益效果为:本发明可有效预防混凝土找平层空鼓破损,又可有效控制并预防混凝土找平层开裂破损。
Construction method for anti-hollowing and anti-cracking concrete leveling layer of industrial building floor
工业楼地面防空鼓抗裂混凝土找平层施工方法
FANG JIANXIN (Autor:in)
30.09.2022
Patent
Elektronische Ressource
Chinesisch
Hollowing-prevention cracking-prevention process of concrete floor leveling layer
Europäisches Patentamt | 2020
|Bridge engineering bridge floor leveling layer hollowing filling equipment and construction method
Europäisches Patentamt | 2021
|